Timeline Bar
Timeline
Registration & Cost Details
Inventory
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 1 BHK | 8 | 38.86–39.2 |
| 2 BHK | 185 | 51.48–65.57 |
| 3 BHK | 191 | 61.38–6138 |
Promoters & Contact
Contact Details
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| BP2773/GH/OPT/1104 | 14 Feb 2013 | 15 Dec 2017 | 31 Dec 2018 | 14 Nov 2022 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| GH-10B | 27665 | Plot |
Approved Unit Plan
Individual floor/unit rows are not listed here.
Frequently Asked Questions
What is the RERA registration number of HIMALAYA PRIDE (PHASE 1 : TOWER A & B)?
The RERA registration number of HIMALAYA PRIDE (PHASE 1 : TOWER A & B) is UPRERAPRJ8836, as recorded on the UP-RERA portal.
What is the RERA status of HIMALAYA PRIDE (PHASE 1 : TOWER A & B)?
As reported by UP-RERA, the status of HIMALAYA PRIDE (PHASE 1 : TOWER A & B) is "Registered".
Where is HIMALAYA PRIDE (PHASE 1 : TOWER A & B) located?
As reported to UP-RERA, HIMALAYA PRIDE (PHASE 1 : TOWER A & B) is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.
Is HIMALAYA PRIDE (PHASE 1 : TOWER A & B) completed?
As reported to UP-RERA, HIMALAYA PRIDE (PHASE 1 : TOWER A & B) was completed on 5 Aug 2020.
Is HIMALAYA PRIDE (PHASE 1 : TOWER A & B) delayed?
Measured against the latest completion date reported to UP-RERA, HIMALAYA PRIDE (PHASE 1 : TOWER A & B) is 19 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.