Estanzo

Timeline Bar

Registered1 Apr 2021
Completed3 Jun 2024
Promised13 Jul 2026

Timeline

Promised completion13 Jul 2026
Revised completion13 Jul 2026
Actual completion3 Jun 2024
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹21,000
Project cost (in ₹ Lakhs)₹1,060 Lakhs
Project duration65 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Mar 2021

Inventory

Total units142
Unit TypeUnitsCarpet Area (sqm)
1 BHK13631.743
STUDIO617.31

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9670222298
Emailehil@eldecohousing.co.in
Coordinator9670222298
AddressShop No S-16, Second Floor, Eldeco Station 1, Site No.1, Faridabad sector 12, Faridabad 121007, Haryana India

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
MAP2019082411560842314 Jul 202013 Jul 202513 Jul 202612 Jul 2028

Land Parcels

Khasra No.AreaPlot Type
N.A3124Plot

Approved Unit Plan

Unit plan rows on file13
Total flats (sum of rows)142
BlocksEldeco Saksham
Floor types1 BHK, STUDIO, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Eldeco Saksham At Samridhi, Udyan 2?

The RERA registration number of Eldeco Saksham At Samridhi, Udyan 2 is UPRERAPRJ421679, as recorded on the UP-RERA portal.

What is the RERA status of Eldeco Saksham At Samridhi, Udyan 2?

As reported by UP-RERA, the status of Eldeco Saksham At Samridhi, Udyan 2 is "Registered".

Where is Eldeco Saksham At Samridhi, Udyan 2 located?

As reported to UP-RERA, Eldeco Saksham At Samridhi, Udyan 2 is located at Sarojini Nagar, Lucknow, Uttar Pradesh.

Is Eldeco Saksham At Samridhi, Udyan 2 completed?

As reported to UP-RERA, Eldeco Saksham At Samridhi, Udyan 2 was completed on 3 Jun 2024.

Is Eldeco Saksham At Samridhi, Udyan 2 delayed?

Measured against the latest completion date reported to UP-RERA, Eldeco Saksham At Samridhi, Udyan 2 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026