Timeline Bar
Registered14 Aug 2017
Promised20 Sept 2022
Today4 Aug 2026
Timeline
Promised completion20 Sept 2022
Revised completion20 Sept 2022
Actual completion—
Possession delay46 mo delay
Registration & Cost Details
Registration fee (in ₹)₹32,000
Project cost (in ₹ Lakhs)₹22 Lakhs
Project duration66 months
Project categoryResidential
Locality—
Original start date21 Sept 2017
Proposed start date21 Sept 2017
Inventory
Total units164
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 132 | 51.49–53.92 |
| 3 BHK | 32 | 82.16 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9970022555
Emailinfo@gracelands.co.in
Coordinator9970022555
AddressSHOP NO 101/102, WHC ROAD, SWAPNIL TARANGINI APARTMENT, PLOT NO J-12, LAXMI NAGAR NAGPUR, MAHARASHTR
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 367/BHAWAN/2014-15 | 21 Mar 2017 | 20 Mar 2022 | 20 Sept 2022 | 20 Sept 2022 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 1195 | 2460 | — |
| 1197 | 9120 | — |
| 1198 | 310 | — |
| 1201 | 10140 | — |
| 1200 | 4610 | — |
| 1205 | 1230 | — |
| 1202 | 6040 | — |
| 1199 | 920 | — |
| 1203 | 2660 | — |
| 1195 | 2460 | Khasra |
| 1197 | 9120 | Khasra |
| 1198 | 310 | Khasra |
| 1201 | 10140 | Khasra |
| 1200 | 4610 | Khasra |
| 1205 | 1230 | Khasra |
| 1202 | 6040 | Khasra |
| 1199 | 920 | Khasra |
| 1203 | 2660 | Khasra |
Approved Unit Plan
Unit plan rows on file41
Total flats (sum of rows)164
BlocksTower A
Floor types2 BHK, 3 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 7109 | 17 Jul 2014 | — | — |
| 7108 | 17 Jul 2014 | — | — |
| 8607 | 26 Aug 2014 | — | — |
| 8042 | 7 Aug 2014 | — | — |
Frequently Asked Questions
What is the RERA registration number of Grace City?
The RERA registration number of Grace City is UPRERAPRJ11281, as recorded on the UP-RERA portal.
What is the RERA status of Grace City?
As reported by UP-RERA, the status of Grace City is "Registered".
Where is Grace City located?
As reported to UP-RERA, Grace City is located at Kanpur, Kanpur Nagar, Uttar Pradesh.
When will Grace City be completed?
The latest completion date reported to UP-RERA for Grace City is 20 Sept 2022.
Is Grace City delayed?
Measured against the latest completion date reported to UP-RERA, Grace City is 46 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026