Omaxe Limited

UPRERACompany

Omaxe Limited (RERA ID: UPRERAPRM2386) is a company registered with UP-RERA since 2017. It has 33 projects on record with Estanzo.

Summarize this record with:ChatGPTPerplexityClaudeGrok

One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.

Projects by this promoter

33 on record · 1 as co-promoter
Registered32Completed1each project counted once, under the authority’s own step
C-1(Hazratganj Commercial) at Omaxe integrated tow UPRERA
UPRERAPRJ1925 · Lucknow
Promised completion 28 Jan 2024 · Extended
Registered
Commercial and Service Apartment at Eternity - 2 UPRERA
UPRERAPRJ988231 · Mathura
Promised completion 1 Apr 2031
Registered
COMM. (Krishna Crest - 1), at Omaxe Eternity, Vrindavan UPRERA
UPRERAPRJ2227 · Mathura
Promised completion 29 Nov 2020 · Extended
Registered
COMM. (Krishna Crest - 2), at Omaxe Eternity, Vrindavan UPRERA
UPRERAPRJ2200 · Mathura
Promised completion 30 Nov 2020 · Extended
Registered
EWS & New LIG, at Omaxe Eternity, Vrindavan UPRERA
UPRERAPRJ3191 · Mathura
Promised completion 28 Dec 2022 · Extended
Registered
GH-1 Grand Omaxe LINCOLN A and B UPRERA
UPRERAPRJ624607 · Lucknow
Promised completion 28 Feb 2030
Registered
GH-1 (Grand Omaxe), Phase - 1, at Omaxe Integrated UPRERA
UPRERAPRJ809 · Lucknow
Promised completion 28 Jul 2025 · Extended
Registered
GH-1 (Grand Omaxe), Phase - 2, at Omaxe Integrated UPRERA
UPRERAPRJ775 · Lucknow
Promised completion 29 Jul 2025 · Extended
Registered
GH-1 (Grand Omaxe), Phase - 3, at Omaxe Integrated UPRERA
UPRERAPRJ1181 · Lucknow
Promised completion 28 Jul 2025 · Extended
Registered
GH-1 (Grand Omaxe), Phase - 4, at Omaxe Integrated UPRERA
UPRERAPRJ1550 · Lucknow
Promised completion 29 Jul 2025 · Extended
Registered
GH-1 Grand Omaxe Phase-5 UPRERA
UPRERAPRJ892218 · Lucknow
Promised completion 20 Jun 2026 · Extended
Registered
GH-1 GRAND OMAXE PHASE-6 UPRERA
UPRERAPRJ283534 · Lucknow
Promised completion 7 Aug 2027
Registered
GH-1 Grand Omaxe Regent UPRERA
UPRERAPRJ537348 · Lucknow
Promised completion 28 Feb 2030
Registered
GH-3 (Waterscape), Phase - 1, at Omaxe Integrated UPRERA
UPRERAPRJ1538 · Lucknow
Promised completion 24 Mar 2023 · Extended
Registered
GH-3 (Waterscape), Phase - 2, at Omaxe Integrated UPRERA
UPRERAPRJ1263 · Lucknow
Promised completion 24 Mar 2023 · Extended
Registered
GH4 PHASE 4(THE RESORT) UPRERA
UPRERAPRJ326163 · Lucknow
Promised completion 31 Dec 2028
Registered
GH-4 (Residency-II) Phase-1,Omaxe Integrated towns UPRERA
UPRERAPRJ1682 · Lucknow
Promised completion 29 Jun 2022 · Extended
Registered
GH-4 (Residency-II) Phase-3, Omaxe Integrated Township UPRERA
UPRERAPRJ368818 · Lucknow
Promised completion 29 Apr 2025 · Extended
Registered
GH-4 (Residency II) Phase II at Omaxe integrated T UPRERA
UPRERAPRJ1720 · Lucknow
Promised completion 29 Dec 2023 · Extended
Completed
GH-5 (Hazratganj Residency), at Omaxe Integrated T UPRERA
UPRERAPRJ2050 · Lucknow
Promised completion 16 Jan 2025 · Extended
Registered

See the 1 as co-promoter

Showing 20 of 33 projects on record. See all 33 projects

Promoters sharing a director

none matched

Linked by a director’s DIN, never by name alone. Each company is its own record.

No other promoter shares a director with Omaxe Limited on record.

Filings for more time

36 filings
Extension filings36
Projects with at least one22 of 33
Longest single extension547 days - GH-6 (EWS & LIG) at Omaxe Integrated Township
Latest extension runs to20 Jun 2026 - GH-1 Grand Omaxe Phase-5
Permits carrying a revalidation23 across 16 projects

Directors & ownership

7 named by UPRERA
Chairman
MR. ROHTASH GOEL
Director
DIN 00828759
Director
DIN 08055468
Director
DIN 02451363
Director
DIN 06934656
Director
DIN 00003735
Director
DIN 03575020

Promoter timeline

16 Nov 2015 - 16 Oct 2026
  1. Project registered
    official source ↗
  2. Completion certificate filed
    official source ↗
  3. Completion certificate filed
    official source ↗
  4. Completion certificate filed
    official source ↗
  5. Completion certificate filed
    official source ↗
  6. Project registered
    official source ↗
  7. Extension filed
    new completion date on file 20 Jun 2026as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  8. Completion certificate filed
    official source ↗
  9. Completion certificate filed
    official source ↗
  10. Completion certificate filed
    official source ↗
  11. Project registered
    official source ↗
  12. Project registered
    official source ↗
Show 98 earlier filings
  1. Extension filed
    new completion date on file 28 Jul 2025official source ↗
  2. Extension filed
    new completion date on file 28 Jul 2025official source ↗
  3. Permit revalidated
    valid to 18 Mar 2032as recorded by UPRERA: Group Housing/14188/LDA/BP/24-25/2254/06122024official source ↗
  4. Permit revalidated
    valid to 18 Mar 2032as recorded by UPRERA: Group Housing/14188/LDA/BP/24-25/2254/06122024official source ↗
  5. Completion certificate filed
    official source ↗
  6. Extension filed
    new completion date on file 29 Apr 2025official source ↗
  7. Project registered
    official source ↗
  8. Permit revalidated
    valid to 7 Aug 2027as recorded by UPRERA: Group Housing/11628/LDA/BP/23-24/4679/01042024official source ↗
  9. Permit revalidated
    valid to 7 Aug 2027as recorded by UPRERA: Group-Housing/11628/LDA/BP/23-24/4679/01042024official source ↗
  10. Completion certificate filed
    official source ↗
  11. Completion certificate filed
    official source ↗
  12. Extension filed
    new completion date on file 29 Jan 2025official source ↗
  13. Extension filed
    new completion date on file 29 Jul 2025official source ↗
  14. Extension filed
    new completion date on file 16 Jan 2025official source ↗
  15. Extension filed
    new completion date on file 29 Jul 2025official source ↗
  16. Extension filed
    new completion date on file 29 Jan 2025official source ↗
  17. Completion certificate filed
    official source ↗
  18. Extension filed
    new completion date on file 30 Apr 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  19. Extension filed
    new completion date on file 28 Apr 2025official source ↗
  20. Completion certificate filed
    official source ↗
  21. Permit revalidated
    valid to 21 Dec 2025as recorded by UPRERA: LDA/BP/21-22/2875official source ↗
  22. Extension filed
    new completion date on file 30 Jan 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  23. Extension filed
    new completion date on file 30 Jan 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  24. Extension filed
    new completion date on file 30 Jan 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  25. Extension filed
    new completion date on file 30 Jan 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  26. Extension filed
    new completion date on file 30 Jan 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  27. Extension filed
    new completion date on file 28 Jan 2024official source ↗
  28. Extension filed
    new completion date on file 29 Dec 2023official source ↗
  29. Extension filed
    new completion date on file 29 Oct 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  30. Project registered
    official source ↗
  31. Extension filed
    new completion date on file 30 Mar 2024official source ↗
  32. Permit revalidated
    valid to 22 Mar 2024as recorded by UPRERA: COMMERCIAL BUILDING/05564/LDA/BP/22-23/0827/06072022official source ↗
  33. Completion certificate filed
    official source ↗
  34. Completion certificate filed
    official source ↗
  35. Extension filed
    new completion date on file 30 Jul 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  36. Extension filed
    new completion date on file 30 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  37. Extension filed
    new completion date on file 30 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  38. Extension filed
    new completion date on file 24 Mar 2023official source ↗
  39. Project registered
    official source ↗
  40. Project registered
    official source ↗
  41. Permit revalidated
    as recorded by UPRERA: GROUP HOUSING/05996/LDA/BP/21-22/3048/29082022official source ↗
  42. Completion certificate filed
    official source ↗
  43. Completion certificate filed
    official source ↗
  44. Extension filed
    new completion date on file 24 Mar 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  45. Extension filed
    new completion date on file 29 Jul 2023official source ↗
  46. Extension filed
    new completion date on file 29 Jun 2023official source ↗
  47. Project registered
    official source ↗
  48. Permit revalidated
    valid to 7 Aug 2027as recorded by UPRERA: 39411official source ↗
  49. Permit revalidated
    valid to 7 Aug 2027as recorded by UPRERA: 39411official source ↗
  50. Extension filed
    new completion date on file 30 Jul 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  51. Extension filed
    new completion date on file 29 Jun 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  52. Extension filed
    new completion date on file 30 Jun 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  53. Extension filed
    new completion date on file 28 Dec 2022official source ↗
  54. Extension filed
    new completion date on file 29 Dec 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  55. Completion certificate filed
    official source ↗
  56. Project registered
    official source ↗
  57. Completion certificate filed
    official source ↗
  58. Extension filed
    new completion date on file 14 May 2021official source ↗
  59. Extension filed
    new completion date on file 29 Nov 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  60. Extension filed
    new completion date on file 30 Nov 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  61. Extension filed
    new completion date on file 30 Nov 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  62. Permit revalidated
    valid to 7 Aug 2027as recorded by UPRERA: 39411official source ↗
  63. Permit revalidated
    valid to 7 Aug 2027as recorded by UPRERA: 42975official source ↗
  64. Permit revalidated
    valid to 7 Aug 2027as recorded by UPRERA: 39411official source ↗
  65. Permit revalidated
    valid to 2 Feb 2024as recorded by UPRERA: 42975official source ↗
  66. Project registered
    official source ↗
  67. Project registered
    official source ↗
  68. Project registered
    official source ↗
  69. Permit revalidated
    valid to 21 Nov 2025as recorded by UPRERA: 40951official source ↗
  70. Project registered
    official source ↗
  71. Permit revalidated
    as recorded by UPRERA: 42975official source ↗
  72. Permit revalidated
    valid to 25 Sept 2022as recorded by UPRERA: 42656official source ↗
  73. Permit revalidated
    valid to 25 Sept 2022as recorded by UPRERA: 42447official source ↗
  74. Permit revalidated
    valid to 25 Sept 2022as recorded by UPRERA: 42447official source ↗
  75. Permit revalidated
    valid to 25 Sept 2022as recorded by UPRERA: 42447official source ↗
  76. Project registered
    official source ↗
  77. Project registered
    official source ↗
  78. Project registered
    official source ↗
  79. Project registered
    official source ↗
  80. Project registered
    official source ↗
  81. Project registered
    official source ↗
  82. Project registered
    official source ↗
  83. Project registered
    official source ↗
  84. Project registered
    official source ↗
  85. Project registered
    official source ↗
  86. Project registered
    official source ↗
  87. Project registered
    official source ↗
  88. Project registered
    official source ↗
  89. Project registered
    official source ↗
  90. Project registered
    official source ↗
  91. Project registered
    official source ↗
  92. Project registered
    official source ↗
  93. Project registered
    official source ↗
  94. Project registered
    official source ↗
  95. Permit revalidated
    as recorded by UPRERA: 41253 (Revision Applied)official source ↗
  96. Permit revalidated
    as recorded by UPRERA: 41253 (Revision Applied)official source ↗
  97. Permit revalidated
    valid to 30 Dec 2024as recorded by UPRERA: 41134official source ↗
  98. Permit revalidated
    as recorded by UPRERA: 39312official source ↗

Quarterly reports filed, by financial year

FY 2020-21
83 reports across 23 projects
FY 2021-22
74 reports across 20 projects
FY 2022-23
72 reports across 21 projects
FY 2023-24
57 reports across 18 projects
FY 2024-25
50 reports across 14 projects
FY 2025-26
40 reports across 14 projects
FY 2026-27
8 reports across 8 projects
Counts the reports UPRERA publishes as filed.
A filing is not an outcome.

Common questions about Omaxe Limited

How many projects has Omaxe Limited registered with RERA?

Estanzo holds 33 projects on record with UPRERA, filed by Omaxe Limited (promoter RERA ID UPRERAPRM2386). This counts filings by this legal entity only - a builder brand may file through several entities.

Who are the directors of Omaxe Limited?

Omaxe Limited disclosed 7 directors or partners to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.

When was Omaxe Limited registered with RERA?

Omaxe Limited has been registered with UPRERA since 26 Jul 2017.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗