Timeline Bar
Registered5 Mar 2022
Promised30 Jun 2026
Today4 Aug 2026
Timeline
Promised completion30 Jun 2026
Revised completion30 Jun 2026
Actual completion—
Possession delay1 mo delay
Registration & Cost Details
Registration fee (in ₹)₹1,58,000
Project cost (in ₹ Lakhs)₹1,224 Lakhs
Project duration51 months
Project categoryResidential
Locality—
Original start date—
Proposed start date1 Apr 2022
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeIndividual
Mobile9810114855
Emailadmin@rishabhnath.in
Coordinator9810114855
Address7397 B-10 Vasant Kunj South West Delhi 110070
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 915 | 12 Aug 2021 | 11 Aug 2026 | 30 Jun 2026 | 10 Aug 2029 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 1678, 1679, 1680, 1688, 1690, 1691D, 1692M, 1693, 1694, 1695, 1696, 1697 | 30590 | Khasra |
Frequently Asked Questions
What is the RERA registration number of GREENWOOD ESTATE?
The RERA registration number of GREENWOOD ESTATE is UPRERAPRJ594236, as recorded on the UP-RERA portal.
What is the RERA status of GREENWOOD ESTATE?
As reported by UP-RERA, the status of GREENWOOD ESTATE is "Registered".
Where is GREENWOOD ESTATE located?
As reported to UP-RERA, GREENWOOD ESTATE is located at Shamli **, Muzaffarnagar, Uttar Pradesh.
When will GREENWOOD ESTATE be completed?
The latest completion date reported to UP-RERA for GREENWOOD ESTATE is 30 Jun 2026.
Is GREENWOOD ESTATE delayed?
Measured against the latest completion date reported to UP-RERA, GREENWOOD ESTATE is 1 month beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026