Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ17421
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Sept 2018
Project duration42 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant addressA2/3, F.F., Safdarjung Enclave, south delhi Delhi India 110029.
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated

    42890

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  9. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered8 Sept 2018
Original completion31 Aug 2020
Revised completion28 Feb 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary23 Feb 2023
Registration fee₹65,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors84 · 1 · 13 (units from plan)
Homes · commercial units0 · 84 (shops and offices filed in the same plan)
ConfigurationUnitsCarpet area
SHOP8435-217
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A1 · SHOP138435-217
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
SIKKA ASSOSIATES – Mr. Raman Sikka
License 93/16497
A-2/1, Africa Avenue, Safdar Gunj enclave, New Delhi
Engineer
NNC Design International - Mr. Mani
Jaswant Apartment, 25, Shaheen Bagh, Okhla Village, Okhla, New Delhi, Delhi 110025
Contractor
Akashganga Infraventures India Ltd.
Behind Denso Co., Vill. Tilapata , Greater Noida, G.B. Nagar, Uttar Pradesh-201301
Sr.Development work declared to RERA
1Demarcation of Plots
Proper Demracation completed
2Boundary Wall
NA
3Road Work
NA
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
The portable water supply of desired quality & purity shall be ensured by tapping underground water as per approval from authorities.
6Sewer System
Proper provision of sewer lines has been provided
7Drain
Proper provision of drainage has been provided
8Parks
NA
9Tree Planting
NA
10Design For Electric Supply Including Street Lighting
All the workings shall confer to Bureau Of Indian Standards , Indian Electricity Rules & Indian Electricity Acts
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Provisions are provided for recycled water to be used in Flushing & Irrigation works
13Solid Waste Management And Disposal System
Collection system has been proposed to be developed in the building
14Water Conservation System
Proper guidelines will be followed for conservation of natural water
15Energy Management System Including Use of Renewable Energy
Solar energy
16Fire Protection And Fire Safety System
All rules & regulations of NBC is being followed
17Social Infrastructure And Other Public Amenities Including Public Health Services
Proper provision fo social infra and public amenities provided.
18Emergency Evacuation Services
Fire Staircase has been provided on each floor for emergency evacuation.
19Other Miscellaneous Work
Misc work
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 21 Dec 2022. 1 of them carries a revalidation.

Sanctioned by Lucknow Development Authority · 5,439 sqm of land · an approved plan of 1 block and 84 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
4289022 Dec 201721 Dec 202221 Dec 202531 Aug 2020—
4289022 Dec 201721 Dec 202221 Dec 202531 Aug 202022 Dec 2017
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 28 Feb 2022.

#Granted fromExtended uptoNote
131 Aug 202030 Aug 2021—
230 Aug 202128 Feb 2022Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Part of TC/G-1/15439Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 8019
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New6 Sept 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New7 Sept 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New7 Sept 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New7 Sept 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New7 Sept 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New7 Sept 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New7 Sept 2018 ↗

Quarterly progress reports

8 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

8 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2100%CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2021-Q2. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameM/s Shalimar Corp Ltd.
RolePromoter · current
RERA IDUPRERAPRM4092
PANAADCS9234L
CIN / TANU70100DL1988PLC390006
Name of chairmanMohd. Abdullah Masood
Registered addressA2/3, F.F., Safdarjung Enclave, south delhi Delhi India 110029.
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Shalimar Corp LimitedBankORIENTAL BANK OF COMMERCEBranchVIVEK KHAND GOMTI NAGAR LUCKNOWA/C no.IFSCORBC0100687
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Iridium

Is Iridium RERA registered?

Yes. Iridium is registered with UPRERA under registration number UPRERAPRJ17421, registered on 8 Sept 2018. Estanzo reproduces that filing; it does not verify the work behind it.

Has Iridium been completed?

UPRERA still lists Iridium as Registered, so it is not shown as completed here. A completion certificate dated 23 Feb 2023 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Iridium?

M/s Shalimar Corp Ltd. is the promoter entity that filed Iridium with UPRERA (promoter RERA ID UPRERAPRM4092). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Iridium more time to complete?

UPRERA's record carries 2 completion extensions for Iridium, the latest running to 28 Feb 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Iridium have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Iridium located?

Iridium is registered in Lucknow, as filed with UPRERA.

What configurations are available in Iridium?

The unit plan filed with UPRERA lists SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Iridium?

The approved unit plan filed with UPRERA runs from 35 to 217 m² of carpet area (about 381 to 2,339 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Iridium?

The approved unit plan describes 1 block and 84 units of which 0 are homes and 84 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Iridium?

About 62 units per acre: 84 planned units across 1.34 acres (5,439 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗