Registered9 Aug 2017
Promised31 Dec 2018
Completed5 Aug 2020

Timeline

Promised completion31 Dec 2018
Revised completion31 Dec 2018
Actual completion5 Aug 2020
Possession delay19 mo delay

Registration & Cost Details

Registration fee (in ₹)₹75,000
Project cost (in ₹ Lakhs)₹1,60,00,00,000 Lakhs
Project duration69 months
Project categoryResidential
Locality
Original start date1 Apr 2013
Proposed start date1 Apr 2013

Inventory

Total units384
Unit TypeUnitsCarpet Area (sqm)
1 BHK838.86–39.2
2 BHK18551.48–65.57
3 BHK19161.38–6138

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9718323007
Emailinfo@himalayaresidency.in
Coordinator9718457780

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BP2773/GH/OPT/110414 Feb 201315 Dec 201731 Dec 201814 Nov 2022

Land Parcels

Khasra No.AreaPlot Type
GH-10B27665Plot

Approved Unit Plan

Unit plan rows on file134
Total flats (sum of rows)384
BlocksTOWER A, TOWER-A, TOWER-B, TOWER-E
Floor types1 BHK, 2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of HIMALAYA PRIDE (PHASE 1 : TOWER A & B)?

The RERA registration number of HIMALAYA PRIDE (PHASE 1 : TOWER A & B) is UPRERAPRJ8836, as recorded on the UP-RERA portal.

What is the RERA status of HIMALAYA PRIDE (PHASE 1 : TOWER A & B)?

As reported by UP-RERA, the status of HIMALAYA PRIDE (PHASE 1 : TOWER A & B) is "Registered".

Where is HIMALAYA PRIDE (PHASE 1 : TOWER A & B) located?

As reported to UP-RERA, HIMALAYA PRIDE (PHASE 1 : TOWER A & B) is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

Is HIMALAYA PRIDE (PHASE 1 : TOWER A & B) completed?

As reported to UP-RERA, HIMALAYA PRIDE (PHASE 1 : TOWER A & B) was completed on 5 Aug 2020.

Is HIMALAYA PRIDE (PHASE 1 : TOWER A & B) delayed?

Measured against the latest completion date reported to UP-RERA, HIMALAYA PRIDE (PHASE 1 : TOWER A & B) is 19 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.