RPS-02, SEC-22D is a RERA-registered residential project by Yamuna Expressway Industrial devlopment Authority in Gautam Budh Nagar (RERA ID UPRERAPRJ8756). Registered with a completion deadline of 8 Mar 2021.
RERA status as reported: Registered.Construction progress
Construction stayed at 0% across 3 consecutive filed quarters (Apr–Jun 2020 to Oct–Dec 2020). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ8756 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Yamuna Expressway Authority |
| Proposed start | 11 Aug 2017 |
| Original start | 11 Aug 2017 |
| Project duration | 43 months |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| Tehsil | Gautam Buddha Nagar |
| Applicant type | Competent authority |
| Applicant address | 1st Floor , Commercial Complex , Block-P2, Sec- Omega 1, Greater Noida - 201308 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
PLNG/DS/05/N-30
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 9 Aug 2017 |
| Original completion | 10 Sept 2019 |
| Revised completion | 8 Mar 2021 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹6,98,000 |
| Sanctioning authority | Yamuna Expressway Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots after development work |
| 2 | Boundary Wall estimate in process |
| 3 | Road Work work in progress |
| 4 | Footpaths work in progress |
| 5 | Water Supply Including Drinking Water Facilities work in progress |
| 6 | Sewer System work in progress |
| 7 | Drain after development work |
| 8 | Parks after development work |
| 9 | Tree Planting planting after development work |
| 10 | Design For Electric Supply Including Street Lighting under planning |
| 11 | Community Buildings under planning |
| 12 | Treatment and Disposal System of Sewage and Sullage water estimate in process |
| 13 | Solid Waste Management And Disposal System under process |
| 14 | Water Conservation System under planning |
| 15 | Energy Management System Including Use of Renewable Energy nill |
| 16 | Fire Protection And Fire Safety System under process |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services under planning |
| 18 | Emergency Evacuation Services under planning |
| 19 | Other Miscellaneous Work nill |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 10 Sept 2019.
Sanctioned by Yamuna Expressway Authority · 1,38,600 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| PLNG/DS/05/N-30 | 11 Sept 2014 | 10 Sept 2019 | 10 Sept 2019 | 10 Sept 2019 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | no file published |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
UPRERA’s record carries 2 completion extensions for this project, the latest running to 8 Mar 2021.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 10 Sept 2019 | 9 Sept 2020 | — |
| 2 | 9 Sept 2020 | 8 Mar 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
14 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| SECTOR 22D | 138600 | Plot |
| Allotment letter from the authority · BN 061390 The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | not reported | — |
| Water supply plan How the project proposed to supply water, as filed at registration. | not reported | — |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | not reported | — |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 29 Jul 2018 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 29 Jul 2018 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 29 Jul 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 29 Jul 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 30 Jul 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 29 Jul 2018 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | As per NBC |
| Fire safety (as filed with RERA) | As per NBC |
| Health service | As per NBC |
| Renewable energy | As per NBC |
| Other facilities | As per NBC |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
4 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
4 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2020-Q4.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Yamuna Expressway Industrial devlopment Authority |
| Role | Promoter · current |
| RERA ID | UPRERAPRM14529 |
| PAN | AAALT0341D |
| CIN / TAN | MRTT00283D |
| Registered address | 1st Floor , Commercial Complex , Block-P2, Sec- Omega 1, Greater Noida - 201308 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Gautam Budh Nagar
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | Individual residential plots, Sec-22D,YEIDABankOriental Bank of CommerceBranchJagat FarmA/C no.IFSCORBC0100898 |
What has changed on this record
6 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 337 (Under Registration - 1 ) → 338 (Under Registration - 2 ) changed in Estanzo’s record | 15 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 336 (Under Registration - 0 ) → 337 (Under Registration - 1 ) changed in Estanzo’s record | 3 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 336 (Under Registration - 1 ) → 336 (Under Registration - 0 ) changed in Estanzo’s record | 23 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 336 (Under Registration - 3 ) → 336 (Under Registration - 1 ) changed in Estanzo’s record | 21 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 335 (Under Registration - 2 ) → 336 (Under Registration - 3 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | 334 (Under Registration - 1 ) → 335 (Under Registration - 2 ) changed in Estanzo’s record | 16 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 15 Oct 2026 · 6 movements on record |
What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
Common questions about RPS-02, SEC-22D
Is RPS-02, SEC-22D RERA registered?
Yes. RPS-02, SEC-22D is registered with UPRERA under registration number UPRERAPRJ8756, registered on 9 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for RPS-02, SEC-22D?
The completion date filed with UPRERA is 8 Mar 2021. No completion certificate is on record yet.
Who is the builder of RPS-02, SEC-22D?
Yamuna Expressway Industrial devlopment Authority is the promoter entity that filed RPS-02, SEC-22D with UPRERA (promoter RERA ID UPRERAPRM14529). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted RPS-02, SEC-22D more time to complete?
UPRERA's record carries 2 completion extensions for RPS-02, SEC-22D, the latest running to 8 Mar 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does RPS-02, SEC-22D have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is RPS-02, SEC-22D located?
RPS-02, SEC-22D is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗