Registered14 Aug 2017
Promised20 Sept 2022
Today4 Aug 2026

Timeline

Promised completion20 Sept 2022
Revised completion20 Sept 2022
Actual completion
Possession delay46 mo delay

Registration & Cost Details

Registration fee (in ₹)₹32,000
Project cost (in ₹ Lakhs)₹22 Lakhs
Project duration66 months
Project categoryResidential
Locality
Original start date21 Sept 2017
Proposed start date21 Sept 2017

Inventory

Total units164
Unit TypeUnitsCarpet Area (sqm)
2 BHK13251.49–53.92
3 BHK3282.16

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9970022555
Emailinfo@gracelands.co.in
Coordinator9970022555
AddressSHOP NO 101/102, WHC ROAD, SWAPNIL TARANGINI APARTMENT, PLOT NO J-12, LAXMI NAGAR NAGPUR, MAHARASHTR

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
367/BHAWAN/2014-1521 Mar 201720 Mar 202220 Sept 202220 Sept 2022

Land Parcels

Khasra No.AreaPlot Type
11952460
11979120
1198310
120110140
12004610
12051230
12026040
1199920
12032660
11952460Khasra
11979120Khasra
1198310Khasra
120110140Khasra
12004610Khasra
12051230Khasra
12026040Khasra
1199920Khasra
12032660Khasra

Approved Unit Plan

Unit plan rows on file41
Total flats (sum of rows)164
BlocksTower A
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
710917 Jul 2014
710817 Jul 2014
860726 Aug 2014
80427 Aug 2014

Frequently Asked Questions

What is the RERA registration number of Grace City?

The RERA registration number of Grace City is UPRERAPRJ11281, as recorded on the UP-RERA portal.

What is the RERA status of Grace City?

As reported by UP-RERA, the status of Grace City is "Registered".

Where is Grace City located?

As reported to UP-RERA, Grace City is located at Kanpur, Kanpur Nagar, Uttar Pradesh.

When will Grace City be completed?

The latest completion date reported to UP-RERA for Grace City is 20 Sept 2022.

Is Grace City delayed?

Measured against the latest completion date reported to UP-RERA, Grace City is 46 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026