UNNATI AWAS YOJNA - PHASE 3 is a RERA-registered residential project by GANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED in Agra (RERA ID UPRERAPRJ15396). Registered with a completion deadline of 29 Mar 2026.
RERA status as reported: Registered.Construction progress
Construction stayed at 93% across 24 consecutive filed quarters (Apr–Jun 2020 to Jan–Mar 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ15396 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Agra Development Authority |
| Proposed start | 7 Mar 2018 |
| Project duration | 97 months |
| Address | Agra, Agra |
| Tehsil | Agra |
| Applicant type | Company |
| Applicant address | 31/472 C1,IST FLORE ,GANASH PLAZA SULTAN GANJ PULIYA PIPASS ROAD AGRA |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
3 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 8 Mar 2018 |
| Original completion | 31 Mar 2022 |
| Revised completion | 29 Mar 2026 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹12,500 |
| Sanctioning authority | Agra Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | — | 40-55 |
| SHOP | — | 13 |
| 3 BHK | — | 72 |
| 1 BHK | — | 38 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| COMMERCIAL BLOCK 001 · SHOP | 2 | — | 13 |
| Kaveri Tower 002 · 2 BHK | 10 | — | 55 |
| Narmada Tower -3 · 3 BHK | 7 | — | 72 |
| SUTLEJ TOWER -1 · 2 BHK, 1 BHK | 10 | — | 38-42 |
| kaveri Tower 003 · 2 BHK | 10 | — | 55 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots yes |
| 2 | Boundary Wall yes |
| 3 | Road Work yes |
| 4 | Footpaths yes |
| 5 | Water Supply Including Drinking Water Facilities yes |
| 6 | Sewer System yes |
| 7 | Drain yes |
| 8 | Parks yes |
| 9 | Tree Planting yes |
| 10 | Design For Electric Supply Including Street Lighting yes |
| 11 | Community Buildings yes |
| 12 | Treatment and Disposal System of Sewage and Sullage water yes |
| 13 | Solid Waste Management And Disposal System yes |
| 14 | Water Conservation System yes |
| 15 | Energy Management System Including Use of Renewable Energy no |
| 16 | Fire Protection And Fire Safety System yes |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services yes |
| 18 | Emergency Evacuation Services no |
| 19 | Other Miscellaneous Work yes |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 10 Jul 2021.
Sanctioned by Agra Development Authority · 1,420 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 634/A V-1/S A Y -DPR/2016 | 11 Jul 2016 | 10 Jul 2021 | 10 Jul 2024 | 31 Mar 2022 | |
| 634/A V-1/S A Y -DPR/2016 | 11 Jul 2016 | 10 Jul 2021 | 31 Mar 2024 | 30 Sept 2022 | |
| 634/A V-1/S A Y -DPR/2016 | 11 Jul 2016 | 10 Jul 2021 | 31 Mar 2024 | 30 Sept 2022 |
| Document | File |
|---|---|
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
UPRERA’s record carries 3 completion extensions for this project, the latest running to 29 Mar 2026.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 31 Mar 2022 | 30 Sept 2022 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 30 Sept 2022 | 29 Mar 2024 | — |
| 3 | 29 Mar 2024 | 29 Mar 2026 | — |
Land & documents
7 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 1/4, 1/5, 1/13, 20 TO 25, 26/2, 42 TO 53, 56 8, 9 | 35385.15 | — |
| 1/4, 1/5, 1/13, 20 TO 25, 26/2, 42 TO 53, 56 8, 9 | 35385.15 | Khasra |
4 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 27 Sept 2009.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 4858 | 27 Sept 2009 | self | — |
| 3814 | 28 Jul 2010 | self | — |
| 5563 | 7 Oct 2013 | self | — |
| 1697 | 13 Apr 2011 | self | — |
| Registry document · 4858 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · REVISED UNITS DETAIL The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · REVISED UNITS DETAIL The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · REVISED UNITS DETAIL The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | Old | 8 Mar 2018 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | Old | 8 Mar 2018 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | Old | 8 Mar 2018 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | Old | 8 Mar 2018 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 8 Mar 2018 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | AVAILABLE |
| Fire safety (as filed with RERA) | AVAILABLE |
| Other facilities | RCC ROAD, 24X7 SECURITY, PARK, KIDS PARK, SWIMMING POOL, CONVENIENT SHOPS |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
24 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
24 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q4.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 93% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | GANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED |
| Role | Promoter · current |
| RERA ID | UPRERAPRM2735 |
| PAN | AAECG6731F |
| CIN / TAN | U70102UP2012PLC049767 |
| Name of chairman | ANIL AGARWAL |
| Registered address | 31/472 C1,IST FLORE ,GANASH PLAZA SULTAN GANJ PULIYA PIPASS ROAD AGRA |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Agra
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | GIDCO UNNATI AWAS YOJNABankHDFC BANK LIMITEDBranchHDFC BANK LIMITED SANJAY PLACE, AGRAA/C no.IFSCHDFC0000121 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 24 (Under Registration - 1 ) → 24 (Under Registration - 0 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 23 Aug 2026 |
Common questions about UNNATI AWAS YOJNA - PHASE 3
Is UNNATI AWAS YOJNA - PHASE 3 RERA registered?
Yes. UNNATI AWAS YOJNA - PHASE 3 is registered with UPRERA under registration number UPRERAPRJ15396, registered on 8 Mar 2018. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for UNNATI AWAS YOJNA - PHASE 3?
The completion date filed with UPRERA is 29 Mar 2026. No completion certificate is on record yet.
Who is the builder of UNNATI AWAS YOJNA - PHASE 3?
GANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED is the promoter entity that filed UNNATI AWAS YOJNA - PHASE 3 with UPRERA (promoter RERA ID UPRERAPRM2735). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted UNNATI AWAS YOJNA - PHASE 3 more time to complete?
UPRERA's record carries 3 completion extensions for UNNATI AWAS YOJNA - PHASE 3, the latest running to 29 Mar 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does UNNATI AWAS YOJNA - PHASE 3 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is UNNATI AWAS YOJNA - PHASE 3 located?
UNNATI AWAS YOJNA - PHASE 3 is registered in Agra, as filed with UPRERA.
What configurations are available in UNNATI AWAS YOJNA - PHASE 3?
The unit plan filed with UPRERA lists 2 BHK, SHOP, 3 BHK and 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in UNNATI AWAS YOJNA - PHASE 3?
The approved unit plan filed with UPRERA runs from 13 to 72 m² of carpet area (about 143 to 777 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗