GH4 PHASE 4(THE RESORT)

UPRERARegistered

GH4 PHASE 4(THE RESORT) is a RERA-registered residential project by Omaxe Limited in Lucknow (RERA ID UPRERAPRJ326163). Registered with a completion deadline of 31 Dec 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
26.94%Q3'25
30.7%Q4'25
34.46%Q1'26
37.77%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ326163
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Jan 2023
Project duration72 months
AddressSarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompany
Applicant addressSHOP No-19-B, FIRST FLOOR, OMAXE CELEBRATION MALL, SOHNA ROAD, GURGAON-122001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated

    GROUP HOUSING/05996/LDA/BP/21-22/3048/29082022

  2. 2 building permits sanctioned

  3. Registered with RERA

  4. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered28 Dec 2022
Original completion31 Dec 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹66,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors144 · 4 · 20 (units from plan)
  • 3 BHK68 47%
  • 4 BHK68 47%
  • PENTHOUSE8 6%
ConfigurationUnitsCarpet area
3 BHK68170
PENTHOUSE8349-403
4 BHK68214
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower A1 · 3 BHK, PENTHOUSE2034170-349
Tower A2 · 3 BHK, PENTHOUSE2038170-349
Tower B1 · 4 BHK, PENTHOUSE2036214-403
Tower B2 · 4 BHK, PENTHOUSE2036214-403
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Apurba Borah
License CA/2013/61818
10, LSC, kalkaji, New Delhi
Engineer
Sanjeev Jain
Lower ground floor, CR Park , New Delhi -19
Contractor
In House
In House
Sr.Development work declared to RERA
1Demarcation of Plots
Demarcation of Plots completed at the site
2Boundary Wall
Boundar wall(Height approx 1500 from Road Level or as per design/requirement) will be constructed by brick work/MS Railing as per design by Promoter
3Road Work
Internal Drive way 9 mtr and 6 mtr wide as per approved plan will be constructed by RCC or as per requirement and designed by promoter
4Footpaths
Footpath width 600/900 mm, as per designed by promoter, will be developed by using pavers/stone as per requirements.
5Water Supply Including Drinking Water Facilities
24 hr water supply including drinking water facilities will be provided by the promoter through submersible/OHT on terrace.
6Sewer System
S.T.P will be constructed by promoter at site for Sewer Disposal
7Drain
Covered Drainage system will be developed and connected with RWH and overflow will be connected with existing govt. drainage.
8Parks
Common Parks/Green area available for all GH-4. And will be developed as per approved plan and requirements.
9Tree Planting
Total 333 Trees required as per approved plan in GH-4 and same will be planted in common area/open area of the project GH-4
10Design For Electric Supply Including Street Lighting
Electricity supply will be provided from ESS already constructed at Integrated Township
11Community Buildings
Community Buildings will be provided for GH- 4 project
12Treatment and Disposal System of Sewage and Sullage water
S.T.P. will be constructed at site and treated water will be use in flushing and irrigation
13Solid Waste Management And Disposal System
Solid Waste Management and Disposal System will be provided as per govt norms
14Water Conservation System
Water conservation system will be provided as per govt norms
15Energy Management System Including Use of Renewable Energy
Energy Management system i/c use of renewable energy will be provided as per govt norms
16Fire Protection And Fire Safety System
Fire NOC received and fire protection and fire safety system will be provided as per design and norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
Common Social infrastructure and public amenities i/c Public health services will be provided in Integrated Township
18Emergency Evacuation Services
Fire Stair case will be provided as per Approved drawings.
19Other Miscellaneous Work
As per specification and approved map all work will be developed
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

90 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1ABHINAV KHAREUPRERAAGT14915
2ABHINEET GAURUPRERAAGT14935
3ABHISHEK KUMAR SINGHUPRERAAGT15288
4Ajit RaiUPRERAAGT11295
5Akansha BansalUPRERAAGT20837
6AKASH DEEP SRIVASTAVAUPRERAAGT15712
7AMIT AGARWALUPRERAAGT11945
8Amit KhareUPRERAAGT19477
9AMIT KUMAR NISHADUPRERAAGT14016
10Amit madanUPRERAAGT19393
11Amit MisraUPRERAAGT18676
12Anamika MishraUPRERAAGT16351
13ANAND KUMAR SHUKLAUPRERAAGT10831
14ANURAG GUPTAUPRERAAGT14504
15ANYA PROPERTIESUPRERAAGT15969
16ARJUN SINGH YADAVUPRERAAGT11879
17ASA FINCAP ADVISORS LLPUPRERAAGT10926
18Ashish TripathiUPRERAAGT18925
19Balbir SinghUPRERAAGT20260
20BASECAMP INFRA CONSULTANTS (OPC) PRIVATE LIMITEDUPRERAAGT14759
21BIPIN CHANDRA PANTUPRERAAGT13687
22BRIXWELL REALTY & CONSTRUCTION LLPUPRERAAGT15068
23CITYMAX PROPMART PRIVATE LIMITEDUPRERAAGT13792
24DAIWIK REALTORSUPRERAAGT12075
25Dev Real Estate and FinanceUPRERAAGT16776
26GOLDEN ESTATEUPRERAAGT10397
27Hitesh KesarwaniUPRERAAGT11538
28HITESH KHANNAUPRERAAGT13833
29INVESTORS CARE INFRATECH PVT LTDUPRERAAGT13542
30KAUSHTUBH REALTY PRIVET LIMITEDUPRERAAGT13025
31KHUSHBOO KUSHWAHAUPRERAAGT19671
32KUMAR KESHAVUPRERAAGT18972
33LINK PROPERTIESUPRERAAGT10081
34LIPIKA CHATTERJEEUPRERAAGT14888
35M.S. Property Consultants L.L.P.UPRERAAGT10074
36manju tripathiUPRERAAGT14947
37MARKANDEY SINGHUPRERAAGT18928
38MOHD AFZALUPRERAAGT13830
39Mohd Atif AliUPRERAAGT17360
40MONISHA BUDHRAJAUPRERAAGT16694
41Mr. Janardan AgarwalUPRERAAGT10555
42Mukesh kumar SharmaUPRERAAGT11494
43Narendra SinghUPRERAAGT14206
44Pankaj MittalUPRERAAGT13523
45PIXEL GLOBAL INFRA PRIVATE LIMITEDUPRERAAGT13936
46Prashant GuptaUPRERAAGT19667
47Prem Prakash KhareUPRERAAGT13677
48Priya MishraUPRERAAGT18717
49R K PROPERTIESUPRERAAGT11201
50RADHE SHAYMUPRERAAGT19129
51RADHESH CHANDRAUPRERAAGT10484
52RAJEEV CHHOKERUPRERAAGT19007
53RAJEEV KUMAR SHUKLAUPRERAAGT13288
54Rajesh kumarUPRERAAGT20162
55RAJNI NIGAMUPRERAAGT10897
56REALTYSTRUCTURE INFRATECH PRIVATE LIMITEDUPRERAAGT10144
57Rishabh SaxenaUPRERAAGT13851
58S.R.Broker LLPUPRERAAGT10051
59Sakshi GuptaUPRERAAGT16025
60Sandeep TripathiUPRERAAGT12229
61SANJEEV KUMAR BANKAUPRERAAGT10894
62Santosh Kumar Mishra C/O UNITEDWORLD PROPERTIES (P) LTD.UPRERAAGT22197
63SATYAM SINGHUPRERAAGT18865
64SDR INFRA BUILD PVT LTDUPRERAAGT11062
65Shalini VermaUPRERAAGT15031
66SHALINI WADHWAUPRERAAGT15032
67SHREE SHRADDHA PROPERTIESUPRERAAGT10301
68SHRI RUDRA REAL ESTATESUPRERAAGT14251
69shrikant upadhyayUPRERAAGT15563
70SILVER EDGE REAL ESTATE SOLUTIONUPRERAAGT12168
71SOURABH NIGAMUPRERAAGT10900
72STRAIGHTEDGE REAL ESTATE PRIVATE LIMITEDUPRERAAGT10067
73TARUN PREET SINGH SAHNIUPRERAAGT12537
74TULSI REAL ESTATEUPRERAAGT13187
75Tushar ChandaniUPRERAAGT12001
76Udai AssociatesUPRERAAGT14663
77Unnisis Infrratech Private LimitedUPRERAAGT15300
78Vajrakaya Buildwell Private LimitedUPRERAAGT12913
79VANDANA SRIVASTAVAUPRERAAGT18502
80Varun Properties Inc.UPRERAAGT11985
81VELOCITY DEVELOPERSUPRERAAGT10813
82Vikram singhUPRERAAGT10860
83VINAY KUMAR SINGHUPRERAAGT11226
84VINEET THAPARUPRERAAGT20835
85VINITA MISHRAUPRERAAGT16506
86Vinod DawraUPRERAAGT19609
87VIRENDRA KUMAR DEWANUPRERAAGT13205
88VISHAL BAJPAIUPRERAAGT11344
89VISHAL KUMARUPRERAAGT14798
90vishal srivastavaUPRERAAGT11982
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 21 Nov 2027. 1 of them carries a revalidation.

Sanctioned by Lucknow Development Authority · 12,175 sqm of land · an approved plan of 4 blocks and 144 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
LDA/BP/21-23-304822 Nov 202221 Nov 202721 Nov 203021 Nov 2030—
GROUP HOUSING/05996/LDA/BP/21-22/3048/2908202222 Nov 202221 Nov 202721 Nov 203031 Dec 202822 Nov 2022
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

22 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
4578100Khasra
4583240Khasra
4504851Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 9385
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 1524
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 20645
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 314
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · Land chart
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 19141
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 19141
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New25 Nov 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New25 Nov 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New25 Nov 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New25 Nov 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New26 Nov 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New26 Nov 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New26 Nov 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New26 Nov 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 Nov 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New9 Dec 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New9 Dec 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New9 Dec 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New26 Nov 2022 ↗

Quarterly progress reports

14 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

14 quarterly progress reports are on file with UPRERA, covering 2022-Q4 to 2026-Q1.

QuarterConstructionCertificates
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q226.94%CA ↗ · Arch ↗ · Eng ↗
2025-Q330.7%CA ↗ · Arch ↗ · Eng ↗
2025-Q434.46%CA ↗ · Arch ↗ · Eng ↗
2026-Q137.77%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameOmaxe Limited
RolePromoter · current
RERA IDUPRERAPRM2386
PANAAACO0171H
CIN / TANDELO01861G
Name of chairmanMr. Rohtash Goel
Registered addressSHOP No-19-B, FIRST FLOOR, OMAXE CELEBRATION MALL, SOHNA ROAD, GURGAON-122001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameADVAY PROPERTIES PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressGROUND FLOOR, 22 OMAXE VALUE MALL AJNARA ROAD AMRITSAR Amritsar PB 143001 IN
RERA contact
Legal nameAGASTHYA PROPERTIES PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressGround Floor,22,Omaxe Value mall, , , Ajnara Road, Amritsar, Punjab, 143101
RERA contact
Legal nameAMOD BUILDERS PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressGround Floor 22,,omaxe Value mall , Ajnara Road , Amritsar , 26-Punjab , 91-India , 143001
RERA contact

Nearby projects

Lucknow

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
OMAXE SEPERATE ACCOUNT FOR GH-4 PHASE 4BankIDBI BANKBranchINDRA NAGARA/C no.IFSCIBKL0000277
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

5 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)224 (Under Registration - 4 ) → 225 (Under Registration - 4 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)224 (Under Registration - 5 ) → 224 (Under Registration - 4 )
changed in Estanzo’s record
23 Sept 2026
Promoter’s complaints tally (all their projects)223 (Under Registration - 4 ) → 224 (Under Registration - 5 )
changed in Estanzo’s record
11 Sept 2026
Promoter’s complaints tally (all their projects)223 (Under Registration - 5 ) → 223 (Under Registration - 4 )
changed in Estanzo’s record
7 Sept 2026
Promoter’s complaints tally (all their projects)220 (Under Registration - 3 ) → 223 (Under Registration - 5 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 18 Oct 2026 · 5 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about GH4 PHASE 4(THE RESORT)

Is GH4 PHASE 4(THE RESORT) RERA registered?

Yes. GH4 PHASE 4(THE RESORT) is registered with UPRERA under registration number UPRERAPRJ326163, registered on 28 Dec 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for GH4 PHASE 4(THE RESORT)?

The completion date filed with UPRERA is 31 Dec 2028. No completion certificate is on record yet.

Who is the builder of GH4 PHASE 4(THE RESORT)?

Omaxe Limited is the promoter entity that filed GH4 PHASE 4(THE RESORT) with UPRERA (promoter RERA ID UPRERAPRM2386). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does GH4 PHASE 4(THE RESORT) have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is GH4 PHASE 4(THE RESORT) located?

GH4 PHASE 4(THE RESORT) is registered in Lucknow, as filed with UPRERA.

What configurations are available in GH4 PHASE 4(THE RESORT)?

The unit plan filed with UPRERA lists 3 BHK, PENTHOUSE and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in GH4 PHASE 4(THE RESORT)?

The approved unit plan filed with UPRERA runs from 170 to 403 m² of carpet area (about 1,832 to 4,336 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in GH4 PHASE 4(THE RESORT)?

The approved unit plan describes 4 blocks and 144 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is GH4 PHASE 4(THE RESORT)?

About 48 units per acre: 144 planned units across 3.01 acres (12,175 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗