Timeline Bar

Registered6 Dec 2023
Completed24 Mar 2026
Promised31 Mar 2029

Timeline

Promised completion31 Mar 2029
Revised completion31 Mar 2029
Actual completion24 Mar 2026
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹42,000
Project cost (in ₹ Lakhs)₹7,489 Lakhs
Project duration96 months
Project categoryResidential
Locality
Original start date
Proposed start date5 Apr 2021

Inventory

Total units312
Unit TypeUnitsCarpet Area (sqm)
1 BHK1244.7
2 BHK22052.45–55.45
3 BHK8068.04

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9810302222
Emailaapl.rera@gmail.com
Coordinator9810302222
Address10, NEW RAJDHANI ENCLAVE, VIKAS MARG, DELHI - 110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q281.8%
2025-Q389.4%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
GDA/BP/20-21/093230 Mar 202131 Mar 202631 Mar 202931 Mar 2029

Land Parcels

Khasra No.AreaPlot Type
22485060Khasra
2261501.38Khasra
22673160Khasra
22682910Khasra
2269868.62Khasra
23657500Khasra
23673540Khasra
23684050Khasra
23692780Khasra
23702780Khasra
23714170Khasra
23724050Khasra
23733540Khasra
23748090Khasra

Approved Unit Plan

Unit plan rows on file79
Total flats (sum of rows)312
BlocksBLOCK-mn
Floor types1 BHK, 2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of CITY GRACE?

The RERA registration number of CITY GRACE is UPRERAPRJ787285, as recorded on the UP-RERA portal.

What is the RERA status of CITY GRACE?

As reported by UP-RERA, the status of CITY GRACE is "Registered".

Where is CITY GRACE located?

As reported to UP-RERA, CITY GRACE is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is CITY GRACE completed?

As reported to UP-RERA, CITY GRACE was completed on 24 Mar 2026.

Is CITY GRACE delayed?

Measured against the latest completion date reported to UP-RERA, CITY GRACE is on time.