Estanzo

Timeline Bar

Registered29 May 2023
Completed29 May 2024
Promised31 Jul 2024

Timeline

Promised completion31 Jul 2024
Revised completion31 Jul 2024
Actual completion29 May 2024
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,88,000
Project cost (in ₹ Lakhs)₹512 Lakhs
Project duration23 months
Project categoryCommercial
Locality
Original start date
Proposed start date1 Feb 2023

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8009551300
Emailcsd@rituhousing.com
Coordinator8826900994
AddressKAMLA TOWER, KANPUR, U.P.-208001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Plotted development/04257/KDA/LD/22-23/1674/2903202320 May 202319 May 202831 Jul 202418 May 2029

Land Parcels

Khasra No.AreaPlot Type
Plot No. 2, Scheme No. 39, Jajmau, Kanpur17791.34Plot

Frequently Asked Questions

What is the RERA registration number of GULISTAN PLAZA?

The RERA registration number of GULISTAN PLAZA is UPRERAPRJ838684, as recorded on the UP-RERA portal.

What is the RERA status of GULISTAN PLAZA?

As reported by UP-RERA, the status of GULISTAN PLAZA is "Registered".

Where is GULISTAN PLAZA located?

As reported to UP-RERA, GULISTAN PLAZA is located at Kanpur, Kanpur Nagar, Uttar Pradesh.

Is GULISTAN PLAZA completed?

As reported to UP-RERA, GULISTAN PLAZA was completed on 29 May 2024.

Is GULISTAN PLAZA delayed?

Measured against the latest completion date reported to UP-RERA, GULISTAN PLAZA is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.