Experion Capital Phase-1 is a RERA-registered residential project by Experion Developers Pvt. Ltd in Lucknow (RERA ID UPRERAPRJ4224). Registered with a completion deadline of 24 May 2024.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ4224 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 1 Dec 2017 |
| Project duration | 78 months |
| Address | Lucknow, Lucknow |
| Tehsil | Lucknow |
| Applicant type | Company |
| Applicant address | Registered Address -F-9, Ist Floor, Manish Plaza I, Plot -7, MLU, Sector 10, Dwarka, New Delhi – 110 075 Corporate Address Second Floor, Plot No.-18, Sector-32, Gurugram, Haryana |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
- valid to
Permit revalidated
41210
3 building permits sanctioned
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
- valid to
Permit revalidated
MAP-20181011115032947
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
Completion certificate filed
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 29 Jul 2017 |
| Original completion | 30 Nov 2022 |
| Revised completion | 24 May 2024 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 3 Oct 2023 |
| Registration fee | ₹77,500 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- OTHER137 42%
- 3 BHK134 41%
- SHOP57 17%
- 1 BHK2 1%
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 2 | 46-53 |
| 3 BHK | 134 | 82-111 |
| SHOP | 57 | 30-227 |
| OTHER | 137 | 6-122 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Commercial · SHOP, OTHER | 7 | 192 | 6-122 |
| Commercial Cum Club · SHOP | 1 | 2 | 84-227 |
| Tower T1 · 1 BHK, 3 BHK | 17 | 68 | 46-82 |
| Tower T2 · 1 BHK, 3 BHK | 17 | 68 | 53-111 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots The project site admeasuring is located adjacent to the new high court complex towards north and Indira Gandhi pratishthan Bhawan towards east at Gomti Nagar Lucknow |
| 2 | Boundary Wall Boundary wall shall be constructed as per approved layout plan. |
| 3 | Road Work 6m wide internal roads shall be provided as per approved layout plan. |
| 4 | Footpaths Footpaths shall be provided as per the Landscape scheme. |
| 5 | Water Supply Including Drinking Water Facilities Municipal supplied water from Jal kal Vibhag will be treated for domestic purposes as per norms. |
| 6 | Sewer System Sewerage from house holds shall be treated in S.T.P. |
| 7 | Drain Storm water shall be collected and recharged in ground. Final overflow to be connected with municipal drainage system if required |
| 8 | Parks Green Area shall be provided as per the approved layout plan. |
| 9 | Tree Planting Evergreen flowering trees shall be provided as per the Landscape plan. |
| 10 | Design For Electric Supply Including Street Lighting Direct supply of electricity shall be supplied by UPPCL design as per their norms . Street lights shall be provided as per N.B.C. |
| 11 | Community Buildings Club shall be provided for residential owners only. |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP will be provided to treat sewage and treated water will be used for flushing and gardening. |
| 13 | Solid Waste Management And Disposal System Solid waste shall be collected and disposed through Municipal approved vendor. |
| 14 | Water Conservation System Low flow fixtures shall be provided. |
| 15 | Energy Management System Including Use of Renewable Energy Energy conservation measures like use of solar energy in street lighting at 20% of overall street lights. |
| 16 | Fire Protection And Fire Safety System Fire protection and fire safety system shall be as per N.B.C 2005. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Roads ,fire tender paths, club including swimming pool and green area shall be provided. |
| 18 | Emergency Evacuation Services Emergency evacuation services shall be provided as per N.B.C 2005. |
| 19 | Other Miscellaneous Work Internal road and Green Area shall be provided . |
Registered agents
19 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | 360 REALTORS LLP | UPRERAAGT10868 |
| 2 | AMIT KUMAR NISHAD | UPRERAAGT14016 |
| 3 | ASA FINCAP ADVISORS LLP | UPRERAAGT10926 |
| 4 | GOLDEN ESTATE | UPRERAAGT10397 |
| 5 | M.S. Property Consultants L.L.P. | UPRERAAGT10074 |
| 6 | RANVEER PROPERTIES | UPRERAAGT10234 |
| 7 | RELIVE SOLUTIONS PVT. LTD. | UPRERAAGT10078 |
| 8 | SANJEEV KUMAR BANKA | UPRERAAGT10894 |
| 9 | SANTOSH KUMAR | UPRERAAGT10156 |
| 10 | SDR INFRA BUILD PVT LTD | UPRERAAGT11062 |
| 11 | SG CONSTRUCTIONS | UPRERAAGT13538 |
| 12 | SILVER EDGE REAL ESTATE SOLUTION | UPRERAAGT12168 |
| 13 | STRAIGHTEDGE REAL ESTATE PRIVATE LIMITED | UPRERAAGT10067 |
| 14 | Surender Singh | UPRERAAGT13452 |
| 15 | VANDANA AGARWAL | UPRERAAGT13353 |
| 16 | Varun Properties Inc. | UPRERAAGT11985 |
| 17 | VIKAS PANDEY | UPRERAAGT11324 |
| 18 | vikram Jeet Singh Chadha | UPRERAAGT10805 |
| 19 | VIRENDRA KUMAR DEWAN | UPRERAAGT13205 |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 11 Jan 2022. 2 of them carry a revalidation, the latest valid to 11 Jan 2025.
Sanctioned by Lucknow Development Authority · 14,487 sqm of land · an approved plan of 4 blocks and 330 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 41210 | 12 Jan 2017 | 11 Jan 2022 | 11 Jan 2025 | 30 Nov 2022 | — | |
| 41210 | 12 Jan 2017 | 11 Jan 2022 | 29 May 2023 | 11 Jan 2022 | 14 Jul 2020 valid to 11 Jan 2022 as MAP-20181011115032947 | |
| 41210 | 12 Jan 2017 | 11 Jan 2022 | 7 Jun 2025 | 11 Jan 2022 | 12 Jan 2017 valid to 11 Jan 2025 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
UPRERA’s record carries 2 completion extensions for this project, the latest running to 24 May 2024.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 30 Nov 2022 | 29 May 2023 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 29 May 2023 | 24 May 2024 | — |
Land & documents
18 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| TCG 1-A/V6 | 9409.95 | Plot |
| TCG 1-A/V7 | 18164 | Plot |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 9 Apr 2008.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 3516 | 9 Apr 2008 | self | — |
| Sale deed · 994 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 3516 The registered deed by which the promoter bought the land. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 25 Jan 2021 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 25 Jan 2021 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 25 Jan 2021 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 3 Aug 2018 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 3 Aug 2018 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 3 Aug 2018 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 25 Jan 2021 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 3 Aug 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 3 Aug 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 3 Aug 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 3 Aug 2018 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 28 Nov 2017 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | Old | 29 Nov 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 29 Nov 2017 ↗ |
Quarterly progress reports
13 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
13 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Experion Developers Pvt. Ltd |
| Role | Promoter · current |
| RERA ID | UPRERAPRM3669 |
| PAN | AACCG8138L |
| CIN / TAN | U70109DL2006FTC151343 |
| Name of chairman | Mr. Basavaraddi Krishnaraddi Malagi |
| Registered address | Registered Address -F-9, Ist Floor, Manish Plaza I, Plot -7, MLU, Sector 10, Dwarka, New Delhi – 110 075 Corporate Address Second Floor, Plot No.-18, Sector-32, Gurugram, Haryana |
| RERA contact | |
| Registered since | 2017 |
| Legal name | A.G. Housing & properties Private Limited |
| Role | Co-promoter · current |
| RERA ID | UPRERAPRM2461 |
| Applicant type | Company |
| PAN | AAICA6285G |
| CIN / TAN | U74900UP2010PTC040823 |
| Name of chairman | Manoj Agarwal , Anurag Agarwal, Vikas Agarwal |
| Registered address | B-18, Sector-B, Aliganj, Lucknow B-18, Sector-B, Aliganj, Lucknow B-21, Sector-B, Aliganj, Lucknow |
| RERA contact | |
| Registered since | 2017 |
| Legal name | EXPERION HOSPITALITY PRIVATE LIMITED |
| Role | Co-promoter |
| Applicant type | Company |
| Address | Registered Address -F-9, Ist Floor, Manish Plaza I, Plot -7, MLU, Sector 10, Dwarka, New Delhi – 110 075 Corporate Address Second Floor, Plot No.-18, Sector-32, Gurugram, Haryana |
| RERA contact |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | Experion Developers Private LimitedBankState Bank of IndiaBranch36 Janpath, New DelhiA/C no.IFSCSBIN0050732 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 6 (Under Registration - 1 ) → 6 (Under Registration - 0 ) changed in Estanzo’s record | 13 Sept 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 13 Sept 2026 |
What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
- No architect, engineer or contractor is published for this project.Ask who the architect and engineer of record are - they are the professionals who certify each quarterly filing.
Common questions about Experion Capital Phase-1
Is Experion Capital Phase-1 RERA registered?
Yes. Experion Capital Phase-1 is registered with UPRERA under registration number UPRERAPRJ4224, registered on 29 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has Experion Capital Phase-1 been completed?
UPRERA still lists Experion Capital Phase-1 as Registered, so it is not shown as completed here. A completion certificate dated 3 Oct 2023 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of Experion Capital Phase-1?
Experion Developers Pvt. Ltd is the promoter entity that filed Experion Capital Phase-1 with UPRERA (promoter RERA ID UPRERAPRM3669). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Experion Capital Phase-1 more time to complete?
UPRERA's record carries 2 completion extensions for Experion Capital Phase-1, the latest running to 24 May 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Experion Capital Phase-1 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Experion Capital Phase-1 located?
Experion Capital Phase-1 is registered in Lucknow, as filed with UPRERA.
What configurations are available in Experion Capital Phase-1?
The unit plan filed with UPRERA lists 1 BHK, 3 BHK, SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Experion Capital Phase-1?
The approved unit plan filed with UPRERA runs from 6 to 227 m² of carpet area (about 67 to 2,441 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Experion Capital Phase-1?
The approved unit plan describes 4 blocks and 330 units of which 273 are homes and 57 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Experion Capital Phase-1?
About 92 units per acre: 330 planned units across 3.58 acres (14,487 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗