Eldeco 7 Peaks Residences is a RERA-registered residential project by Eldeco Homes Developers Limited in Sector Omicron 1A, Gautam Budh Nagar (RERA ID UPRERAPRJ106523). Registered with a completion deadline of 14 Nov 2030.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ106523 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Greater Noida Authority |
| Proposed start | 1 Jan 2026 |
| Project duration | 59 months |
| Address | Plot GH-01 & GH-01A, Block A; Sector Omicron 1A, Sector Omicron 1A, Gautam Buddha Nagar, Gautam Budh Nagar |
| Tehsil | Gautam Buddha Nagar |
| Applicant type | Company |
| Applicant address | 201-212, Splendor Forum, IInd Floor,Jasola District Centre, New Delhi-110025 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
- valid to
Permit revalidated
PLG/BP SM-20-Jun-2025-25169
2 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 28 Jan 2026 |
| Original completion | 14 Nov 2030 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹1,54,500 |
| Sanctioning authority | Greater Noida Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK686 82%
- 4 BHK81 10%
- PENTHOUSE28 3%
- 2 BHK25 3%
- SHOP16 2%
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 25 | 73-85 |
| 3 BHK | 686 | 92-124 |
| 4 BHK | 81 | 144 |
| SHOP | 16 | 5-203 |
| PENTHOUSE | 28 | 92-144 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| TOWER 5/ EVEREST · OTHER, 3 BHK, 2 BHK, 4 BHK, PENTHOUSE | 33 | 116 | 80-144 |
| TOWER 6/ KILI WEST · OTHER, SHOP, 2 BHK, 3 BHK, PENTHOUSE | 34 | 136 | 5-203 |
| Tower 1/ ASGARD · OTHER, 2 BHK, 3 BHK, PENTHOUSE | 33 | 116 | 75-105 |
| Tower 2/ BLANC · OTHER, 2 BHK, 3 BHK, PENTHOUSE | 33 | 116 | 75-105 |
| Tower 3/ CRESTONE · OTHER, 3 BHK, 2 BHK, 4 BHK, PENTHOUSE | 33 | 116 | 80-144 |
| Tower 4/ DENALI · OTHER, 3 BHK, 2 BHK, 4 BHK, PENTHOUSE | 33 | 116 | 80-144 |
| Tower 7/ KILI EAST · OTHER, 2 BHK, 3 BHK, PENTHOUSE | 34 | 120 | 73-94 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots PPROPOSED GROUP HOUSING IS A PART OF DEVELOPMENT PLAN BY GNIDA SPREAD OVER AN AREA OF 30470.52 SQMT |
| 2 | Boundary Wall BOUNDARY WALL/FENCE WITH A HEIGHT OF 1.5 TO 2.5 FROM INTERNAL ROAD LEVEL |
| 3 | Road Work CC/ PAVER/ GRANITE INTERNAL ROAD ALONG WITH SIDE PAVMENT SHALL BE CONSTRUCTED AS PER APPROVED LAYOUT IT VARIES IN WIDTH FROM 2 TO 4 M. OUTER PERIPHERIAL ROAD IS APPROX 6M. |
| 4 | Footpaths CONTINUOUS LINKED PATHWAYIN THE COMPLEX PROVIDED TO ENABLE PEOPLE TO HAVE A WALKABLE NEIGHBOURHOOD. THE WIDTH OF FOOTPATH VARIES FROM 1.5M TO 3 M. |
| 5 | Water Supply Including Drinking Water Facilities WATER SUPPLY FROM UNDERGROUND TANK SHALL BE PUMPED TO OHT ON TERRACE OF EACH TOWER. THROUGH AN UNDERGROUND TANK. A WELL DESIGNED PLUMBING SYSTEM WILL BE THERE. IN TOTAL THERE WILL BE 1 OHT ON EACH OF THE 6 TOWERS AND 1 UGT IN THE PROJECT. |
| 6 | Sewer System A WELL DESIGNED SEWER SYSTEM WILL BE LAID TO COLLECT SOIL / WASTE WATER WHICH IN TURN WILL CONNECT TO THE MAIN SEWER LINE |
| 7 | Drain A WELL DESIGNED SYSTEM OF COVERED AND UNDERGROUND DRAIN SHALL BE IN PLACE |
| 8 | Parks ALL THE GREEN AREAS WILL HAVE GRASS COVERED WITH MINIUMUM PAVED AREA, SITTING AND PLAY ING ARRANGEMENTS. LOW HEIGHT PLANTATION SHALL BE PROVIDED |
| 9 | Tree Planting 4.5-6 M HIGH TREES SHALL BE ALONG MAIN INTERNAL ROADSA |
| 10 | Design For Electric Supply Including Street Lighting CONNECTION FROM LESA TO BE OBTAINED FROM REQUIRED ELECTRICAL LOAD FOR STREET LIGHTING AND COMPLEX REQUIREMENT IN GENERAL. Total Load 7279 kW |
| 11 | Community Buildings A WELL DESIGNED COMMUNITY BUILDING IA A PART OF THE SCHEME . CLUB WITH AN AREA OF 4030.899 SQMT |
| 12 | Treatment and Disposal System of Sewage and Sullage water A WELL DESIGNED STP WITH CAPACITY 575 KLD IN PLACE TO TAKE CARE OF SEWAGE SULLAGE |
| 13 | Solid Waste Management And Disposal System COLLECTION AND DISPOSAL OF SOILD WASTE WILL BE COORDINATED WITH GNIDA |
| 14 | Water Conservation System ALL THE TERRACE STORM WATER WILL BE HARVESTED TO RECHARGE GROUND WATER. WASTE WATER SHALL BE RECYCLED AND USED FOR IRRIGATION/ GARDENING |
| 15 | Energy Management System Including Use of Renewable Energy 25 PERCENT OF STREET LIGHTWILL HAVE SOLAR ENERGY BACKUP. COMMON AREA LIGHT TO BE BRIGHTNESS SENSITIVE TO SAVE ENERGY. BEE5 STAR RATING DG SET OF CAPACITY 2000KV X3 NOS AND 1250 KV 1 NO. |
| 16 | Fire Protection And Fire Safety System A WELL DESIGNED FIREFIGTHING SYSTEM / EVACUATION ARRANGEMENT SHALL BE IN PLACE AS FAS , PRESSURISED FIRE ESCAPES, DOWNCOMER, FIRE EXTINGUISHER |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services CLUB AND KIDS PLAY AREA PROVIDED |
| 18 | Emergency Evacuation Services ALL THE EXIT POINTS WITH ADEQUATE WIDTH AS PER NORMS AVIALABLE TO FACILITATE EVACUATION IN CASE OF EMERGENCY |
| 19 | Other Miscellaneous Work NA |
Registered agents
4 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | INVESTOXPERT ADVISORS PVT LTD | UPRERAAGT21108 |
| 2 | JOINT BRICKS PROPMART | UPRERAAGT11518 |
| 3 | PC MANTRA INFOSYSTEM PVT. LTD. | UPRERAAGT10580 |
| 4 | Walmond Realty Dart Pvt Ltd | UPRERAAGT10777 |
Permits & extensions
2 permits
An approval and the date it runs to - not proof the work matching it was done.
2 sanctioning permits are on record with UPRERA, the latest valid to 14 Nov 2030. 1 of them carries a revalidation, valid to 27 Jan 2031.
Sanctioned by Greater Noida Authority · 30,470.52 sqm of land · an approved plan of 7 blocks and 836 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| PLG/BP SM-20 JUN 2025-25169 | 15 Nov 2025 | 14 Nov 2030 | 14 Nov 2032 | 14 Nov 2030 | — | |
| PLG/BP SM-20-Jun-2025-25169 | 15 Nov 2025 | 14 Nov 2030 | 13 Nov 2032 | 14 Nov 2030 | 15 Nov 2025 valid to 27 Jan 2031 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
23 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| GH-01 and GH-01A | 30470.52 | Plot |
| Lease deed · 10979 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Allotment letter from the authority · 1394 The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Lease deed · 1 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Water supply plan How the project proposed to supply water, as filed at registration. | not reported | — |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | not reported | — |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | not reported | — |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | not reported | — |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 15 Dec 2025 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 15 Dec 2025 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 12 Dec 2025 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 12 Dec 2025 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 5 Jan 2026 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 5 Jan 2026 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 5 Jan 2026 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 5 Jan 2026 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 12 Dec 2025 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 15 Dec 2025 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 6 Jan 2026 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 5 Jan 2026 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 15 Dec 2025 ↗ |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | New | 6 Jan 2026 ↗ |
Quarterly progress reports
2 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
2 quarterly progress reports are on file with UPRERA, covering 2025-Q4 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2025-Q4 | 30.41% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 29.63% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Eldeco Homes Developers Limited |
| Role | Promoter · current |
| RERA ID | UPRERAPRM421713 |
| PAN | AAGCE6361F |
| CIN / TAN | U70109DL2021PLC386190 |
| Registered address | 201-212, Splendor Forum, IInd Floor,Jasola District Centre, New Delhi-110025 |
| RERA contact | |
| Registered since | 2025 |
Nearby projects
Gautam Budh Nagar
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | ELDECO HOMES DEVELOPERS LTD-COLL A/C FOR ELDECO 7 PEAKS RESIDENCES-ESCBankHDFC BANKBranchELDECO STUDIO APARTMENTBranch addressPLOT NO. 3, ELDECO STUDIA APARTMENT, SECTOR -93A, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002830Branch emailsupport@hdfc.bank.in |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | ELDECO HOMES DEVELOPERS LTD-SEP A/C FOR ELDECO 7 PEAKS RESIDENCES- ESCBankHDFC BANKBranchELDECO STUDIO APARTMENTBranch addressPLOT NO. 3, ELDECO STUDIO APARTMENT, SECTOR-93A, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002830 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | ELDECO HOMES DEVELOPERS LTD-TRAN A/C FOR ELDECO 7 PEAKS RESIDENCES-ESCBankHDFC BANKBranchELDECO STUDIO APARTMENTBranch addressPLOT NO.3, ELDECO STUDIO APARTMENT, SECTOR-93A, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002830 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about Eldeco 7 Peaks Residences
Is Eldeco 7 Peaks Residences RERA registered?
Yes. Eldeco 7 Peaks Residences is registered with UPRERA under registration number UPRERAPRJ106523, registered on 28 Jan 2026. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for Eldeco 7 Peaks Residences?
The completion date filed with UPRERA is 14 Nov 2030. No completion certificate is on record yet.
Who is the builder of Eldeco 7 Peaks Residences?
Eldeco Homes Developers Limited is the promoter entity that filed Eldeco 7 Peaks Residences with UPRERA (promoter RERA ID UPRERAPRM421713). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does Eldeco 7 Peaks Residences have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Eldeco 7 Peaks Residences located?
Eldeco 7 Peaks Residences is registered in Sector Omicron 1A, Gautam Budh Nagar, as filed with UPRERA.
What configurations are available in Eldeco 7 Peaks Residences?
The unit plan filed with UPRERA lists OTHER, 2 BHK, 3 BHK, 4 BHK, SHOP and PENTHOUSE. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Eldeco 7 Peaks Residences?
The approved unit plan filed with UPRERA runs from 5 to 203 m² of carpet area (about 54 to 2,183 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Eldeco 7 Peaks Residences?
The approved unit plan describes 7 blocks and 836 units of which 820 are homes and 16 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Eldeco 7 Peaks Residences?
About 111 units per acre: 836 planned units across 7.53 acres (30,470.52 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗