Timeline Bar

Registered8 Mar 2018
Promised31 Mar 2022
Revised30 Sept 2022
Today4 Aug 2026

Timeline

Promised completion31 Mar 2022
Revised completion30 Sept 2022
Actual completion
Possession delay46 mo delay

Registration & Cost Details

Registration fee (in ₹)₹12,500
Project cost (in ₹ Lakhs)₹1,953 Lakhs
Project duration97 months
Project categoryResidential
Locality
Original start date
Proposed start date7 Mar 2018

Inventory

Total units588
Unit TypeUnitsCarpet Area (sqm)
1 BHK1037.8
2 BHK48039.65–54.8
3 BHK8472.2
SHOP1413.24

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9837009757
Emailrera@ganpatigroupindia.com
Coordinator9897200669
Address31/472 C1,IST FLORE ,GANASH PLAZA SULTAN GANJ PULIYA PIPASS ROAD AGRA

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q193.0%
2020-Q293.0%
2020-Q393.0%
2020-Q493.0%
2021-Q193.0%
2021-Q293.0%
2021-Q393.0%
2021-Q493.0%
2022-Q193.0%
2022-Q293.0%
2022-Q393.0%
2022-Q493.0%
2023-Q193.0%
2023-Q293.0%
2023-Q393.0%
2023-Q493.0%
2024-Q193.0%
2024-Q293.0%
2024-Q393.0%
2024-Q493.0%
2025-Q193.0%
2025-Q293.0%
2025-Q393.0%
2025-Q493.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
634/A V-1/S A Y -DPR/201611 Jul 201610 Jul 202131 Mar 202210 Jul 2024
634/A V-1/S A Y -DPR/201611 Jul 201610 Jul 202130 Sept 202231 Mar 2024
634/A V-1/S A Y -DPR/201611 Jul 201610 Jul 202130 Sept 202231 Mar 2024

Land Parcels

Khasra No.AreaPlot Type
1/4, 1/5, 1/13, 20 TO 25, 26/2, 42 TO 53, 56 8, 935385.15
1/4, 1/5, 1/13, 20 TO 25, 26/2, 42 TO 53, 56 8, 935385.15Khasra

Approved Unit Plan

Unit plan rows on file69
Total flats (sum of rows)588
Total shops14
BlocksCOMMERCIAL BLOCK 001, Kaveri Tower 002, Narmada Tower -3, SUTLEJ TOWER -1, kaveri Tower 003
Floor types1 BHK, 2 BHK, 3 BHK, SHOP

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
485827 Sept 2009
381428 Jul 2010
55637 Oct 2013
169713 Apr 2011

Frequently Asked Questions

What is the RERA registration number of UNNATI AWAS YOJNA - PHASE 3?

The RERA registration number of UNNATI AWAS YOJNA - PHASE 3 is UPRERAPRJ15396, as recorded on the UP-RERA portal.

What is the RERA status of UNNATI AWAS YOJNA - PHASE 3?

As reported by UP-RERA, the status of UNNATI AWAS YOJNA - PHASE 3 is "Registered".

Where is UNNATI AWAS YOJNA - PHASE 3 located?

As reported to UP-RERA, UNNATI AWAS YOJNA - PHASE 3 is located at Agra, Agra, Uttar Pradesh.

When will UNNATI AWAS YOJNA - PHASE 3 be completed?

The latest completion date reported to UP-RERA for UNNATI AWAS YOJNA - PHASE 3 is 30 Sept 2022.

Is UNNATI AWAS YOJNA - PHASE 3 delayed?

Measured against the latest completion date reported to UP-RERA, UNNATI AWAS YOJNA - PHASE 3 is 46 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026