Estanzo

Timeline Bar

Registered29 Mar 2023
Today4 Aug 2026
Promised3 Jan 2027

Timeline

Promised completion3 Jan 2027
Revised completion3 Jan 2027
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹2,96,000
Project cost (in ₹ Lakhs)₹52,100 Lakhs
Project duration47 months
Project categoryResidential
Locality
Original start date
Proposed start date8 Feb 2023

Inventory

Total units2156
Unit TypeUnitsCarpet Area (sqm)
2 BHK46856.07–71.52
3 BHK49281.1
4 BHK240114.16–115.02
OTHER95622.87

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643546733
EmailPK46733@GMAIL.COM
Coordinator8130055636
Helpline9540300400
AddressSF-01, (Second Floor), "EUREKA HOUSE", A-30/2, GALI NO. 3 WEST JYOTI NAGAR, DELHI - 110094

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q28.0%
2025-Q312.5%
2025-Q418.5%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
04/19-20/L/PKW4 Jan 20223 Jan 20273 Jan 20273 Jan 2030

Land Parcels

Khasra No.AreaPlot Type
630 and 63246670Khasra
10005870Khasra
100415086Khasra

Approved Unit Plan

Unit plan rows on file270
Total flats (sum of rows)2156
BlocksA, B, C, D, E, F, G, H, I, Land-B Tower-A (EWS), Land-B Tower-B (EWS), Land-B Tower-C (EWS), Land-B Tower-D (EWS), Land-B Tower-E (EWS), Land-B Tower-F (EWS)
Floor types2 BHK, 3 BHK, 4 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Diya GreenCity NH-24?

The RERA registration number of Diya GreenCity NH-24 is UPRERAPRJ705122, as recorded on the UP-RERA portal.

What is the RERA status of Diya GreenCity NH-24?

As reported by UP-RERA, the status of Diya GreenCity NH-24 is "Registered".

Where is Diya GreenCity NH-24 located?

As reported to UP-RERA, Diya GreenCity NH-24 is located at Dhaulana, Hapur, Uttar Pradesh.

When will Diya GreenCity NH-24 be completed?

The latest completion date reported to UP-RERA for Diya GreenCity NH-24 is 3 Jan 2027.

Is Diya GreenCity NH-24 delayed?

Measured against the latest completion date reported to UP-RERA, Diya GreenCity NH-24 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026