Timeline Bar

Registered14 Aug 2017
Promised23 Jun 2019
Completed27 Jun 2023

Timeline

Promised completion23 Jun 2019
Revised completion23 Jun 2019
Actual completion27 Jun 2023
Possession delay48 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,88,000
Project cost (in ₹ Lakhs)₹40,635 Lakhs
Project duration56 months
Project categoryResidential
Locality
Original start date29 Jan 2014
Proposed start date24 Jun 2015

Inventory

Total units1320
Unit TypeUnitsCarpet Area (sqm)
2 BHK132046.89–67.59

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9811005579
Emailceo@gnida.in
Coordinator9871090103
AddressPLOT NO-01, KNOWLEDGE PARK-04, GREATER NOIDA, G.B. NAGAR UP

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
11 Aug 201731 Jul 202223 Jun 201931 Jul 2022

Land Parcels

Khasra No.AreaPlot Type
43740
44400
451010
471760
482470
4911105
50570
51570
10116050
1031050
110860
43740Khasra
44400Khasra
451010Khasra
471760Khasra
482470Khasra
4911105Khasra
50570Khasra
51570Khasra
1031050Khasra
110860Khasra
10116050Khasra

Approved Unit Plan

Unit plan rows on file135
Total flats (sum of rows)1320
BlocksA, B, C, D, E, F, G, H, I
Floor types2 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
NA1 Aug 2017
NA1 Aug 2017

Frequently Asked Questions

What is the RERA registration number of BHS-17 LOHIYA ENCLAVE OMICRON-1A?

The RERA registration number of BHS-17 LOHIYA ENCLAVE OMICRON-1A is UPRERAPRJ9632, as recorded on the UP-RERA portal.

What is the RERA status of BHS-17 LOHIYA ENCLAVE OMICRON-1A?

As reported by UP-RERA, the status of BHS-17 LOHIYA ENCLAVE OMICRON-1A is "Registered".

Where is BHS-17 LOHIYA ENCLAVE OMICRON-1A located?

As reported to UP-RERA, BHS-17 LOHIYA ENCLAVE OMICRON-1A is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is BHS-17 LOHIYA ENCLAVE OMICRON-1A completed?

As reported to UP-RERA, BHS-17 LOHIYA ENCLAVE OMICRON-1A was completed on 27 Jun 2023.

Is BHS-17 LOHIYA ENCLAVE OMICRON-1A delayed?

Measured against the latest completion date reported to UP-RERA, BHS-17 LOHIYA ENCLAVE OMICRON-1A is 48 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026