Timeline Bar

Registered1 Aug 2017
Promised28 Feb 2021
Completed15 Oct 2022

Timeline

Promised completion28 Feb 2021
Revised completion28 Feb 2021
Actual completion15 Oct 2022
Possession delay20 mo delay

Registration & Cost Details

Registration fee (in ₹)₹5,31,500
Project cost (in ₹ Lakhs)₹96,690 Lakhs
Project duration75 months
Project categoryResidential
Locality
Original start date1 Mar 2016
Proposed start date1 Mar 2016

Inventory

Total units1794
Unit TypeUnitsCarpet Area (sqm)
1 BHK10442.22
2 BHK50669.34
3 BHK84891.64
4 BHK336126.67

Promoters & Contact

Contact Details

Applicant TypeSocieties
Mobile7065044956
Emailcgewho@nic.in
Coordinator7065044956
Address6TH FLOOR , JANPATH BHAWAN, A WING ,JANPATH NEW DELHI 01

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q33.0%
2021-Q4
2022-Q12.6%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/(BP)2836FTSNO-66125 Jan 201624 Jan 202128 Feb 202124 Jan 2023

Land Parcels

Khasra No.AreaPlot Type
SECTOR P4BUILDERS AREA
7153832Plot

Approved Unit Plan

Unit plan rows on file28
Total flats (sum of rows)1794
Blocks1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1817616 Jul 2010

Frequently Asked Questions

What is the RERA registration number of GROUP HOUSING CGEWHO PHASE I?

The RERA registration number of GROUP HOUSING CGEWHO PHASE I is UPRERAPRJ1005, as recorded on the UP-RERA portal.

What is the RERA status of GROUP HOUSING CGEWHO PHASE I?

As reported by UP-RERA, the status of GROUP HOUSING CGEWHO PHASE I is "Registered".

Where is GROUP HOUSING CGEWHO PHASE I located?

As reported to UP-RERA, GROUP HOUSING CGEWHO PHASE I is located at PLOT NO.7, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is GROUP HOUSING CGEWHO PHASE I completed?

As reported to UP-RERA, GROUP HOUSING CGEWHO PHASE I was completed on 15 Oct 2022.

Is GROUP HOUSING CGEWHO PHASE I delayed?

Measured against the latest completion date reported to UP-RERA, GROUP HOUSING CGEWHO PHASE I is 20 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026