Estanzo

Timeline Bar

Registered31 Jul 2017
Promised31 Mar 2018
Revised30 Dec 2018
Completed29 Mar 2019

Timeline

Promised completion31 Mar 2018
Revised completion30 Dec 2018
Actual completion29 Mar 2019
Possession delay3 mo delay

Registration & Cost Details

Registration fee (in ₹)₹2,10,000
Project cost (in ₹ Lakhs)₹41,700 Lakhs
Project duration69 months
Project categoryCommercial
Locality
Original start date15 Apr 2013
Proposed start date15 Apr 2013

Inventory

Total units724
Unit TypeUnitsCarpet Area (sqm)
SHOP14970
STUDIO57525

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9312629047
Emailsingh-rajeev2@dlf.in
Coordinator9628543111
AddressDLF CENTRE, SANSAD MARG, NEW DELHI 110001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
39783

Revalidated: 39783 (29 Apr 2016)

18 Mar 201617 Mar 2021

Revalidated upto: 17 Mar 2021

30 Dec 201817 Mar 2021
39783

Revalidated: 39783 (18 Mar 2016)

18 Mar 201617 Mar 2021

Revalidated upto: 1 Jan 1900

30 Dec 201817 Mar 2024

Land Parcels

Khasra No.AreaPlot Type
NANA
TCG 6 BY 619951Plot

Approved Unit Plan

Unit plan rows on file31
Total flats (sum of rows)724
Total shops149
BlocksB1, B2
Floor typesSHOP, STUDIO

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
84066 Sept 2007

Frequently Asked Questions

What is the RERA registration number of CITY CENTRE, LUCKNOW, MY PAD?

The RERA registration number of CITY CENTRE, LUCKNOW, MY PAD is UPRERAPRJ4882, as recorded on the UP-RERA portal.

What is the RERA status of CITY CENTRE, LUCKNOW, MY PAD?

As reported by UP-RERA, the status of CITY CENTRE, LUCKNOW, MY PAD is "Registered".

Where is CITY CENTRE, LUCKNOW, MY PAD located?

As reported to UP-RERA, CITY CENTRE, LUCKNOW, MY PAD is located at Lucknow, Lucknow, Uttar Pradesh.

Is CITY CENTRE, LUCKNOW, MY PAD completed?

As reported to UP-RERA, CITY CENTRE, LUCKNOW, MY PAD was completed on 29 Mar 2019.

Is CITY CENTRE, LUCKNOW, MY PAD delayed?

Measured against the latest completion date reported to UP-RERA, CITY CENTRE, LUCKNOW, MY PAD is 3 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.