RG Mirage Tower L is a RERA-registered residential project by RG Residency Private Limited in Gautam Budh Nagar (RERA ID UPRERAPRJ766232). Registered with a completion deadline of 30 Jun 2026.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ766232 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Noida Authority |
| Proposed start | 1 Jan 2022 |
| Project duration | 54 months |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| Tehsil | Gautam Buddha Nagar |
| Applicant type | Company |
| Applicant address | Registered Office Address - G-05, Ground Floor, Plot No. SU LSC B-Block RG City Centre, Lawrence Road, Delhi North West DL-110035 Corporate Office Address - G-05, Ground Floor, Plot No. SU LSC B-Block RG City Centre, Lawrence Road, Delhi North West DL-110035 Site Address - GH-02, Sector 120, NOIDA, GUTAM BUDDHA NAGAR, UTTAR PRADESH PIN- 201301 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
NOIDA/M.V.N./2019/III-206/1136
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 14 Jan 2022 |
| Original completion | 30 Jun 2026 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹30,500 |
| Sanctioning authority | Noida Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK132 72%
- 4 BHK52 28%
| Configuration | Units | Carpet area |
|---|---|---|
| 3 BHK | 132 | 113-117 |
| 4 BHK | 52 | 151-151 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| TOWER-L · 3 BHK, 4 BHK, OTHER | 29 | 184 | 113-151 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Plot No. GH-02, Sector 120, Noida demarcation had been done by Noida Development Authority. |
| 2 | Boundary Wall Yes, Masonry Pucca and Railing Boundary Wall. |
| 3 | Road Work Yes, RCC Trimix Road with Kerb Stone on sides and Stone Paving in front of Towers. |
| 4 | Footpaths Yes, Footpaths will be constructed using interlocking / Paver as per Sanctioned Plans. |
| 5 | Water Supply Including Drinking Water Facilities Yes, Water Supply from Authority further water to be collected in under Ground Water Reservoirs and Terrace Tanks, equipped with Hydro Pneumatic Pumps with GI rings and risers. |
| 6 | Sewer System Proper sewerage will be constructed using R.C.C / UPVC pipes as per drawings and will be treated with STP.STP treated water will be used as mentioned above and residual will be disposed of in government sewerage system. |
| 7 | Drain Draining system will be constructed using R.C.C. / UPVC pipes as per drawings. |
| 8 | Parks Yes, Beautiful Landscape with Civil Work with Masonry and Stone, Horticulture Work and various types of Plantation. |
| 9 | Tree Planting Sufficient No. of trees as per Sanctioned Layout will be planted in the project. Beautiful landscape with civil work with masonry and stone, horticulture work and various types of plantation , shrubs , trees are to be planted out of that 50 percent will be evergreen tree. |
| 10 | Design For Electric Supply Including Street Lighting HT electrical supply will be made by competent authority, a sub station will be set-up in project as per drawings and LT electrical supply will be available for individual unit(s). Sufficient power back-up arrangement will be made using DG Sets. Street Lighting will be done using LT supply / power back-up. |
| 11 | Community Buildings Yes, with Banquet, Gym , Indoor Games, facilities at 27th and 28th Floor lvl. |
| 12 | Treatment and Disposal System of Sewage and Sullage water Sewerage Treatment Plant will be installed / constructed as per approved drawings. All sewerage will be treated and treated water will be available for gardening and flushing and residual of sewerage treatment plant will be drained in government sewer system. |
| 13 | Solid Waste Management And Disposal System Yes , Solid Waste will be collected manually and disposal will be done as per norms. |
| 14 | Water Conservation System Water conservation will be done by rain water harvesting system and through Sewerage Treatment Plant(STP). |
| 15 | Energy Management System Including Use of Renewable Energy Good quality and approved brand equipment will be used in sub station to minimize energy loss and Solar Energy System will be installed as per norms and approved drawings. |
| 16 | Fire Protection And Fire Safety System Diesel Pump - 1 No. 2850 lpm and 150 lpm head, Electrical Pump for Hydrant - 1 No. 2850 lpm and 150 m head, Electrical Pump for Sprinkler- 1 No. 2850 lpm and 150 m head , Jockey Pumps - 2 Nos 180 lpm and 150m head, Basement internal External hydrants sprinklers. Fire tender path shall be provided as per NBC. Fire fighting systems along with pumps and UGT of Fire tank capacity (200) KL (common) and OHT of Fire tank capacity 10 KL (each block) shall be provided as per NBC and NOC from fire Department. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Proper Water Supply and Sanitary facilities on Ground Floor of Every Tower. |
| 18 | Emergency Evacuation Services Yes, Refuge area provided at Every Towers on 18th ,21st 24th Floor in addition to Main and Fire Staircase. Staircase shall be provided in Basement and all the Towers for fire / emergency exit as per NBC. |
| 19 | Other Miscellaneous Work Proper security system including Security Guard ,CCTV Cameras and controlled access will be made available |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 6 Aug 2024.
Sanctioned by Noida Authority · 5,034 sqm of land · an approved plan of 1 block and 184 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| NOIDA/M.V.N./2019/III-206/1136 | 7 Aug 2019 | 6 Aug 2024 | 6 Aug 2029 | 30 Jun 2026 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
18 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| GH-02, Sector 120, Noida, Gautam Buddha Nagar, Uttar Pradesh | 51067 | Plot |
| Lease deed · 2152 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Allotment letter from the authority · Noida/GHP/GH-2009-(VI)/2009/4604 The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Allotment letter from the authority · Affidavit The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Allotment letter from the authority · Reply of Objection Letter RG Mirage Tower L Project The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Allotment letter from the authority · Reply Letter of RG Mirage Tower L The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | not reported | — |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 29 Jan 2022 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 20 Dec 2021 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 20 Dec 2021 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 20 Dec 2021 ↗ |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | New | 3 Dec 2021 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 3 Dec 2021 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 3 Dec 2021 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 3 Dec 2021 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 20 Dec 2021 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 3 Dec 2021 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 4 Dec 2021 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 3 Dec 2021 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 3 Dec 2021 ↗ |
Quarterly progress reports
18 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
18 quarterly progress reports are on file with UPRERA, covering 2021-Q4 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 17% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 16% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 29.32% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 35.62% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | RG Residency Private Limited |
| Role | Promoter · current |
| RERA ID | UPRERAPRM154195 |
| PAN | AAECR5932M |
| CIN / TAN | DELR17700E |
| Name of chairman | Rajesh Goyal |
| Registered address | Registered Office Address - G-05, Ground Floor, Plot No. SU LSC B-Block RG City Centre, Lawrence Road, Delhi North West DL-110035 Corporate Office Address - G-05, Ground Floor, Plot No. SU LSC B-Block RG City Centre, Lawrence Road, Delhi North West DL-110035 Site Address - GH-02, Sector 120, NOIDA, GUTAM BUDDHA NAGAR, UTTAR PRADESH PIN- 201301 |
| RERA contact | |
| Registered since | 2021 |
Nearby projects
Gautam Budh Nagar
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | RG Residency Pvt. Ltd. Collection Account for RG Mirage Tower LBankHDFC Bank Ltd.BranchSector 110, NOIDABranch addressPlot No. 1, Block A-2, Commercial Complex, Sector 110, NOIDA, Distt. Gautam Buddha Nagar,Uttar Pradesh, PIN-201304A/C no.IFSCHDFC0000930 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | RG Residency Pvt. Ltd. Separate Bank Account for RG Mirage Tower LBankHDFC Bank Ltd.BranchSector 110, NOIDABranch addressPlot No.1, Block A-2, Commercial Complex, Sector 110, NOIDA, Distt. Gautam Buddha Nagar, Uttar Pradesh, PIN- 201304Branch districtGautam Buddha NagarA/C no.IFSCHDFC0000930 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | RG Residency Pvt. Ltd. RERA Transaction Account for RG Mirage Tower LBankHDFC Bank Ltd.BranchSector 110, NOIDABranch addressPlot No. 1, Block A-2, Commercial Complex, Sector 110, NOIDA, Distt. Gautam Buddha Nagar, Uttar Pradesh, PIN-201304Branch districtGautam Buddha NagarA/C no.IFSCHDFC0000930 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about RG Mirage Tower L
Is RG Mirage Tower L RERA registered?
Yes. RG Mirage Tower L is registered with UPRERA under registration number UPRERAPRJ766232, registered on 14 Jan 2022. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for RG Mirage Tower L?
The completion date filed with UPRERA is 30 Jun 2026. No completion certificate is on record yet.
Who is the builder of RG Mirage Tower L?
RG Residency Private Limited is the promoter entity that filed RG Mirage Tower L with UPRERA (promoter RERA ID UPRERAPRM154195). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does RG Mirage Tower L have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is RG Mirage Tower L located?
RG Mirage Tower L is registered in Gautam Budh Nagar, as filed with UPRERA.
What configurations are available in RG Mirage Tower L?
The unit plan filed with UPRERA lists 3 BHK, 4 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in RG Mirage Tower L?
The approved unit plan filed with UPRERA runs from 113 to 151 m² of carpet area (about 1,218 to 1,629 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in RG Mirage Tower L?
The approved unit plan describes 1 block and 184 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is RG Mirage Tower L?
About 148 units per acre: 184 planned units across 1.24 acres (5,034 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗