Timeline Bar
Registered11 Aug 2017
Promised31 Mar 2021
Today3 Aug 2026
Timeline
Promised completion31 Mar 2021
Revised completion31 Mar 2021
Actual completion—
Possession delay64 mo delay
Registration & Cost Details
Registration fee (in ₹)₹2,55,000
Project cost (in ₹ Lakhs)₹80,600 Lakhs
Project duration57 months
Project categoryResidential
Locality—
Original start date1 Apr 2015
Proposed start date31 Dec 2016
Inventory
Total units1087
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 3 BHK | 1007 | 85.65–115.91 |
| 4 BHK | 80 | 85.65–143.67 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8505833393
Emailreracompliance@lotusarena1.in
Coordinator8505833393
AddressFlat No.14, Ground Floor, Pul Pehlad Pur, DDA MIG Suraj Apartment, New Delhi – 110044
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| IV-1399/731 | 29 Apr 2014 | 28 Apr 2019 | 31 Mar 2021 | 27 Apr 2024 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| Not Applicable | 0 | — |
| SC-01/A2, Sector-79, Noida | 50000 | Plot |
Approved Unit Plan
Unit plan rows on file633
Total flats (sum of rows)1087
BlocksA1/T1/A, A2/T2/B, A3/T3/C, A4/T4/D, A5/T5/E, A6/T6/F, B1/T9/G, B2/T8/H, B3/T7/J
Floor types3 BHK, 4 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 5077 | 20 Oct 2012 | — | — |
Frequently Asked Questions
What is the RERA registration number of Lotus Arena?
The RERA registration number of Lotus Arena is UPRERAPRJ5409, as recorded on the UP-RERA portal.
What is the RERA status of Lotus Arena?
As reported by UP-RERA, the status of Lotus Arena is "Registered".
Where is Lotus Arena located?
As reported to UP-RERA, Lotus Arena is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will Lotus Arena be completed?
The latest completion date reported to UP-RERA for Lotus Arena is 31 Mar 2021.
Is Lotus Arena delayed?
Measured against the latest completion date reported to UP-RERA, Lotus Arena is 64 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026