GH-1 Grand Omaxe Phase-5 is a RERA-registered real-estate project in Lucknow (RERA ID UPRERAPRJ892218). Its RERA-registered completion deadline (20 Jun 2026) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ892218 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Feb 2019 |
| Project duration | 89 |
| Address | Sarojini Nagar, Lucknow |
| RERA registered | 5 Mar 2019 |
| Promised completion | 21 Dec 2025 |
| Revised completion | 20 Jun 2026 |
| Completion certificate filed | — not on record |
| Registration fee | ₹52,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 1 | 117 |
| 3 BHK | 1 | 113 |
| 4 BHK | 129 | 127–131 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 42975 | 22 Dec 2017 | 21 Dec 2022 | 21 Dec 2025 |
| 42975 | 22 Dec 2017 | 21 Dec 2022 | 21 Dec 2025 |
| 42975 | 22 Dec 2019 | 21 Dec 2022 | 20 Jun 2026 |
| Khasra | Area | Type |
|---|---|---|
| 400 | 3730 | Khasra |
| 401 | 3260 | Khasra |
| 404 | 2150 | Khasra |
| 405 | 4670 | Khasra |
| 408 | 7100 | Khasra |
| 409 | 1240 | Khasra |
| 410 | 340 | Khasra |
| 411 | 4820 | Khasra |
| 412 | 2580 | Khasra |
| 413 | 3270 | Khasra |
| 414 | 4170 | Khasra |
| 480 | 5260 | Khasra |
| 399 | 1460 | Khasra |
| 406 | 130 | Khasra |
| 446 | 3160 | Khasra |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | 11.45% | CA · Arch · Eng | view ↗ |
| 2020-Q2 | 11.45% | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
| 2023-Q3 | 74.78% | CA · Arch · Eng | view ↗ |
| 2023-Q4 | 80.72% | CA · Arch · Eng | view ↗ |
| 2024-Q1 | 80.72% | CA · Arch · Eng | view ↗ |
| 2024-Q2 | 91.71% | CA · Arch · Eng | view ↗ |
| 2024-Q3 | 91.71% | CA · Arch · Eng | view ↗ |
| 2024-Q4 | 91.71% | CA · Arch · Eng | view ↗ |
| 2025-Q1 | 91.71% | CA · Arch · Eng | view ↗ |
| 2025-Q2 | 91.71% | CA · Arch · Eng | view ↗ |
| 2025-Q3 | 91.71% | CA · Arch · Eng | view ↗ |
| 2025-Q4 | 93.61% | CA · Arch · Eng | view ↗ |
| 2026-Q1 | 99.07% | CA · Arch · Eng | view ↗ |
Yes. GH-1 Grand Omaxe Phase-5 is registered with UPRERA under registration number UPRERAPRJ892218, registered on 5 Mar 2019. Estanzo reproduces that filing; it does not verify the work behind it.
GH-1 Grand Omaxe Phase-5 is 2 months past the completion date filed with UPRERA (20 Jun 2026), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
GH-1 Grand Omaxe Phase-5 is registered in Lucknow, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗