GROUP HOUSING CGEWHO PHASE II is a RERA-registered residential project by CENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING ORGAN in Sector P4, Gautam Budh Nagar (RERA ID UPRERAPRJ674438). Registered with a completion deadline of 2 Oct 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
3.16%Q3'25
2.11%Q4'25
3.21%Q1'26
3.74%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ674438
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start29 Jan 2024
Project duration45 months
AddressPlot No. 07, Sector P-4, Builders Area, Greater Noida, Sector P4, Dadri, Gautam Budh Nagar
TehsilDadri
Applicant typeSocieties
Applicant address6TH FLOOR , JANPATH BHAWAN, A WING ,JANPATH NEW DELHI 01
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG(BP)2836-S/520 DATED 03.10.2022

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered22 Feb 2024
Original completion2 Oct 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹4,47,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors336 · 6 · 16 (units from plan)
ConfigurationUnitsCarpet area
4 BHK336127
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
D1 (D-11) · OTHER, 4 BHK1656127
D10 (D-8) · OTHER, 4 BHK1656127
D11 (D-9) · OTHER, 4 BHK1656127
D12 (D-10) · OTHER, 4 BHK1656127
D2 (D-12) · OTHER, 4 BHK1656127
D9 (D-7) · OTHER, 4 BHK1656127
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
R T AND ASSOCIATES PVT LTD. RAHUL TYAGI
License CA/97/22027
A-48 SEC 67 NOIDA 201310
Engineer
Dr. GYAN CHAND
PLOT NO 1085 NITIKHAND 1 INDRAPURAM- GHAZIABAD UP 201014
Contractor
KANWARJI CONSTRUCTION CO.
2nd FLOOR HOUSE NUMBER G 144 GOVIND PURAM HAPUR ROAD GHAZIABAD UP 201310
Sr.Development work declared to RERA
1Demarcation of Plots
MULTISTORY BUILDING
2Boundary Wall
FOUNDATION IN RCC+ SUPERSTRUCTURE IN BRICK WORK + MS RAILING
3Road Work
VACCUM DEWATERED REINFORCED CEMENT CONCRETE ROADS
4Footpaths
PAVERS BLOCKS/ CHECKERED TILES
5Water Supply Including Drinking Water Facilities
GI PIPES/ CPVC PIPES
6Sewer System
SCI PIPES / HUME PIPE WITH SEWAGE TREATMENT PLANT
7Drain
SCI PIPES, COVERED CHANNEL DRAINS WITH RAIN WATER HARVENTING SYSTEM
8Parks
7817 Sq.Mt. GREEN PROPOSED
9Tree Planting
300 No. TREE PROPOSED
10Design For Electric Supply Including Street Lighting
11 KVA ELECTRICAL SUPPLY BY NPCL
11Community Buildings
EXISTING COMMUNITY CENTRE WITH MULTI PURPOSE HALLS AND FACILITIES
12Treatment and Disposal System of Sewage and Sullage water
175 KLD STP PROPOSED
13Solid Waste Management And Disposal System
EXISTING BIO DIGESTOR
14Water Conservation System
RAIN WATER HARVESTING SYSTEM
15Energy Management System Including Use of Renewable Energy
SOLAR STREET LIGHTS AND SOLAR WATER HEATING SYSTEM FOR KITCHEN ONLY
16Fire Protection And Fire Safety System
AS PER NBC PROPOSED
17Social Infrastructure And Other Public Amenities Including Public Health Services
SHOPPING, NURSING HOME AND NURSERY SCHOOL
18Emergency Evacuation Services
FIRE STAIRCASE WITH FIRE ALARM SYSTEM
19Other Miscellaneous Work
AS PER NBC
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 2 Oct 2027.

Sanctioned by Greater Noida Authority · 28,049 sqm of land · an approved plan of 6 blocks and 336 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG(BP)2836-S/520 DATED 03.10.20223 Oct 20222 Oct 20272 Oct 20282 Oct 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

23 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
7 SEC P4153781Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 18176
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New14 Feb 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New21 Dec 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New21 Dec 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New21 Dec 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New20 Dec 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New20 Dec 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New21 Dec 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New20 Dec 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New9 Jan 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New29 Jan 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New18 Jan 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New2 Feb 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New18 Jan 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New21 Dec 2023 ↗

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2023-Q4 to 2026-Q2.

QuarterConstructionCertificates
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q23.16%CA ↗ · Arch ↗ · Eng ↗
2025-Q32.11%CA ↗ · Arch ↗ · Eng ↗
2025-Q43.21%CA ↗ · Arch ↗ · Eng ↗
2026-Q13.74%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameCENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING ORGAN
RolePromoter · current
RERA IDUPRERAPRM2209
PANAAATC1861B
CIN / TANS/21181
Registered address6TH FLOOR , JANPATH BHAWAN, A WING ,JANPATH NEW DELHI 01
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
CGEWHO COLLECTION ACCOUNT FOR GREATER NOIDA PH-II PROJECTBankCANARA BANKBranchNOIDA MORNABranch addressB16/17 SEC 18 NOIDA GAUTAM BUDDHA NAGAR 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCCNRB0018778Branch emailcb18778@canarabank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
CGEWHO SEPARATE BANK ACCOUNT FOR GREATER NOIDA PH-II PROJECTBankCANARA BANKBranch18778-NOIDA (MORNA) BRANCHBranch addressSEC 18 NOIDA MORNA UTTAR PRADESH 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCCNRB0018778
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
CGEWHO RERA TRANSACTION ACCOUNT FOR GREATER NOIDA PH-II PROJECTBankCANARA BANKBranch18778-NOIDA (MORNA) 201301Branch addressSEC 18 NOIDA, MORNA, UTTAR PRADESH 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCCNRB0018778
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
18 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about GROUP HOUSING CGEWHO PHASE II

Is GROUP HOUSING CGEWHO PHASE II RERA registered?

Yes. GROUP HOUSING CGEWHO PHASE II is registered with UPRERA under registration number UPRERAPRJ674438, registered on 22 Feb 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for GROUP HOUSING CGEWHO PHASE II?

The completion date filed with UPRERA is 2 Oct 2027. No completion certificate is on record yet.

Who is the builder of GROUP HOUSING CGEWHO PHASE II?

CENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING ORGAN is the promoter entity that filed GROUP HOUSING CGEWHO PHASE II with UPRERA (promoter RERA ID UPRERAPRM2209). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does GROUP HOUSING CGEWHO PHASE II have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is GROUP HOUSING CGEWHO PHASE II located?

GROUP HOUSING CGEWHO PHASE II is registered in Sector P4, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in GROUP HOUSING CGEWHO PHASE II?

The unit plan filed with UPRERA lists OTHER and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in GROUP HOUSING CGEWHO PHASE II?

The approved unit plan describes 6 blocks and 336 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is GROUP HOUSING CGEWHO PHASE II?

About 48 units per acre: 336 planned units across 6.93 acres (28,049 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗