Timeline Bar
Registered22 Dec 2020
Completed23 Feb 2022
Promised31 Mar 2022
Timeline
Promised completion31 Mar 2022
Revised completion31 Mar 2022
Actual completion23 Feb 2022
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹1,28,000
Project cost (in ₹ Lakhs)₹1,162 Lakhs
Project duration16 months
Project categoryResidential
Locality—
Original start date—
Proposed start date1 Dec 2020
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8009551300
Emailcsd@rituhousing.com
Coordinator8009551300
AddressKAMLA TOWER, KANPUR, U.P.-208001
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 1055/BHAWAN/ONLINE/2018-19 | 29 Jun 2019 | 28 Jun 2024 | 31 Mar 2022 | 28 Jun 2025 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| PART OF PLOT NO. 2, SCHEME NO. 39, JAJMAU, KANPUR | 24534.46 | Plot |
Frequently Asked Questions
What is the RERA registration number of EMERALD GULISTAN PHASE-III?
The RERA registration number of EMERALD GULISTAN PHASE-III is UPRERAPRJ542474, as recorded on the UP-RERA portal.
What is the RERA status of EMERALD GULISTAN PHASE-III?
As reported by UP-RERA, the status of EMERALD GULISTAN PHASE-III is "Registered".
Where is EMERALD GULISTAN PHASE-III located?
As reported to UP-RERA, EMERALD GULISTAN PHASE-III is located at Kanpur, Kanpur Nagar, Uttar Pradesh.
Is EMERALD GULISTAN PHASE-III completed?
As reported to UP-RERA, EMERALD GULISTAN PHASE-III was completed on 23 Feb 2022.
Is EMERALD GULISTAN PHASE-III delayed?
Measured against the latest completion date reported to UP-RERA, EMERALD GULISTAN PHASE-III is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026