Registered11 Oct 2017
Promised31 Mar 2024
Today4 Aug 2026

Timeline

Promised completion31 Mar 2024
Revised completion31 Mar 2024
Actual completion
Possession delay28 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,38,000
Project cost (in ₹ Lakhs)₹42,219 Lakhs
Project duration78 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Apr 2018

Inventory

Total units385
Unit TypeUnitsCarpet Area (sqm)
2 BHK6869.2
3 BHK182104.9–126.4
4 BHK56150.36–169.2
PENTHOUSE7256.02–325.85
OTHER7283.3

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9560450810
Emailgodrejnest@godrejproperties.com
Coordinator9978856617
Address7th Floor, Tower B, Plot No.8, Sector 127, Noida-201301

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
1) Master Plan No. IV/1451/950 dated 17.01.2017 2)Building Plan No. IV/1490/929 dated 30.09.201617 Jan 201716 Jan 202231 Mar 202415 Jan 2027

Land Parcels

Khasra No.AreaPlot Type
SC-02/H&I72000 sq. Mtrs
SC-02, H&I, Sector-150, Noida72000Plot

Approved Unit Plan

Unit plan rows on file407
Total flats (sum of rows)385
BlocksTower A1 [(2BHK) Type1], Tower A1 [(3RHK) Type2], Tower A2 [(2BHK) Type1], Tower A2 [(3RHK) Type2], Tower B3 [3 BHK + S. WC (Type 3)], Tower B3 [3BHK+2 Store/ Utility](Type 4)], Tower B3 [Simplex Penthouse 4BHK+TOI+Lounge+P RM+U, Tower B3 [Simplex Penthouse+ 4 TOI+lounge+ P RM+Ut, Tower C1 [3BHK +2Store/Utility] type4, Tower C1 [Simplex penthouse 4BHK+4toi+lounge+P.RM+, Tower D1 [3 BHK+2 Store/Utility](Type 6), Tower D1 [4 BHK+Utility/ Store](Type 5), Tower D1 [4 BHK+Utility/Store+ Family Lounge/Study, Tower D1 [Duplex Penthouse 4 BHK+Utility](Type 10), Tower D1 [Duplex Penthouse 5 BHK+Store+Utility](Ty, Tower D1 [Duplex Penthouse 5 BHK+Study+Utility](Ty
Floor types2 BHK, 3 BHK, 4 BHK, PENTHOUSE, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
. Lease Deed dated 20/11/2015, Book No.1, Volume N20 Nov 2015
Sub Lease Deed Dated 17/06/2016, Book No. 1, Volum17 Jun 2016

Frequently Asked Questions

What is the RERA registration number of GODREJ NEST PHASE-1?

The RERA registration number of GODREJ NEST PHASE-1 is UPRERAPRJ13521, as recorded on the UP-RERA portal.

What is the RERA status of GODREJ NEST PHASE-1?

As reported by UP-RERA, the status of GODREJ NEST PHASE-1 is "Registered".

Where is GODREJ NEST PHASE-1 located?

As reported to UP-RERA, GODREJ NEST PHASE-1 is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will GODREJ NEST PHASE-1 be completed?

The latest completion date reported to UP-RERA for GODREJ NEST PHASE-1 is 31 Mar 2024.

Is GODREJ NEST PHASE-1 delayed?

Measured against the latest completion date reported to UP-RERA, GODREJ NEST PHASE-1 is 28 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026