ELDECO Housing and Industries Ltd. (RERA ID: UPRERAPRM21) is a company registered with UP-RERA since 2017. It has 28 projects on record with Estanzo, of which 3 are on RERA's Default-on-QPR list.
One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.
Projects by this promoter
28 on record · 5 as co-promoter
Showing 20 of 28 projects on record. See all 28 projects
Filings for more time
11 filings
| Extension filings | 11 |
| Projects with at least one | 11 of 28 |
| Longest single extension | 182 days - Eldeco Select at Saubhagyam (T5) |
| Latest extension runs to | 24 Aug 2026 - Eldeco South Block at Eldeco Shaurya |
| Permits carrying a revalidation | 3 across 3 projects |
Directors & ownership
7 named by UPRERA
Promoter timeline
28 Jul 2017 - 23 Apr 2026
- Project registeredofficial source ↗
- Completion certificate filedofficial source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 24 Aug 2026as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 24 Aug 2026as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 24 Aug 2026as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedvalid to 23 Jul 2030as recorded by UPRERA: Plotted Resi development/ Plotted Housing/14324/LDA/LD/24-25/0492/18122024official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 11 Jun 2025as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
Show 49 earlier filings
- Extension filednew completion date on file 14 Apr 2025as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 13 Feb 2025official source ↗
- Project registeredofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 11 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Project registeredofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 19 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 17 Dec 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedvalid to 15 Mar 2026as recorded by UPRERA: 2095(earlier permit no was 386 dated 17/06/2019)official source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 18 May 2021official source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 27 Feb 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedas recorded by UPRERA: 42738official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
Quarterly reports filed, by financial year
Common questions about ELDECO Housing and Industries Ltd.
How many projects has ELDECO Housing and Industries Ltd. registered with RERA?
Estanzo holds 28 projects on record with UPRERA, filed by ELDECO Housing and Industries Ltd. (promoter RERA ID UPRERAPRM21). This counts filings by this legal entity only - a builder brand may file through several entities.
Who are the directors of ELDECO Housing and Industries Ltd.?
ELDECO Housing and Industries Ltd. disclosed 7 directors or partners to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.
When was ELDECO Housing and Industries Ltd. registered with RERA?
ELDECO Housing and Industries Ltd. has been registered with UPRERA since 26 Jul 2017.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗