Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'25
31.47%Q3'25
49.1%Q4'25
67.8%Q1'26
95%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ569226
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryPrayagraj(Allahabad) Development Authority
Proposed start21 Apr 2025
Project duration60 months
AddressPART OF ARAZI NO 878, MAUJA- ANDAWA, PARGANA-JHUNSI, ANDAWA, Phulpur, Prayagraj
TehsilPhulpur
Applicant typeCompany
Applicant address14 IBRAHIMPUR, MAZRA KATKA, JHUNSI, NEAR INDIAN OIL TRIVENIPURAM, ALLAHABAD
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Plotted Resi development/Plotted Housing/04710/PDA/LD/24-25/1129/24022025

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion certificate filed

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered3 Jun 2025
Original completion20 Apr 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary3 Oct 2026
Registration fee₹46,000
Sanctioning authorityPrayagraj(Allahabad) Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
SINGH AND ASSOCIATES
License CA/2011/51859
139A, ALLENGANJ, PRAYAGRAJ
Engineer
SINGH AND ASSOCIATES
139A, ALLENGANJ, PRAYAGRAJ
Contractor
TRIDEV CONSTRUCTION
22/19D, NYAY NAGAR, DHOOMANGANJ, PRAYAGRAJ, UTTAR PRADESH
Sr.Development work declared to RERA
1Demarcation of Plots
As per approved map a total of 53 plots are being developed of various sizes. Demarcation of plot will be done with RCC pillars on four corner of 5 ft height.
2Boundary Wall
Project bounded by compound wall. The said boundary wall is constructed with 9 inch thick brick work and 6 ft in height. the construction is done by fly-ash/red brick work using cement mortar in 1-6 ratio
3Road Work
The internal road will be developed within the project with 9 meter width. Road construction is carried out with basic earth work followed by WBM. GSB, stone dust and ganga sand followed with extensive compaction and thereafter finished with CC work 5 inch thick concrete.
4Footpaths
The footpath (3ft wide) have been designed to carry sewer (6 inch hume pipe) water line (2 inch UPVC) storm water ( 6 Inch PVC pipe) Drain pipe. All these services are underground. The footpath is constructed using paver blocks with kerb stone (12 inch wide)
5Water Supply Including Drinking Water Facilities
Water is being supplied through borewell with 6 inch boring and 5HP pump. Supply to units will be done by underground UPVC pipes of 2 inch thickness.
6Sewer System
A network underground 6 inch hume/PVC pipe will be laid to carry sewerage from household to STP placed within the project. The project is planned with packaged STP of 40 KLD.
7Drain
Roof top run off and kitchen waste water is from households through 6 inch PVC pipes which is laid underground or road (9inch wide ) side drain depending upon the classification of waste water. The waste water will be used for irrigation and road cleaning.
8Parks
Total park area to be developed is 1220 Sq. mtr. The park will be developed as per the horticulture plan, hierarchical trees and shrubs will be planted as per forest policy. The park will be bounded with MS grill and ample lighting arrangement will be made. Park benches will be installed at regular interval.
9Tree Planting
More than 50 trees have been planted within the project. Avenue trees such as kadam and bushes and hedges will be planted hierarchical order. Flowering plants and evergreen plant have been planted in open areas and other installation.
10Design For Electric Supply Including Street Lighting
Underground cables will be used to supply LT power with 3.5x70mm armoured cable and electrical distribution from DB to individual units by 10mm wires. Modern street light will be installed alternatively at every 40 to 60 ft interval.
11Community Buildings
Considering the small size of project no such community building is planned.
12Treatment and Disposal System of Sewage and Sullage water
Package STP of 40 KLD installed as per MBBR technology. The sewage and sullage water will be carried from households through underground services pipes to STP. Treated water from STP will be used for irrigation and road cleaning. The detailed project report for the treatment of Sewage through STP has been submitted before PDA.
13Solid Waste Management And Disposal System
STP planned for the project works to break-down solid waste and filtered water is received from the incoming gray water. This filtered water is used to for irrigation and washing of roads.
14Water Conservation System
Rain water harvesting is planned at the north end of the project land and the stipulated NOC from ground water department will be taken. RWH pits of 40 cumt. along with filters have been planned.
15Energy Management System Including Use of Renewable Energy
The electrical plan of the project has been developed as per norms of UP electricity board and PuVVNL. Solar flood light at strategic location will be provided to supplement the street light on utility power.
16Fire Protection And Fire Safety System
Being a plotted development project the requirement for fire protection is limited, however 4 number fire hydrant and sand bucket have been placed at various easily accessible areas.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not applicable in this project.
18Emergency Evacuation Services
Emergency evacuation areas has been earmarked in open space such as park and tot-lots with a capacity to hold minimum 100 persons at a time in case of requirement. Being plotted development project the need for such services is minimal .
19Other Miscellaneous Work
Development norms rules and commitment made before PDA in the development plan will be adhere to.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 20 Apr 2030.

Sanctioned by Prayagraj(Allahabad) Development Authority · 8,123 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Plotted Resi development/Plotted Housing/04710/PDA/LD/24-25/1129/2402202521 Apr 202520 Apr 203020 Apr 203320 Apr 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
8788550Plot
1616242050368550Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 1/10855/27-48/15295
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · Fasli Year 1426-1431
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New1 May 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New23 Apr 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New23 Apr 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New23 Apr 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New23 Apr 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New23 Apr 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New23 Apr 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New23 Apr 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New23 Apr 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New1 May 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New23 Apr 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New23 Apr 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New23 Apr 2025 ↗

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2025-Q1 to 2026-Q2.

QuarterConstructionCertificates
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q231.47%CA ↗ · Arch ↗ · Eng ↗
2025-Q349.1%CA ↗ · Arch ↗ · Eng ↗
2025-Q467.8%CA ↗ · Arch ↗ · Eng ↗
2026-Q195%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameABHIYAAN BUILDCON PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM7626
PANAAGCS9845J
CIN / TANU45202UP1989PTC010507
Name of chairmanANUBHAV VERMA
Registered address14 IBRAHIMPUR, MAZRA KATKA, JHUNSI, NEAR INDIAN OIL TRIVENIPURAM, ALLAHABAD
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Prayagraj

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
ABHIYAAN BUILDCON-COLLECTION ACCOUNT FOR CITIZEN PAVITRABankINDIAN BANKBranchHINDI SAHITYA SAMMELAN BRANCHBranch address12, KP KAKKAR ROAD, PRAYAGRAJBranch districtPrayagrajA/C no.IFSCIDIB000A580Branch emaila580@indianbank.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
ABHIYAAN BUILDCON-SEPARATE BANK ACCOUNT FOR CITIZEN PAVITRABankINDIAN BANKBranchHINDI SAHITYA SAMMELAN BRANCHBranch address12, KP KAKKAR ROAD, PRAYAGRAJBranch districtPrayagraj, Uttar PradeshA/C no.IFSCIDIB000A580
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
ABHIYAAN BUILDCON RERA TRANSACTION ACCOUNT FOR CITIZEN PAVITRABankINDIAN BANKBranchHINDI SAHITYA SAMMELAN BRANCHBranch address12, KP KAKKAR ROAD, PRAYAGRAJBranch districtPrayagraj, Uttar PradeshA/C no.IFSCIDIB000A580
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

3 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Latest completion certificate filed on2026-10-03
first recorded by Estanzo
11 Oct 2026
Completion date recorded2026-10-03
first recorded by Estanzo
11 Oct 2026
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
7 Oct 2026
When these facts last moved
Latest completion certificate filed onfirst recorded by Estanzo · 11 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about CITIZEN PAVITRA

Is CITIZEN PAVITRA RERA registered?

Yes. CITIZEN PAVITRA is registered with UPRERA under registration number UPRERAPRJ569226, registered on 3 Jun 2025. Estanzo reproduces that filing; it does not verify the work behind it.

Has CITIZEN PAVITRA been completed?

UPRERA still lists CITIZEN PAVITRA as Registered, so it is not shown as completed here. A completion certificate dated 3 Oct 2026 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of CITIZEN PAVITRA?

ABHIYAAN BUILDCON PRIVATE LIMITED is the promoter entity that filed CITIZEN PAVITRA with UPRERA (promoter RERA ID UPRERAPRM7626). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does CITIZEN PAVITRA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is CITIZEN PAVITRA located?

CITIZEN PAVITRA is registered in ANDAWA, Prayagraj, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗