Timeline Bar

Registered15 Aug 2017
Promised3 Sept 2021
Today4 Aug 2026

Timeline

Promised completion3 Sept 2021
Revised completion3 Sept 2021
Actual completion
Possession delay59 mo delay

Registration & Cost Details

Registration fee (in ₹)₹18,500
Project cost (in ₹ Lakhs)₹4,444 Lakhs
Project duration55 months
Project categoryResidential
Locality
Original start date4 Sept 2013
Proposed start date14 Aug 2017

Inventory

Total units74
Unit TypeUnitsCarpet Area (sqm)
3 BHK7491.43–99.42

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8860618422
Emailhilston@urbtechindia.com
Coordinator8860618422
AddressS- 116, BASEMENT, GREATER KAILSAH-II, NEW DELHI

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/CPA/2013/IV-1409/6924 Sept 20133 Sept 20183 Sept 20213 Sept 2023

Land Parcels

Khasra No.AreaPlot Type
SC-01/B1-SECTOR 7924000

Approved Unit Plan

Unit plan rows on file22
Total flats (sum of rows)74
BlocksTower G
Floor types3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
507620 Oct 2012

Frequently Asked Questions

What is the RERA registration number of Hilston by URBTECH - TOWER G?

The RERA registration number of Hilston by URBTECH - TOWER G is UPRERAPRJ11498, as recorded on the UP-RERA portal.

What is the RERA status of Hilston by URBTECH - TOWER G?

As reported by UP-RERA, the status of Hilston by URBTECH - TOWER G is "Registered".

Where is Hilston by URBTECH - TOWER G located?

As reported to UP-RERA, Hilston by URBTECH - TOWER G is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Hilston by URBTECH - TOWER G be completed?

The latest completion date reported to UP-RERA for Hilston by URBTECH - TOWER G is 3 Sept 2021.

Is Hilston by URBTECH - TOWER G delayed?

Measured against the latest completion date reported to UP-RERA, Hilston by URBTECH - TOWER G is 59 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.