Estanzo

Timeline Bar

Registered12 Jul 2024
Today4 Aug 2026
Promised21 May 2029

Timeline

Promised completion21 May 2029
Revised completion21 May 2029
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹79,000
Project cost (in ₹ Lakhs)₹40,580 Lakhs
Project duration60 months
Project categoryResidential
LocalitySECTOR-1, GREATER NOIDA WEST
Original start date
Proposed start date1 Jun 2024

Inventory

Total units375
Unit TypeUnitsCarpet Area (sqm)
3 BHK294101.54–189.15
4 BHK64149.29–210.42
SHOP1717.55–44

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9818444995
Emailrera@crcgroup.in
Coordinator9599109259
Helpline9871909220
AddressRegistered Office Address- SHOP NO. 111, VARDHMAN MAYUR MARKET KONDLI MAYUR VIHAR PHASE-III, DELHI 110096 Corporate Office Address- GROUND FLOOR, LOGIX TECHNO PARK SECTOR-127 NOIDA. 201301 Site Address- GH-8A TECHZONE-IV GREATER NOIDA WEST. 201306

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q211.0%
2025-Q316.0%
2025-Q422.0%
2026-Q131.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BP/SM-27-MAR-2024; 2076822 May 202421 May 202921 May 202921 May 2034

Land Parcels

Khasra No.AreaPlot Type
Plot No.11B14769Plot

Approved Unit Plan

Unit plan rows on file214
Total flats (sum of rows)375
Total shops17
BlocksTOWER -1, TOWER -2, TOWER -3, TOWER -4, TOWER -5
Floor types3 BHK, 4 BHK, SHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of CRC MAESTA?

The RERA registration number of CRC MAESTA is UPRERAPRJ724518, as recorded on the UP-RERA portal.

What is the RERA status of CRC MAESTA?

As reported by UP-RERA, the status of CRC MAESTA is "Registered".

Where is CRC MAESTA located?

As reported to UP-RERA, CRC MAESTA is located at PLOT NO.11B, SECTOR-1, GREATER NOIDA WEST, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will CRC MAESTA be completed?

The latest completion date reported to UP-RERA for CRC MAESTA is 21 May 2029.

Is CRC MAESTA delayed?

Measured against the latest completion date reported to UP-RERA, CRC MAESTA is on time.