ELITE is a RERA-registered mixed project by AGRASEN REALTORS & DEVELOPERS PRIVATE LIMITED in Lacchipur, Gorakhpur (RERA ID UPRERAPRJ954073). Registered with a completion deadline of 21 Jul 2029.
RERA status as reported: Registered.Construction progress
Construction stayed at 0.45% across 4 consecutive filed quarters (Jul–Sep 2025 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ954073 |
| Project category | Mixed |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Gorakhpur Development Authority |
| Proposed start | 24 Aug 2024 |
| Project duration | 59 months |
| Address | Sonauli Road, Gorakhpur, Lacchipur, Gorakhpur, Gorakhpur |
| Tehsil | Gorakhpur |
| Applicant type | Company |
| Applicant address | WZ-106/136 RAJOURI GARDEN EXT. NEAR CAMBRIDGE FOUNDATION SCHOOL, NEW DELHI - 110027 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
Group Housing/05829/GKDA/BP/23-24/1883/13032024
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 10 Oct 2024 |
| Original completion | 21 Jul 2029 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹59,250 |
| Sanctioning authority | Gorakhpur Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK78 55%
- SHOP54 38%
- 5 BHK8 6%
- OTHER2 1%
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 54 | 17-40 |
| OTHER | 2 | 735-737 |
| 3 BHK | 78 | 119-128 |
| 5 BHK | 8 | 100-113 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Elite Heights · OTHER, 3 BHK, 5 BHK | 12 | 86 | 100-128 |
| Elite Square · SHOP, OTHER | 5 | 56 | 17-40 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots We possess a plot measuring 6888.60 square meters with primary entrance gate that opens onto a 32-meter wide main road. |
| 2 | Boundary Wall A 2-meter high, 230-mm thick brick wall with RCC columns and beams will be constructed. At the corner facing the road, the project logo will be displayed, creating an attractive, iconic design for the entrance gate. |
| 3 | Road Work From the main entrance gate, there will be an interlocking brick or RCC road throughout the project, with a width starting at 6 meters. |
| 4 | Footpaths We will not be providing any footpath. |
| 5 | Water Supply Including Drinking Water Facilities We will install 2 pumps to meet the requirements of the blocks through underground pipelines. |
| 6 | Sewer System An MBBR sewage treatment system will be installed. All sewage water will be directed to the STP, and any overflow from the STP will be connected to the municipal sewerage system once it is operational. |
| 7 | Drain A storm water drainage system will be provided. Storm water from the roads and landscaped areas will be directed to the storm water drain channel and then to the rainwater harvesting pit to recharge the groundwater. Any overflow will be connected to the municipal drain line. |
| 8 | Parks We will create a green area featuring various activities, including gaming facilities for children. |
| 9 | Tree Planting We will plant various types of trees along the boundary wall and in the green areas. |
| 10 | Design For Electric Supply Including Street Lighting We will design and implement the system in accordance with the local electricity boards regulations, incorporating a centralized transformer, HT panel, LT panel, feeder pillar, and DG backup for common services such as external lighting, fountains, STP, and the pump room. |
| 11 | Community Buildings A clubhouse will be provided at ground floor level, featuring a gymnasium, a multipurpose hall, and a card room. |
| 12 | Treatment and Disposal System of Sewage and Sullage water An MBBR sewage treatment system will be installed. All sewage water will be directed to the STP, and any overflow from the STP will be connected to the municipal sewerage system once it is operational. |
| 13 | Solid Waste Management And Disposal System A designated area for proper garbage collection is provided for solid waste management. |
| 14 | Water Conservation System We will install low-flow fixtures, dual flush cisterns, and a rainwater harvesting system to decrease water consumption and enhance groundwater levels. |
| 15 | Energy Management System Including Use of Renewable Energy We will utilize LED lighting in external and common areas, along with solar lights in landscaped zones. All engineering equipment will be energy-efficient, and we will also recommend that individuals use LED lights and energy-efficient air conditioning systems. |
| 16 | Fire Protection And Fire Safety System All norms of National Builing Code and Local Fire Authority recommendations will be complied with. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services Staircases will be equipped with emergency exit doors. |
| 19 | Other Miscellaneous Work NA |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 21 Jul 2029.
Sanctioned by Gorakhpur Development Authority · 6,889 sqm of land · an approved plan of 2 blocks and 142 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| Group Housing/05829/GKDA/BP/23-24/1883/13032024 | 22 Jul 2024 | 21 Jul 2029 | 21 Jul 2032 | 21 Jul 2029 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
Land & documents
16 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 619 Mi | 6888.6 | Khasra |
| Registry document · 1629 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Khatauni extract · 1429-1434 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Land division An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 28 Aug 2024 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 28 Aug 2024 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 28 Aug 2024 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 28 Aug 2024 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 28 Aug 2024 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 28 Aug 2024 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 28 Aug 2024 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 28 Aug 2024 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 28 Aug 2024 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 5 Sept 2024 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 28 Aug 2024 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 28 Aug 2024 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 28 Aug 2024 ↗ |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | New | 28 Aug 2024 ↗ |
Quarterly progress reports
8 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
8 quarterly progress reports are on file with UPRERA, covering 2024-Q2 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 0.45% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 0.45% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 0.45% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 0.45% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | AGRASEN REALTORS & DEVELOPERS PRIVATE LIMITED |
| Role | Promoter · current |
| RERA ID | UPRERAPRM310302 |
| PAN | AAJCA6474C |
| CIN / TAN | U45100DL2011PTC221947 |
| Name of chairman | VIKAS KEJRIWAL |
| Registered address | WZ-106/136 RAJOURI GARDEN EXT. NEAR CAMBRIDGE FOUNDATION SCHOOL, NEW DELHI - 110027 |
| RERA contact | |
| Registered since | 2024 |
| Legal name | MOHD TARIQ SAYEED |
| Role | Co-promoter |
| Applicant type | Individual |
| Address | S/O MOHD HAMID ALI, H.NO 661/12 2ND FLOOR GALI NO 12 ZAKIR NAGAR OKNIA SOUTH DELHI |
| RERA contact |
| Legal name | MAHBOOB SAYEED |
| Role | Co-promoter |
| Applicant type | Individual |
| Address | S/O MU HAMID ALI,GULFISHAAN SAJID ALI ROAD, QAZIPUR KHURD, GORAKHPUR, UTTARPRADESH 273001 |
| RERA contact |
| Legal name | ASIF SAYEED |
| Role | Co-promoter |
| Applicant type | Individual |
| Address | S/O MOHAMMAD HAMID ALI GULFESHAN SAJID ALI ROAD,QAZIKHURD, GORAKHPUR UTTAR PRADESH 273001 |
| RERA contact |
Nearby projects
Gorakhpur
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | ARDPL RERA COLLECTION ACCOUNT ELITEBankPunjab National BankBranchBank Road, GorakhpurBranch addressBank Road, GorakhpurBranch districtGorakhpurA/C no.IFSCPUNB0038410Branch emailbo038410@pnb.co.in |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | ARDPL RERA SEPERATE AC ELITEBankPunjab National BankBranchBank Road, GorakhpurBranch addressBank Road, GorakhpurBranch districtGorakhpur, Uttar PradeshA/C no.IFSCPUNB0038410 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | ARDPL RERA TRANSACTION ACCOUNT ELITEBankPunjab National BankBranchBank Road, GorakhpurBranch addressBank Road, GorakhpurBranch districtGorakhpur, Uttar PradeshA/C no.IFSCPUNB0038410 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about ELITE
Is ELITE RERA registered?
Yes. ELITE is registered with UPRERA under registration number UPRERAPRJ954073, registered on 10 Oct 2024. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for ELITE?
The completion date filed with UPRERA is 21 Jul 2029. No completion certificate is on record yet.
Who is the builder of ELITE?
AGRASEN REALTORS & DEVELOPERS PRIVATE LIMITED is the promoter entity that filed ELITE with UPRERA (promoter RERA ID UPRERAPRM310302). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does ELITE have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is ELITE located?
ELITE is registered in Lacchipur, Gorakhpur, as filed with UPRERA.
What configurations are available in ELITE?
The unit plan filed with UPRERA lists SHOP, OTHER, 3 BHK and 5 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in ELITE?
The approved unit plan filed with UPRERA runs from 17 to 737 m² of carpet area (about 187 to 7,931 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in ELITE?
The approved unit plan describes 2 blocks and 142 units of which 88 are homes and 54 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is ELITE?
About 83 units per acre: 142 planned units across 1.70 acres (6,889 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗