CHANDA GREENS RESIDENCY-1

UPRERARegistered

CHANDA GREENS RESIDENCY-1 is a RERA-registered residential project by Madhav Developers in MATHURA (RERA ID UPRERAPRJ386200). Registered with a completion deadline of 5 Feb 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
65%Q3'25
75%Q4'25
85%Q1'26
86.98%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ386200
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMathura-Vrindavan Development Authority
Proposed start1 Mar 2024
Project duration60 months
AddressKHASRA NO. 18, 20 & 23, MAUZA BAKALPUR, MATHURA, MATHURA, Mathura, Mathura
TehsilMathura
Applicant typePartnership Firm
Applicant addressG-23, KAUSHIKI TOWER, OPPOSITE ROADWAY WORKSHOP, BADRI NAGAR, MATHURA, U.P.
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MVDA/LD/23-24/0139

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered2 May 2024
Original completion5 Feb 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,35,000
Sanctioning authorityMathura-Vrindavan Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Kanchana Agrawal
License CA/2016/78675
House No.4, Brij Enclave, Brij Nagar, Mathura, Uttar Pradesh
Engineer
Shiv Kumar Mishra
Block No. C-9, Shop No. F-11, 12 Cloth Market, Sanajay Place, Agra, Uttar Pradesh
Contractor
Shokat Ali
Village and Post Khamini, Goverdhan Road, Mathura, Uttar Pradesh
Sr.Development work declared to RERA
1Demarcation of Plots
Residential Plots of different sizes for public and semi public plots as approved by the authorities and demarcated on approved map and accordingly the demarcation will be done on the site.
2Boundary Wall
It will be the responsibility of the developer to construct the boundary wall around the whole society. No boundary walls is being provided by the developer for the individual plots that boundary wall will be constructed by the buyers.
3Road Work
Approach road to the site has been paved by MVDA, Demarcation of internal road and earth work on the roads has been done, We propose to develop internal roads with 80MM Interlocking concrete pavers.
4Footpaths
All main artery roads and sub-artery roads will have footpaths in the shoulders and these footpaths will be finished with the material which will allow rain water percolation into the soil below.
5Water Supply Including Drinking Water Facilities
An underground tank of 50KL capacity and 200 KL overhead tank has already been built at the site. Drawings of pipelines for water supply and sewerage are being prepared by the consultant, the work for same shall be initiated shortly.
6Sewer System
Sub-mains with provision to link the disposal to each and every plot through chambers/ manholes will be laid in front of all the plots and these sub-mains will be connected to the manholes of trunk mains laid in the service corridors of the arterial and sub-arterial roads. The trunk mains will ultimately terminate into the STP where the sewerage will be treated.
7Drain
Rainwater harvesting pits provided at different locations as per the designs, and overflow of rainwater harvesting pits will be connected to the external drainage network. The external drainage network will be provided to carry the road and plot run-offs and finally disposed off into the natural strom drains.
8Parks
Park and all green areas have been demarcated. Boundary wall work on parks has been initiated. Actual horticulture work shall be started after completion of civil work.
9Tree Planting
Trees of different species will be planted on the periphery of the site and along roads, Big leaf trees will also be provided on the periphery.
10Design For Electric Supply Including Street Lighting
As per the norms of UPPCL, the 11 KVA line till site has been erected and made functional by DVVNL. Drawings for internal electrification has been received, will be submitted to DVVNL for their approval and estimated preparation.
11Community Buildings
Not Applicable.
12Treatment and Disposal System of Sewage and Sullage water
As explained above the sewerage and sullage water will be treated in STPs PHYTORID technology STP is processed in the township.
13Solid Waste Management And Disposal System
Door to door collection of said solid waste arrangement will be made in the township through the maintenance agency which will be assigned maintenance of the society, besides this garbage bins and collection points have been proposed in the township. A tie up with the local municipality for organizing solid waste disposal of this township.
14Water Conservation System
Rainwater harvesting pits number and size based on the design at different locations will be provided in the township and only the overflow of these pits will be drained into natural nalahs.
15Energy Management System Including Use of Renewable Energy
No Provision has been made for any renewable Energy Equipment as per size of Project.
16Fire Protection And Fire Safety System
Not Applicable
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
Not Applicable
19Other Miscellaneous Work
The township is being developed with reasonably sized greens.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 5 Feb 2029.

Sanctioned by Mathura-Vrindavan Development Authority · 25,958 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MVDA/LD/23-24/01396 Feb 20245 Feb 20295 Feb 20305 Feb 2029
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

21 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
2011200Khasra
183800Khasra
2310958Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 6471
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7979
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 9071
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New26 Mar 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New2 Mar 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New11 Apr 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New2 Mar 2024 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New2 Mar 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New27 Mar 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New27 Mar 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New2 Mar 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New2 Mar 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New26 Mar 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New23 Mar 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New2 Mar 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New2 Mar 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New11 Apr 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New11 Apr 2024 ↗

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2023-Q4 to 2026-Q2.

QuarterConstructionCertificates
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q265%CA ↗ · Arch ↗ · Eng ↗
2025-Q375%CA ↗ · Arch ↗ · Eng ↗
2025-Q485%CA ↗ · Arch ↗ · Eng ↗
2026-Q186.98%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMadhav Developers
RolePromoter · current
RERA IDUPRERAPRM279387
PANABVFM3024A
CIN / TANAGRM15056G
Registered addressG-23, KAUSHIKI TOWER, OPPOSITE ROADWAY WORKSHOP, BADRI NAGAR, MATHURA, U.P.
RERA contact
Registered since2024
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameMadhav Properties Limited
RoleCo-promoter · current
RERA IDUPRERAPRM196018
Applicant typeCompany
PANAAACM0779M
CIN / TANU70101DL1988PLC030881
Name of chairmanKRISHNA DAYAL AGARWAL
Registered addressC-281EAST END APARTMENTNEAR NEW ASHOK NAGAR ] NEW DELHI DL 110096 IN
RERA contact
Registered since2022

Nearby projects

Mathura

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
MADHAV DEVELOPERS COLLECTION ACCOUNT FOR CHANDA GREENS RESIDENCY -1BankAXIS BANK LTDBranchGOVERDHAN CHOWKBranch addressGROUND FLOOR, PLOT NO. 215/80/44, PANNA PALACE, GOVERDHAN ROAD, KRISHNA NAGAR, MATHURA, U.P. -281004Branch districtMathuraA/C no.IFSCUTIB0002801Branch emailBRHD2801@AXISBANK.COM
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Madhav Developers Separate Account for Chanda Greens Residency -1BankAxis Bank LtdBranchGoverdhan ChowkBranch addressGround Floor, Plot No. 215/80/44, Panna Palace, Goverdhan Road, Krishna Nagar, Mathura, U.P. -281004Branch districtMathura, Uttar PradeshA/C no.IFSCUTIB0002801
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Madhav Developers Transaction Account for Chanda Greens Residency -1BankAxis Bank LtdBranchGoverdhan ChowkBranch addressGround Floor, Plot No. 215/80/44, Panna Palace, Goverdhan Road, Krishna Nagar, Mathura, U.P. -281004Branch districtMathura, Uttar PradeshA/C no.IFSCUTIB0002801
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about CHANDA GREENS RESIDENCY-1

Is CHANDA GREENS RESIDENCY-1 RERA registered?

Yes. CHANDA GREENS RESIDENCY-1 is registered with UPRERA under registration number UPRERAPRJ386200, registered on 2 May 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for CHANDA GREENS RESIDENCY-1?

The completion date filed with UPRERA is 5 Feb 2029. No completion certificate is on record yet.

Who is the builder of CHANDA GREENS RESIDENCY-1?

Madhav Developers is the promoter entity that filed CHANDA GREENS RESIDENCY-1 with UPRERA (promoter RERA ID UPRERAPRM279387). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does CHANDA GREENS RESIDENCY-1 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is CHANDA GREENS RESIDENCY-1 located?

CHANDA GREENS RESIDENCY-1 is registered in MATHURA, Mathura, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗