CRC MAESTA

UPRERARegistered

CRC MAESTA is a RERA-registered residential project by CRC Homes Private Limited in SECTOR-1, GREATER NOIDA WEST, Gautam Budh Nagar (RERA ID UPRERAPRJ724518). Registered with a completion deadline of 21 May 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
11%Q3'25
16%Q4'25
22%Q1'26
31%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ724518
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Jun 2024
Project duration60 months
AddressPLOT NO.11B, SECTOR-1, GREATER NOIDA WEST, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressRegistered Office Address- SHOP NO. 111, VARDHMAN MAYUR MARKET KONDLI MAYUR VIHAR PHASE-III, DELHI 110096 Corporate Office Address- GROUND FLOOR, LOGIX TECHNO PARK SECTOR-127 NOIDA. 201301 Site Address- GH-8A TECHZONE-IV GREATER NOIDA WEST. 201306
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/BP/SM-27-MAR-2024; 20768

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered12 Jul 2024
Original completion21 May 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹79,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors375 · 5 · 36 (units from plan)
Homes · commercial units358 · 17 (shops and offices filed in the same plan)
  • 3 BHK294 78%
  • 4 BHK64 17%
  • SHOP17 5%
ConfigurationUnitsCarpet area
3 BHK294102-189
4 BHK64149-210
SHOP1718-44
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER -1 · 3 BHK, OTHER3258107
TOWER -2 · 3 BHK, OTHER3358119-189
TOWER -3 · 4 BHK, OTHER3664149-210
TOWER -4 · 3 BHK, OTHER3358118-189
TOWER -5 · 3 BHK, SHOP, OTHER3313718-102
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
RAJIV GANDHI
License CA/91/13852
A-64,SECTOR-83 NOIDA 201301
Engineer
VMS CONSULTANTS PVT LTD
83/84 SAKHAR BHAWAN 230 , NARIMAN POINT MUMBAI 400021
Contractor
KATYANI STEEL WORKS
120/5,KRISHNA NAGAR SAFADARJUNG ENCLAVE DELHI -110029
Sr.Development work declared to RERA
1Demarcation of Plots
The Plot No. GH-11B, Sector-1, Greater NOIDA West had been demarcated by Greater NOIDA Industrial Development Authority (GNIDA).
2Boundary Wall
A Boundary wall of RCC/Brick of thickness 115mm / 230/150mm and ht of 1800mm with plaster and railing will be prepared.
3Road Work
Access driveway to all the towers will be provided and that drive way will be of pavers M 30 grade with thickness of 65 mm and 100mm kerb stone sides if required. An entry of tower, there will a pattern as per the design.
4Footpaths
Footpath will be provided using 40-50mm paver whenever required.
5Water Supply Including Drinking Water Facilities
Greater NOIDA Industrial Development Authority (GNIDA)/Tanker shall supply water for the entire society, and it shall be collected in under ground water tanks of 100 KL X 1 No Domestic Treated Water and 100 KL X1 No Raw Water Tanks and Water pipes to overhead tanks at respective tower. WTP will be equipped with Hydro Pneumatic pump with GI ring and Riser.
6Sewer System
STP of 250 KL Capacity will be constructed using RCC and required pump rooms, STP treated Water will be used in flushing system and gardening.
7Drain
Storm Water drainage system will be constructed using 300 mm dia pipes as per drawings.
8Parks
Landscape will civil work masonry 115/230 mm and stone, paver, grass and various type of plantation, shrubs.
9Tree Planting
Tree Plantation will be as per sanctioned plan in which 50 percent trees will be evergreen trees
10Design For Electric Supply Including Street Lighting
HT Electrical supply will be provided by NPCL, Substation consisting of 2 Nos 1250 KVA and 1 X 800 KVA Transformers, LT Panel and 1 no. X 750 KVA, 1X600 KVA and 1 no X 500 KVA DG Set will be there. Street Lighting will be done using LT Supply and Power Back up.
11Community Buildings
Community building will be made as per approved building plan and there will be multi purpose hall, indoor games, GYM, Entrance Lobby etc.
12Treatment and Disposal System of Sewage and Sullage water
250 KL STP will be installed as per sanctioned drawing. All sewerage will be treated and treated water will be used for landscaping and flushing system.
13Solid Waste Management And Disposal System
Collection, Storage and disposal will be done manually, and disposal will be done as per norms.
14Water Conservation System
3 nos. Rain Water Harvesting System is being provided to conserve rain water and dual flush system will also be provided.
15Energy Management System Including Use of Renewable Energy
Usage of LED Lights will be used all over the project and use of solar PV System will also be explored.
16Fire Protection And Fire Safety System
In compliance to the National Building Code of India 2016, Part IV requirements, Fire Protection and Safety System Consisting of- Underground fire tanks of 270X2 = 540m3 Each tower having 10m3 fire overhead water tank Main electric fire hydrant and sprinkler pumps provided of 2850 LPM each. Jockey Pump for Hydrant and Sprinkler Pump of 180 LPM each. Diesel Engine Fire Pump of 2850 LPM. Water Certain pump of 2280 LPM All Project sprinkler system provided in compliance to IS Codes and project fire safety requirements aligned to NBC 2016 Part IV.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Social gathering places in the community building are being provided.
18Emergency Evacuation Services
Yes, Refuge area provided at every tower on 18th and 27th Floor in addition to main and fire staircase.
19Other Miscellaneous Work
Proper Security System including Security Guard, CCTV, Cameras and controlled access will be made available.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 21 May 2029.

Sanctioned by Greater Noida Authority · 14,769 sqm of land · an approved plan of 5 blocks and 375 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG/BP/SM-27-MAR-2024; 2076822 May 202421 May 202921 May 203421 May 2029
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Plot No.11B14769Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 20687
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · PERMISSION TO SUB LEASE
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · JOINT DEVELOPMENT AGREEMENT
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · LAND TITLE SEARCH REPORT
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · REVOCATION OF CANCELLATION OF LAND LETTER
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · RESTORATION ORDER FROM GNOIDA
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · FORM RA-7
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New12 Jun 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New25 May 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New25 May 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New25 May 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New25 May 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New25 May 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New25 May 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New25 May 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 May 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New25 May 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New25 May 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New25 May 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New12 Jun 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New25 May 2024 ↗

Quarterly progress reports

10 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

10 quarterly progress reports are on file with UPRERA, covering 2024-Q1 to 2026-Q2.

QuarterConstructionCertificates
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q211%CA ↗ · Arch ↗ · Eng ↗
2025-Q316%CA ↗ · Arch ↗ · Eng ↗
2025-Q422%CA ↗ · Arch ↗ · Eng ↗
2026-Q131%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameCRC Homes Private Limited
RolePromoter · current
RERA IDUPRERAPRM137312
PANAAICC8998A
CIN / TANDELC21422C
Name of chairmanMr. Satish Garg
Registered addressRegistered Office Address- SHOP NO. 111, VARDHMAN MAYUR MARKET KONDLI MAYUR VIHAR PHASE-III, DELHI 110096 Corporate Office Address- GROUND FLOOR, LOGIX TECHNO PARK SECTOR-127 NOIDA. 201301 Site Address- GH-8A TECHZONE-IV GREATER NOIDA WEST. 201306
RERA contact
Registered since2021
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameCOMELY BUILDTECH INDIA PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressGH-11B ,SECTOR -1, GREATER NOIDA WEST ,GAUTAM BUDDHA NAGAR ,UP, 201306
RERA contact

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
CRC HOMES PVT LTD COLLECTION ACCOUNT FOR CRC MAESTABankICICI BANK LTDBranchICICI BANK SECTOR -18 , NOIDABranch addressK-1 , SENIOR MALL SEECTOR -18,201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0000031Branch emailbhardwaj.puneet@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
CRC HOMES PVT LTD SEPERATE BANK FOR CRC MAESTABankICICI BANK LTDBranchICICI BANK SECTOR -18, NOIDABranch addressK-1, SENIOR MALL ,SECTOR -18 , NOIDA ,201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0000031
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
CRC HOMES PVT LTD RERA TRANSACTION ACCOUNT FOR CRC MAESTABankICICI BANK LTDBranchICICI BANK SECTOR -18 , NOIDABranch addressK-1,SENIOR MALL SECTOR -18, NOIDA ,201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0000031
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
19 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about CRC MAESTA

Is CRC MAESTA RERA registered?

Yes. CRC MAESTA is registered with UPRERA under registration number UPRERAPRJ724518, registered on 12 Jul 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for CRC MAESTA?

The completion date filed with UPRERA is 21 May 2029. No completion certificate is on record yet.

Who is the builder of CRC MAESTA?

CRC Homes Private Limited is the promoter entity that filed CRC MAESTA with UPRERA (promoter RERA ID UPRERAPRM137312). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does CRC MAESTA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is CRC MAESTA located?

CRC MAESTA is registered in SECTOR-1, GREATER NOIDA WEST, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in CRC MAESTA?

The unit plan filed with UPRERA lists 3 BHK, OTHER, 4 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in CRC MAESTA?

The approved unit plan filed with UPRERA runs from 18 to 210 m² of carpet area (about 189 to 2,265 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in CRC MAESTA?

The approved unit plan describes 5 blocks and 375 units of which 358 are homes and 17 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is CRC MAESTA?

About 103 units per acre: 375 planned units across 3.65 acres (14,769 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗