Timeline Bar
Registered12 Mar 2022
Today4 Aug 2026
Promised23 Dec 2026
Timeline
Promised completion23 Dec 2026
Revised completion23 Dec 2026
Actual completion—
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹53,000
Project cost (in ₹ Lakhs)₹1,240 Lakhs
Project duration60 months
Project categoryResidential
Locality—
Original start date—
Proposed start date24 Dec 2021
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeIndividual
Mobile9627669977
Emailsinghharpreet2011@gmail.com
Coordinator9627669977
Address77A SHAHDANA MODELTOWN BAREILLY 243001
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| BDA/LD/21-22/0227 | 24 Dec 2021 | 24 Dec 2021 | 23 Dec 2026 | 23 Dec 2026 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 191 | 1334 | Khasra |
| 536 | 1140 | Khasra |
| 537 | 380 | Khasra |
| 547 | 1260 | Khasra |
| 548 | 630 | Khasra |
| 549 | 760 | Khasra |
| 550 | 1392 | Khasra |
| 551 | 1390 | Khasra |
| 552 | 1260 | Khasra |
Frequently Asked Questions
What is the RERA registration number of GOBIND DHAM?
The RERA registration number of GOBIND DHAM is UPRERAPRJ110203, as recorded on the UP-RERA portal.
What is the RERA status of GOBIND DHAM?
As reported by UP-RERA, the status of GOBIND DHAM is "Registered".
Where is GOBIND DHAM located?
As reported to UP-RERA, GOBIND DHAM is located at Bareilly, Bareilly, Uttar Pradesh.
When will GOBIND DHAM be completed?
The latest completion date reported to UP-RERA for GOBIND DHAM is 23 Dec 2026.
Is GOBIND DHAM delayed?
Measured against the latest completion date reported to UP-RERA, GOBIND DHAM is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026