Registered30 Oct 2021
Completed5 Jun 2024
Promised19 Dec 2024

Timeline

Promised completion19 Dec 2024
Revised completion19 Dec 2024
Actual completion5 Jun 2024
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹17,500
Project cost (in ₹ Lakhs)₹900 Lakhs
Project duration39 months
Project categoryResidential
Locality
Original start date
Proposed start date20 Sept 2021

Inventory

Total units112
Unit TypeUnitsCarpet Area (sqm)
1 BHK11225.75–31.14

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9307502104
Emailverma.anubhav@gmail.com
Coordinator9307502104
Address14 IBRAHIMPUR, MAZRA KATKA, JHUNSI, NEAR INDIAN OIL TRIVENIPURAM, ALLAHABAD

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
02/O.C.(T.C.)/ZONE-5/INTEGRATED/DEV AUTH/2020-2127 Feb 202126 Feb 202619 Dec 202426 Feb 2026

Land Parcels

Khasra No.AreaPlot Type
10913740Khasra

Approved Unit Plan

Unit plan rows on file24
Total flats (sum of rows)112
BlocksEWS TOWER A, EWS TOWER B, EWS TOWER C, LIG TOWER A, LIG TOWER B, LIG TOWER C
Floor types1 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of CITIZEN EWS LIG HOUSING SCHEME?

The RERA registration number of CITIZEN EWS LIG HOUSING SCHEME is UPRERAPRJ781821, as recorded on the UP-RERA portal.

What is the RERA status of CITIZEN EWS LIG HOUSING SCHEME?

As reported by UP-RERA, the status of CITIZEN EWS LIG HOUSING SCHEME is "Registered".

Where is CITIZEN EWS LIG HOUSING SCHEME located?

As reported to UP-RERA, CITIZEN EWS LIG HOUSING SCHEME is located at Phulpur, Prayagraj, Uttar Pradesh.

Is CITIZEN EWS LIG HOUSING SCHEME completed?

As reported to UP-RERA, CITIZEN EWS LIG HOUSING SCHEME was completed on 5 Jun 2024.

Is CITIZEN EWS LIG HOUSING SCHEME delayed?

Measured against the latest completion date reported to UP-RERA, CITIZEN EWS LIG HOUSING SCHEME is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026