Estanzo

Timeline Bar

Registered27 Feb 2019
Promised31 Mar 2026
Today4 Aug 2026

Timeline

Promised completion31 Mar 2026
Revised completion31 Mar 2026
Actual completion
Possession delay4 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,67,000
Project cost (in ₹ Lakhs)₹54,026 Lakhs
Project duration90 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Apr 2019

Inventory

Total units751
Unit TypeUnitsCarpet Area (sqm)
3 BHK74980.82–94.76
SHOP223.22

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8860083374
EmailPIOUSHIDEAWAYS@HOMEKRAFT.IN
Coordinator9643007884
AddressATS Tower Plot No-16 Sector 135, Noida UP 201305

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q2100.0%
2025-Q3100.0%
2025-Q499.0%
2026-Q1100.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/MVN/2019/IV-1513/109130 Jan 201929 Jan 202431 Mar 202629 Jan 2027

Land Parcels

Khasra No.AreaPlot Type
SC-02/J&K, Sector 150 Noida32374.85Plot

Approved Unit Plan

Unit plan rows on file215
Total flats (sum of rows)751
Total shops2
BlocksBlock B Tower 2, 3 & 4, Block C Tower 5, 6, 7 & 8, Block D Tower 9, 10 & 11, Block E Tower 12, Block A Tower 1, Commercial
Floor types3 BHK, SHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of PIOUS HIDEAWAYS?

The RERA registration number of PIOUS HIDEAWAYS is UPRERAPRJ442430, as recorded on the UP-RERA portal.

What is the RERA status of PIOUS HIDEAWAYS?

As reported by UP-RERA, the status of PIOUS HIDEAWAYS is "Registered".

Where is PIOUS HIDEAWAYS located?

As reported to UP-RERA, PIOUS HIDEAWAYS is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

When will PIOUS HIDEAWAYS be completed?

The latest completion date reported to UP-RERA for PIOUS HIDEAWAYS is 31 Mar 2026.

Is PIOUS HIDEAWAYS delayed?

Measured against the latest completion date reported to UP-RERA, PIOUS HIDEAWAYS is 4 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026