HIM Golden City

UPRERARegistered

HIM Golden City is a RERA-registered residential project by John Business Consultants Private Limited in Banthara, Lucknow (RERA ID UPRERAPRJ835863). Registered with a completion deadline of 30 Sept 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
23%Q4'25
15%Q1'26
15%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ835863
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Industrial Development Authority
Proposed start1 Oct 2025
Project duration48 months
AddressKhasra No. 322, 323, 336, 338, Banthara, Sarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompany
Applicant address2nd Floor, Flat no-201,A- Block, Rohit Bhawan, Saprumarg, Hazratganj, Lucknow-226001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    1136/770upsida/pri.ka./2024-25

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered21 Nov 2025
Original completion30 Sept 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹36,500
Sanctioning authorityLucknow Industrial Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Sanjay Kumar Gupta
License CA/1989/12382
108, 1st Floor, Corporate Chamber-1, Vibhuti Khand, Gomti Nagar, Lucknow
Engineer
Bilal Akbar
235/12, Gali Shachara Victoria Street Chowk, Lucknow- 226003
Contractor
New India Constructions
292/185 Tulsidas Marg, Lucknow 226003
Sr.Development work declared to RERA
1Demarcation of Plots
We have one plot having 1 main entrance gate from the 30 m wide front road.
2Boundary Wall
2 m high and 230 mm thick Brick work and rcc work in column and beam. At the center face of boundary wall there would be a Logo of the project which give a beautiful iconic design to boundary wall.
3Road Work
From the main entrance gate we have 80 mm thick interlocking brick / RCC road, throughout the project. Whose wideness starts from 10 mtr.
4Footpaths
We would not provide any footpath
5Water Supply Including Drinking Water Facilities
We will provide Two nos. of pump for the requirement of blocks through underground pipelines.
6Sewer System
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system when come into force.
7Drain
Storm water shall be Provided. Storm water from Roads and other landscape area shall be connect to the Storm water drain channel and go to the Rainwater harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
8Parks
We will provide green area with the different activities and the green area will have gaming facilities for kids.
9Tree Planting
We will provide many type of trees all along the boundary wall & green area
10Design For Electric Supply Including Street Lighting
We will design & implement the system as per local electricity Board and will consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and DG back for common service like External lighting, Fountain, STP, Pump room etc.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system. when come into force.
13Solid Waste Management And Disposal System
There is proper garbage collection area provided for the solid waste management.
14Water Conservation System
We will suggest to individual to use low flow fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
16Fire Protection And Fire Safety System
We will provide Fire Fighting facility in common areas while Individual owner can install their own system as per their and local authoritys requirement.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
Not Applicable
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 26 Dec 2029.

Sanctioned by Lucknow Industrial Development Authority · 6,618 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
1136/770upsida/pri.ka./2024-2527 Dec 202426 Dec 202926 Dec 203230 Sept 2029
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

21 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
322209.11Khasra
323590.89Khasra
336629.28Khasra
3385555.73Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 36209
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 36205
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 36213
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 12499
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1429-1434
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 980
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 205
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New28 Aug 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New9 Aug 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New9 Aug 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New9 Aug 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New9 Aug 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New9 Aug 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New9 Aug 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New9 Aug 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New9 Aug 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New8 Sept 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New8 Sept 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New8 Sept 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New28 Aug 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New9 Aug 2025 ↗

Quarterly progress reports

3 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

3 quarterly progress reports are on file with UPRERA, covering 2025-Q3 to 2026-Q1.

QuarterConstructionCertificates
2025-Q323%CA ↗ · Arch ↗ · Eng ↗
2025-Q415%CA ↗ · Arch ↗ · Eng ↗
2026-Q115%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameJohn Business Consultants Private Limited
RolePromoter · current
RERA IDUPRERAPRM373450
PANAAECJ6167C
CIN / TANU74999UP2019PTC119751
Name of chairmanSyed Mohd John Abbas Rizvi
Registered address2nd Floor, Flat no-201,A- Block, Rohit Bhawan, Saprumarg, Hazratganj, Lucknow-226001
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameHIM PROPERTIES & DEVELOPERS PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
Address340/35KA, Bhawaniganj, Khala Bazar, Chowk, Lucknow-226003
RERA contact

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
JOHN BUSINESS CONSULTANTS PVT LTD COLLE. AC HIM GOLDEN CITYBankState Bank of IndiaBranchSBI HazratganjBranch addressSME Hazratganj Branch 1, Shahnajaf road, HazratganjBranch districtUttar PradeshA/C no.IFSCSBIN0016882Branch emailsbi.16882@sbi.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
JOHN BUSINESS CONSULTANTS PVT LTD SEPARA. AC HIM GOLDEN CITYBankState Bank of IndiaBranchSBI HazratganjBranch addressSME Hazratganj Branch 1, Shahnajaf road, HazratganjBranch districtUttar PradeshA/C no.IFSCSBIN0016882
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
JOHN BUSINESS CONSULTANTS PVT LTD TRANS. AC HIM GOLDEN CITYBankState Bank of IndiaBranchSBI HazratganjBranch addressSME Hazratganj Branch 1, Shahnajaf road, HazratganjBranch districtUttar PradeshA/C no.IFSCSBIN0016882
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about HIM Golden City

Is HIM Golden City RERA registered?

Yes. HIM Golden City is registered with UPRERA under registration number UPRERAPRJ835863, registered on 21 Nov 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for HIM Golden City?

The completion date filed with UPRERA is 30 Sept 2029. No completion certificate is on record yet.

Who is the builder of HIM Golden City?

John Business Consultants Private Limited is the promoter entity that filed HIM Golden City with UPRERA (promoter RERA ID UPRERAPRM373450). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does HIM Golden City have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is HIM Golden City located?

HIM Golden City is registered in Banthara, Lucknow, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗