CENTRAL MARKET

UPRERARegistered

CENTRAL MARKET is a RERA-registered commercial project by WEST WAY REALTY LLP in Gautam Budh Nagar (RERA ID UPRERAPRJ101301). Registered with a completion deadline of 27 Jan 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
100%Q3'25
100%Q4'25
100%Q1'26
100%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ101301
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 May 2023
Project duration57 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typePartnership Firm
Applicant addressGH-3, VAIBHAV KHAND, SHIPRA SUNCITY, GHAZIABAD, U.P.-201014
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    2023/01/07/8244

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion certificate filed

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered25 Apr 2023
Original completion27 Jan 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary24 Sept 2024
Registration fee₹67,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors232 · 1 · 5 (units from plan)
Homes · commercial units3 · 229 (shops and offices filed in the same plan)
  • SHOP229 99%
  • OTHER3 1%
ConfigurationUnitsCarpet area
SHOP2299-107
OTHER340-53
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · SHOP, OTHER52329-107
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 317.16 m² for a SHOP, 277.41 m² for a SHOP, 277.41 m² for a SHOP and 2 other units like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
AMIT KUMAR
License CA/98/22706
B-99, 1ST FLOOR, SECTOR-63, NOIDA
Engineer
GYAN SINGH
A-242, NEW FRIENDS COLONY, NEW DELHI-65
Contractor
MANOJ YADAV NIHAL
NIHAL BUILDWELL PRIVATE LIMITED, B-117, SECTOR-65, NOIDA-201301
Sr.Development work declared to RERA
1Demarcation of Plots
THE PROJECT LAND HAD BEEN DEMARKETED WITH BOUNDRY WALL TO THE EXACT SHAPE AND SIZE AS PER THE SITE PLAN SANCTIONED BY NOIDA AUTHORITY LOCATED AT PLOT NO.- C-01, SECTOR-120, NOIDA-201301
2Boundary Wall
2400 MM HIGH BOUNDRY WALL OF COMBINATION OF RCC COLUMN / BEAM WITH BRICK WORK.
3Road Work
MAIN ROAD EAST SIDE 30 MTRS WIDE AND NORTH SIDE 24 MTRS WIDE. ROAD WORK PROPOSED WITH TRIMIX CONCRETE FLOORING WITH PCC BASE
4Footpaths
FOOTPATHS IS PROPOSED WITH COMBINATION OF KERV STONE/ PAVERS ON COMPACTED SUB GRID WHICH WILL BE LASTING AND VISIBLE AT ALL CONDITIONS
5Water Supply Including Drinking Water Facilities
THE MAIN SOURCE OF DRINKING WATER WILL BE SUPPLY OF RO WATER AND STP TANKER FOR CONSTRUCTION.UNDER GROUND WATER 2 TANK FOR FIRE WATER 150 KLD EACH. RAW WATER 25KLD AND DOMESTIC WATER 25 KLD. OVERHEAD TANK FOR FIRE 10000 LTR, DOMESTIC WATER 25000 LTR , FLUSHING TANK 20000 LTR AND SOFT WATER TANK 10000 LTRS.
6Sewer System
80 KLD CAPACITY S.T.P WILL BE CONSTRUCTED AT SITE AND THE SOIL AND WASTE SHALL BE CARRIED DOWN IN SEPARATE INDIPENDTLY VENTED PIPES, TOW PIPE, DRAINAGE SYSTEM SHALL BE ADOPTED AS PER ASPE STANDARD.
7Drain
SEPARATE DRAIN AND INDIPENDT RAIN WATER DRAINAGE SYSTEM SHALL BE PROVIDED FOR COLLECTING RAIN WATER FROM TARRACE , PAVED AREA, LAWN AND ROADS AND WILL ROUTE TO RECHARGE PITS.
8Parks
AS PER APPROVED MAP LANDSCAPE AREA IS 25 PERCENT OF OPEN AREA . PROPOSED 450.464 SQMTR AREA FOR LANDSCAPING GREEN PARKS AND TREES ATTCHED SANCTION PLAN.
9Tree Planting
THE TREE PLANTATION IN OUR PROJECT WILL BE DONE AS PER SANCTION PLAN APPROVED BY NOIDA AUTHORITY. 20 TREES REQUIRED AND PROPOSED AS PER ATTACHED SANCTION DRAWING.
10Design For Electric Supply Including Street Lighting
11 KVA INCOMING SUPPLY FROM UPPCL SHALL BE OBTAINED AND AFTER CONVERSION IT INTO 440V SUPLLY SHALL BE FEED TO THE ENTIRE SYSTEM. THE SWITCHS WITH TIMER CONTROL FOR STREET LIGHTS SHALL BE PROVIDED THE LUX LEVEL SHALL BE MEET AS PER NBC 2016 GUIDELINES.
11Community Buildings
THE PROVISION OF COMMUNITY BUILDING IS NOT APPLICABLE BY SANCTION PLAN AS APPROVED BY NOIDA AUTHORITY.
12Treatment and Disposal System of Sewage and Sullage water
THE PROVISION OF SEWAGE TREATEMENT PLANT FOR TREATEMENT OF SEWAGE AND SULLAGE WET, THE PLANT SHALL COMPRISE OF PRIMARY AND SECONDARY CHEMICAL AND BIOLOGICAL TERTIARY TREATMENT PLANT.
13Solid Waste Management And Disposal System
THE PROVISION OF SOLID WASTE MANAGEMENT AND DISPOSAL SYSTEM WILL AS PER APPLICABLE NORMS .
14Water Conservation System
THE PROVISION OF RAIN WATER HARVESTING WILL BE DONE AS PER APPLICABLE NORMS.
15Energy Management System Including Use of Renewable Energy
LESS OR NON MOVEMENT AREA ,SENSOR SHALL BE PROVIDED . HYBRIDGE SOLAR SYSTEM SHALL BE PROVIDED AS RENEWABLE ENERGY. IT WILL BE SYNCHRONISING WITH MAIN SUPPLY.
16Fire Protection And Fire Safety System
AS PER ATTACHED FIRE NOC UPFS/2023/71834/GBN/GAUTAMBUDDH NAGAR/19575/DD ON DOCUMENTS ,FIRE PROTECTION AND FIRE SAFTY EQUIPMENTS AND SYSTEM WILL BE PROVIDED IN ACCORDANCE WITH THE FIRE SAFTY NORMS AND NBC2016.
17Social Infrastructure And Other Public Amenities Including Public Health Services
SOCIAL INRASTRUCTURE AND OTHER PUBLIC AMENITIES INCLUDING PUBLIC HEATH SERVICES WILL BE PROVIDED AS PER NORMS OF CONSERN AUTHORITIES.
18Emergency Evacuation Services
EMERGENCY EVACUATION SERVICES WILL BE PROVIDED AS PER SAFTY NORMS OF NBC 2016.
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1WEST WAY REALTY SERVICES PRIVATE LIMITEDUPRERAAGT21913
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 27 Jan 2028.

Sanctioned by Noida Authority · 5,700 sqm of land · an approved plan of 1 block and 232 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
2023/01/07/824428 Jan 202327 Jan 202827 Jan 203127 Jan 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
C-01, SECTOR-1205700Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 202300743002719
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New6 Feb 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New22 Mar 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New22 Mar 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New6 Feb 2023 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New8 Apr 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New6 Feb 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New6 Feb 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New6 Feb 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New6 Feb 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Feb 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Feb 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New7 Feb 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Feb 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New6 Feb 2023 ↗

Quarterly progress reports

13 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

13 quarterly progress reports are on file with UPRERA, covering 2023-Q1 to 2026-Q1.

QuarterConstructionCertificates
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q2100%CA ↗ · Arch ↗ · Eng ↗
2025-Q3100%CA ↗ · Arch ↗ · Eng ↗
2025-Q4100%CA ↗ · Arch ↗ · Eng ↗
2026-Q1100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameWEST WAY REALTY LLP
RolePromoter · current
RERA IDUPRERAPRM212853
PANAAEFW3449B
CIN / TANMRTW01475F
Registered addressGH-3, VAIBHAV KHAND, SHIPRA SUNCITY, GHAZIABAD, U.P.-201014
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
WEST WAY REALTY LLP COLLECTION ACCOUNT FOR CENTRAL MARKETBankAXIS BANKBranchSECTOR-62, NOIDABranch addressGF, OFFICE NO.01, TOWER-A, LOBE-05, THE CORENTHUM, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0000723
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
WEST WAY REALTY LLP SEPARATE ACCOUNT FOR CENTRAL MARKETBankAXIS BANKBranchSECTOR-62, NOIDABranch addressGF, OFFICE NO.1, TOWER-A, LOBE-05, THE CORENTHUM, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0000723
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
WEST WAY REALTY LLP RERA TRANSACTION ACCOUNT FOR CENTRAL MARKETBankAXIS BANKBranchSECTOR-62, NOIDABranch addressGF, OFFICE NO.1 , TOWER-A, LOBE-05, THE CORENTHUM, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0000723
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about CENTRAL MARKET

Is CENTRAL MARKET RERA registered?

Yes. CENTRAL MARKET is registered with UPRERA under registration number UPRERAPRJ101301, registered on 25 Apr 2023. Estanzo reproduces that filing; it does not verify the work behind it.

Has CENTRAL MARKET been completed?

UPRERA still lists CENTRAL MARKET as Registered, so it is not shown as completed here. A completion certificate dated 24 Sept 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of CENTRAL MARKET?

WEST WAY REALTY LLP is the promoter entity that filed CENTRAL MARKET with UPRERA (promoter RERA ID UPRERAPRM212853). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does CENTRAL MARKET have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is CENTRAL MARKET located?

CENTRAL MARKET is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in CENTRAL MARKET?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in CENTRAL MARKET?

The approved unit plan filed with UPRERA runs from 9 to 107 m² of carpet area (about 97 to 1,156 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in CENTRAL MARKET?

The approved unit plan describes 1 block and 232 units of which 3 are homes and 229 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is CENTRAL MARKET?

About 165 units per acre: 232 planned units across 1.41 acres (5,700 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗