Timeline Bar
Registered12 Jul 2024
Today4 Aug 2026
Promised21 May 2029
Timeline
Promised completion21 May 2029
Revised completion21 May 2029
Actual completion—
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹79,000
Project cost (in ₹ Lakhs)₹40,580 Lakhs
Project duration60 months
Project categoryResidential
LocalitySECTOR-1, GREATER NOIDA WEST
Original start date—
Proposed start date1 Jun 2024
Inventory
Total units375
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 3 BHK | 294 | 101.54–189.15 |
| 4 BHK | 64 | 149.29–210.42 |
| SHOP | 17 | 17.55–44 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9818444995
Emailrera@crcgroup.in
Coordinator9599109259
Helpline9871909220
AddressRegistered Office Address- SHOP NO. 111, VARDHMAN MAYUR MARKET KONDLI MAYUR VIHAR PHASE-III, DELHI 110096
Corporate Office Address- GROUND FLOOR, LOGIX TECHNO PARK SECTOR-127 NOIDA. 201301
Site Address- GH-8A TECHZONE-IV GREATER NOIDA WEST. 201306
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| PLG/BP/SM-27-MAR-2024; 20768 | 22 May 2024 | 21 May 2029 | 21 May 2029 | 21 May 2034 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| Plot No.11B | 14769 | Plot |
Approved Unit Plan
Unit plan rows on file214
Total flats (sum of rows)375
Total shops17
BlocksTOWER -1, TOWER -2, TOWER -3, TOWER -4, TOWER -5
Floor types3 BHK, 4 BHK, SHOP, OTHER
Individual floor/unit rows are not listed here.
Frequently Asked Questions
What is the RERA registration number of CRC MAESTA?
The RERA registration number of CRC MAESTA is UPRERAPRJ724518, as recorded on the UP-RERA portal.
What is the RERA status of CRC MAESTA?
As reported by UP-RERA, the status of CRC MAESTA is "Registered".
Where is CRC MAESTA located?
As reported to UP-RERA, CRC MAESTA is located at PLOT NO.11B, SECTOR-1, GREATER NOIDA WEST, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will CRC MAESTA be completed?
The latest completion date reported to UP-RERA for CRC MAESTA is 21 May 2029.
Is CRC MAESTA delayed?
Measured against the latest completion date reported to UP-RERA, CRC MAESTA is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026