Registered12 Nov 2018
Completed29 Feb 2020
Promised15 Nov 2020

Timeline

Promised completion15 Nov 2020
Revised completion15 Nov 2020
Actual completion29 Feb 2020
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,76,500
Project cost (in ₹ Lakhs)₹2,520 Lakhs
Project duration24 months
Project categoryResidential
Locality
Original start date
Proposed start date18 Nov 2018

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8009551300
Emailcsd@rituhousing.com
Coordinator8009551300
AddressKAMLA TOWER, KANPUR, U.P.-208001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
263/BHAWAN/ONLINE/2018-1911 Oct 201810 Oct 202315 Nov 202010 Oct 2026

Land Parcels

Khasra No.AreaPlot Type
PART OF PLOT NO. 2, SCHEME NO. 39, JAJMAU, KANPUR34274.92Plot

Frequently Asked Questions

What is the RERA registration number of EMERALD GULISTAN PHASE-II?

The RERA registration number of EMERALD GULISTAN PHASE-II is UPRERAPRJ17995, as recorded on the UP-RERA portal.

What is the RERA status of EMERALD GULISTAN PHASE-II?

As reported by UP-RERA, the status of EMERALD GULISTAN PHASE-II is "Registered".

Where is EMERALD GULISTAN PHASE-II located?

As reported to UP-RERA, EMERALD GULISTAN PHASE-II is located at Kanpur, Kanpur Nagar, Uttar Pradesh.

Is EMERALD GULISTAN PHASE-II completed?

As reported to UP-RERA, EMERALD GULISTAN PHASE-II was completed on 29 Feb 2020.

Is EMERALD GULISTAN PHASE-II delayed?

Measured against the latest completion date reported to UP-RERA, EMERALD GULISTAN PHASE-II is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026