DELHI-99 is a RERA-registered real-estate project in Ghaziabad (RERA ID UPRERAPRJ5845). Its RERA-registered completion deadline (29 Mar 2022) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ5845 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 23 Mar 2013 |
| Original start | 23 Mar 2013 |
| Project duration | 109 |
| Address | Ghaziabad, Ghaziabad |
| RERA registered | 31 Jul 2017 |
| Promised completion | 31 Dec 2019 |
| Revised completion | 29 Mar 2022 |
| Completion certificate filed | 25 Dec 2024 |
| Registration fee | ₹1,71,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 545 | 50–70 |
| 3 BHK | 428 | 57–96 |
| 4 BHK | 39 | 108–110 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 230/ZONE-8/GH/13-14 | 5 Apr 2014 | 4 Apr 2019 | 31 Dec 2019 |
| 230/ZONE-8/GH/13-14 | 27 Mar 2018 | 26 Mar 2023 | 29 Mar 2022 |
| Khasra | Area | Type |
|---|---|---|
| Kh. No. 2117M Village Beheta Hajipur, Ghaziabad U. | 110 SQ.MT. | — |
| Kh. No. 2116M Village Beheta Hajipur, Ghaziabad | 6890 SQ.MT. | — |
| Kh. No. 2054M Village Beheta Hajipur, Ghaziabad | 3746 SQ.MT. | — |
| Kh. No. 2049 Village Beheta Hajipur, Ghaziabad | 894 SQ.MT. | — |
| Kh. No. 2108 Village Beheta Hajipur, Ghaziabad | 6022 SQ.MT. | — |
| Kh. No. 2115M Village Beheta Hajipur, Ghaziabad | 1206.33 SQ.MT. | — |
| Kh. No. 2055M Village Beheta Hajipur, Ghaziabad | 2842.70 SQ.MT. | — |
| Kh. No. 2056M Village Beheta Hajipur, Ghaziabad | 2258 SQ.MT. | — |
| Kh. No. 2109M Village Beheta Hajipur, Ghaziabad | 1896 SQ.MT. | — |
| Kh. No. 2114M Village Beheta Hajipur, Ghaziabad | 2292.74 SQ.MT. | — |
| Kh. No. 2110MVillage Beheta Hajipur, Ghaziabad | 700 SQ.MT. | — |
| Kh. No. 2107M Village Beheta Hajipur, Ghaziabad | 4327.84 SQ.MT. | — |
| 2115/2049/2108/2116/2117/2055/2056/2114/2057/2063 | 37389 | Khasra |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 22910 (KH. NO.2049, 2054,2108,2116,2117 | 29 Sept 2011 | — | — |
| 22910 (KH. NO.2049, 2054,2108,2116,2117 | 29 Sept 2011 | — | — |
| 22918 (KH. NO.2115M) | 29 Sept 2011 | — | — |
| 22904 (KH. NO.2107M) | 29 Sept 2011 | — | — |
| 18228 (KH. NO.2055M) | 17 May 2012 | — | — |
| 9420 (KH. NO.2109M) | 4 Mar 2013 | — | — |
| 9429 (KH. NO.2114M) | 4 Mar 2013 | — | — |
| 19926 (KH.NO.2056M) | 29 May 2012 | — | — |
| 17838 (KH. NO.2110M) | 29 Apr 2013 | — | — |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | CA · Arch · Eng | view ↗ |
| 2020-Q2 | — | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | Eng | view ↗ |
| 2021-Q2 | — | Eng | view ↗ |
| 2021-Q3 | — | Arch · Eng | view ↗ |
| 2021-Q4 | — | Arch · Eng | view ↗ |
Other projects registered in Ghaziabad.
Yes. DELHI-99 is registered with UPRERA under registration number UPRERAPRJ5845, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.
UPRERA still lists DELHI-99 as Registered, so it is not shown as completed here. A completion certificate dated 25 Dec 2024 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
DELHI-99 is registered in Ghaziabad, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗