Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
9.58%Q3'25
1.4%Q4'25
3.52%Q1'26
5.65%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ752382
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryYamuna Expressway Authority
Proposed start18 Jul 2025
Project duration60 months
AddressPlot no. GH-01C/1, Sector -22D, Yamuna Expressway Industrial Development Authority, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressS-16, Eldeco Station 1, Site No. 1, Sector 12, Faridabad, Haryana-121007
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    YEA/PLANNING/815/2025

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered2 Sept 2025
Original completion17 Jul 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,06,500
Sanctioning authorityYamuna Expressway Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors574 · 4 · 34 (units from plan)
Homes · commercial units558 · 16 (shops and offices filed in the same plan)
  • 3 BHK534 93%
  • PENTHOUSE18 3%
  • SHOP16 3%
  • 2 BHK6 1%
ConfigurationUnitsCarpet area
3 BHK53481-98
2 BHK665
SHOP164-32
PENTHOUSE1882-99
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
ELDECO WONDER PLAZA/ RETAIL · SHOP21232-32
SALOME BLOCK 01 · OTHER, 3 BHK, 2 BHK, PENTHOUSE3418665-99
SERENITY BLOCK 03 · OTHER, 3 BHK, 2 BHK, PENTHOUSE3418665-99
SOLACE BLOCK 02 · OTHER, SHOP, 3 BHK, 2 BHK, PENTHOUSE341904-99
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
AR. SANJAY SHEE
License CA/2001/28449
A3-202, LIFESTYLE HOMES, SECTOR-83, GURGAON 122004
Engineer
SRI P.SREENIVASA CHARY
FLAT NO 3001, RATNAPUNIT APARTMENT, STREET NO 8, MYLARGADDA, SECUNDRABAD 500061
Contractor
A. S. BUILDTECH ENGINEERS PVT. LTD.
B-006 SECTOR 105 NOIDA up
Sr.Development work declared to RERA
1Demarcation of Plots
Proposed group housing is a part of Development Plan by YIEDA spread over an area of 20235 sqmt.
2Boundary Wall
Boundary/ Railing shall be as per design 1650mm from internal road level
3Road Work
CC/ Paver internal road along with side pavement shall be constructed as per approved layout.
4Footpaths
Continuous linked Pathway in the complex provided to enable people to have a walkable neighbourhood
5Water Supply Including Drinking Water Facilities
Water supply from underground tank shall be pumped to the Overhead tank on terrace A well designed plumbing system shall be there to supply drinking water to the units through downcomer.
6Sewer System
A well designed sewerage system shall be laid to collect soil/ water waste which in turn connect to the main sewer line.
7Drain
A well designed system of covered and underground drains shall be in place
8Parks
All the green pockets shall have grass covered with a minimum paved area and sitting/ playing arrangements . Low height plantation shall be a part of it.
9Tree Planting
4.5-6 m high trees shall be along the main running internal roads.
10Design For Electric Supply Including Street Lighting
Connection from LESA to be obtained for required electrical load for street lighting and complex requirement in general . Total requirement 2027.07 kW
11Community Buildings
A well designed community building is a part of the scheme. Club with an area of 1193 sqmt.
12Treatment and Disposal System of Sewage and Sullage water
A well designed STP of capacity approx 220 kLD in place to take care of sewage and sullage
13Solid Waste Management And Disposal System
Collection and Disposal of solid waste will be Co-ordinated with YIEDA
14Water Conservation System
All terrace storm water shall be harvested to recharge ground water . Waste water shall be recycled and used for irrigation / gardening
15Energy Management System Including Use of Renewable Energy
25 percent of street lights will have solar energy back up. Common Area light shall be brightness sensitive to save energy. BEE5 star rating DG set of capacity 2X 750 kVA and 1X 500 kVA CPCB approved
16Fire Protection And Fire Safety System
A well designed FF system / evacuation arrangements shall be in place with FAS , pressurized Fire escapes, Downcomer Fire Extinguisher.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Club and kids play area shall be provided
18Emergency Evacuation Services
All the exit points with adequate width as per norms available to facilitate evacuation in case of emergency
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 17 Jul 2030.

Sanctioned by Yamuna Expressway Authority · 20,235 sqm of land · an approved plan of 4 blocks and 574 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
YEA/PLANNING/815/202518 Jul 202517 Jul 203017 Jul 203517 Jul 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

25 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-01C/120235Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 21565
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · YEA/GH01/4151/2025
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
General body resolution
The resolution authorising an apartment owners’ association to act as the registering entity.
not reported—
Affidavit on balance development work
The promoter’s sworn statement about the development work still to be finished.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New22 Jul 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New22 Jul 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New22 Jul 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New22 Jul 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New22 Jul 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New22 Jul 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New21 Jul 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New22 Jul 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New8 Aug 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Aug 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Aug 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Aug 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New6 Aug 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New22 Jul 2025 ↗

Quarterly progress reports

4 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

4 quarterly progress reports are on file with UPRERA, covering 2025-Q2 to 2026-Q1.

QuarterConstructionCertificates
2025-Q29.58%CA ↗ · Arch ↗ · Eng ↗
2025-Q31.4%CA ↗ · Arch ↗ · Eng ↗
2025-Q43.52%CA ↗ · Arch ↗ · Eng ↗
2026-Q15.65%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameEldeco Sohna Projects Limited
RolePromoter · current
RERA IDUPRERAPRM377130
PANAAFCA9260N
CIN / TANU45200HR2006PLC073744
Registered addressS-16, Eldeco Station 1, Site No. 1, Sector 12, Faridabad, Haryana-121007
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
ELDECO SOHNA PROJECTS LTD- COLL A/C FOR ELDECO WHISPERS OF WONDER-ESCBankHDFC BANKBranchELDECO STUDIO APARTMENT, NOIDABranch addressPLOT NO 3, ELDECO STUDIO APARTMENT, SECTOR 93A, NOIDA-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002830Branch emailnadeem.siddique@hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
ELDECO SOHNA PROJECTS LTD-SEP A/C FOR ELDECO WHISPERS OF WONDER-ESCBankHDFC BANKBranchELDECO STUDIO APARTMENT, NOIDABranch addressPLOT NO.3, ELDECO STUDIO APARTMENT, SECTOR-93A, NOIDA-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002830
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
ELDEDCO SOHNA PROJECTS LTD- TRAN A/C FOR ELDECO WHISPERS OF WONDER-ESCBankHDFC BANKBranchELDECO STUDIO APARTMENT, NOIDABranch addressPLOT NO.3, ELDECO STUDIO APARTMENT, SECTOR-93A, NOIDA-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002830
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Eldeco Whispers of Wonder

Is Eldeco Whispers of Wonder RERA registered?

Yes. Eldeco Whispers of Wonder is registered with UPRERA under registration number UPRERAPRJ752382, registered on 2 Sept 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Eldeco Whispers of Wonder?

The completion date filed with UPRERA is 17 Jul 2030. No completion certificate is on record yet.

Who is the builder of Eldeco Whispers of Wonder?

Eldeco Sohna Projects Limited is the promoter entity that filed Eldeco Whispers of Wonder with UPRERA (promoter RERA ID UPRERAPRM377130). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Eldeco Whispers of Wonder have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Eldeco Whispers of Wonder located?

Eldeco Whispers of Wonder is registered in Sector -22D, Yamuna Expressway Industrial Development Authority, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Eldeco Whispers of Wonder?

The unit plan filed with UPRERA lists OTHER, 3 BHK, 2 BHK, SHOP and PENTHOUSE. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Eldeco Whispers of Wonder?

The approved unit plan filed with UPRERA runs from 4 to 99 m² of carpet area (about 43 to 1,065 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Eldeco Whispers of Wonder?

The approved unit plan describes 4 blocks and 574 units of which 558 are homes and 16 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Eldeco Whispers of Wonder?

About 115 units per acre: 574 planned units across 5.00 acres (20,235 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗