Timeline Bar

Registered11 Aug 2017
Promised31 Mar 2020
Today3 Aug 2026

Timeline

Promised completion31 Mar 2020
Revised completion31 Mar 2020
Actual completion
Possession delay76 mo delay

Registration & Cost Details

Registration fee (in ₹)₹50,000
Project cost (in ₹ Lakhs)₹2,000 Lakhs
Project duration44 months
Project categoryCommercial
Locality
Original start date31 Jan 2017
Proposed start date31 Jan 2017

Inventory

Total units170
Unit TypeUnitsCarpet Area (sqm)
SHOP16312.35–165.71
OTHER718.05–197.4

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile7838191977
Emailk.bharat@bccinfra.com
Coordinator7838191972
AddressB-14, Phase-1, Vivek Vihar, Delhi-110095

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
87/Zone8/2014-153 Jan 20152 Jan 202031 Mar 20201 Jan 2023

Land Parcels

Khasra No.AreaPlot Type
24845
32290
331100
341242
441000
24845Khasra
32290Khasra
441000Khasra
341242Khasra
331100Khasra

Approved Unit Plan

Unit plan rows on file43
Total flats (sum of rows)170
Total shops163
BlocksCOMMERCIAL
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
452731 May 2010
418221 May 2010
203721 Mar 2010
52659 Jun 2008

Frequently Asked Questions

What is the RERA registration number of Central Walk?

The RERA registration number of Central Walk is UPRERAPRJ6208, as recorded on the UP-RERA portal.

What is the RERA status of Central Walk?

As reported by UP-RERA, the status of Central Walk is "Registered".

Where is Central Walk located?

As reported to UP-RERA, Central Walk is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will Central Walk be completed?

The latest completion date reported to UP-RERA for Central Walk is 31 Mar 2020.

Is Central Walk delayed?

Measured against the latest completion date reported to UP-RERA, Central Walk is 76 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026