GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I is a RERA-registered residential project by GANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED in Agra (RERA ID UPRERAPRJ5789). Registered with a completion deadline of 30 Sept 2021.
RERA status as reported: Registered.Construction progress
Construction stayed at 93% across 6 consecutive filed quarters (Apr–Jun 2020 to Jul–Sep 2021). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ5789 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Agra Development Authority |
| Proposed start | 1 Apr 2016 |
| Project duration | 66 months |
| Address | Agra, Agra |
| Tehsil | Agra |
| Applicant type | Company |
| Applicant address | 31/472 C1,IST FLORE ,GANASH PLAZA SULTAN GANJ PULIYA PIPASS ROAD AGRA |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Building permit sanctioned
06/BFS/SA/16-17 AND 901/AB-1/SAY-DPR/2016
Registered with RERA
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 2 Aug 2017 |
| Original completion | 31 Mar 2021 |
| Revised completion | 30 Sept 2021 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹86,000 |
| Sanctioning authority | Agra Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 2 BHK610 73%
- 1 BHK230 27%
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 230 | 27 |
| 2 BHK | 610 | 40-43 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| GOMTI TOWER-002 · 1 BHK | 10 | 230 | 27 |
| SUTLEJ TOWER 002 · 2 BHK | 10 | 140 | 40 |
| SUTLEJ TOWER 003 · 2 BHK | 10 | 130 | 40-43 |
| SUTLEJ TOWER 004 · 2 BHK | 10 | 110 | 40 |
| SUTLEJ TOWER 005 · 2 BHK | 10 | 100 | 40 |
| SUTLEJ TOWER-1 · 2 BHK | 10 | 130 | 40 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots YES |
| 2 | Boundary Wall YES |
| 3 | Road Work YES |
| 4 | Footpaths YES |
| 5 | Water Supply Including Drinking Water Facilities YES |
| 6 | Sewer System YES |
| 7 | Drain YES |
| 8 | Parks YES |
| 9 | Tree Planting YES |
| 10 | Design For Electric Supply Including Street Lighting YES |
| 11 | Community Buildings YES |
| 12 | Treatment and Disposal System of Sewage and Sullage water YES |
| 13 | Solid Waste Management And Disposal System YES |
| 14 | Water Conservation System YES |
| 15 | Energy Management System Including Use of Renewable Energy NO |
| 16 | Fire Protection And Fire Safety System YES |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services YES |
| 18 | Emergency Evacuation Services NO |
| 19 | Other Miscellaneous Work YES |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 19 Jul 2021.
Sanctioned by Agra Development Authority · 16,115 sqm of land · an approved plan of 6 blocks and 840 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 06/BFS/SA/16-17 AND 901/AB-1/SAY-DPR/2016 | 20 Jul 2016 | 19 Jul 2021 | 19 Jul 2024 | 31 Mar 2021 |
UPRERA’s record carries 1 completion extension for this project, running to 30 Sept 2021.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 31 Mar 2021 | 30 Sept 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
12 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 6/2 | 6720 | — |
| 8 | 2100 | — |
| 9 | 1164.85 | — |
| 10 | 1270 | — |
| 11 | 580 | — |
| 12 | 2300 | — |
| 13 | 2420 | — |
| 14 | 1960 | — |
| 16 | 4490 | — |
| 17 | 2190 | — |
| 18 | 1730 | — |
| 19 | 690 | — |
5 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 18 Jan 2014.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 3028 | 24 Sept 2014 | self | — |
| 2016 | 26 Dec 2014 | self | — |
| 3792 | 23 Aug 2014 | self | — |
| 1392 | 3 Jul 2014 | self | — |
| 4059 | 18 Jan 2014 | self | — |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | AVAILABLE |
| Fire safety (as filed with RERA) | AVAILABLE |
| Other facilities | PARK, KIDS PARK, RCC ROADS, 24X7 SECURITY, CONVINIENT SHOPS, SMART BUS SERVICE |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
6 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
6 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | GANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED |
| Role | Promoter · current |
| RERA ID | UPRERAPRM2735 |
| PAN | AAECG6731F |
| CIN / TAN | U70102UP2012PLC049767 |
| Name of chairman | ANIL AGARWAL |
| Registered address | 31/472 C1,IST FLORE ,GANASH PLAZA SULTAN GANJ PULIYA PIPASS ROAD AGRA |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Agra
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | GIDCO UNNATI AWAS YOJNABankHDFC BANK LIMITEDBranchK G MARGA/C no.IFSCHDFC0000003 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 24 (Under Registration - 1 ) → 24 (Under Registration - 0 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 23 Aug 2026 |
Common questions about GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I
Is GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I RERA registered?
Yes. GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I is registered with UPRERA under registration number UPRERAPRJ5789, registered on 2 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I?
The completion date filed with UPRERA is 30 Sept 2021. No completion certificate is on record yet.
Who is the builder of GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I?
GANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED is the promoter entity that filed GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I with UPRERA (promoter RERA ID UPRERAPRM2735). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I more time to complete?
UPRERA's record carries 1 completion extension for GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I, the latest running to 30 Sept 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I located?
GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I is registered in Agra, as filed with UPRERA.
What configurations are available in GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I?
The unit plan filed with UPRERA lists 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I?
The approved unit plan filed with UPRERA runs from 27 to 43 m² of carpet area (about 292 to 462 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I?
The approved unit plan describes 6 blocks and 840 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is GANPATI SMART CITY/UNNATI AWAS YOJNA PHASE-I?
About 211 units per acre: 840 planned units across 3.98 acres (16,115 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗