Estanzo

Timeline Bar

Registered9 Aug 2017
Promised31 Dec 2019
Completed5 Aug 2020

Timeline

Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion5 Aug 2020
Possession delay7 mo delay

Registration & Cost Details

Registration fee (in ₹)₹45,000
Project cost (in ₹ Lakhs)₹90,00,00,000 Lakhs
Project duration55 months
Project categoryResidential
Locality
Original start date30 Jun 2015
Proposed start date30 Jun 2015

Inventory

Total units330
Unit TypeUnitsCarpet Area (sqm)
2 BHK16063.02–63.07
3 BHK12073.11–101.31
PENTHOUSE1039.22–139
SHOP409.22–59.52

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9718323007
Emailinfo@himalayaresidency.in
Coordinator9718457780

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BPS55539

Revalidated: BPS55539 (15 Dec 2017)

15 Dec 20175 Jun 2020

Revalidated upto: 30 Apr 2023

31 Dec 201931 Dec 2020

Land Parcels

Khasra No.AreaPlot Type
GH-10B27665.00Plot

Approved Unit Plan

Unit plan rows on file125
Total flats (sum of rows)330
Total shops40
BlocksTOWER-C
Floor types2 BHK, 3 BHK, PENTHOUSE, SHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of HIMALAYA PRIDE (PHASE 2 : TOWER C)?

The RERA registration number of HIMALAYA PRIDE (PHASE 2 : TOWER C) is UPRERAPRJ8888, as recorded on the UP-RERA portal.

What is the RERA status of HIMALAYA PRIDE (PHASE 2 : TOWER C)?

As reported by UP-RERA, the status of HIMALAYA PRIDE (PHASE 2 : TOWER C) is "Registered".

Where is HIMALAYA PRIDE (PHASE 2 : TOWER C) located?

As reported to UP-RERA, HIMALAYA PRIDE (PHASE 2 : TOWER C) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is HIMALAYA PRIDE (PHASE 2 : TOWER C) completed?

As reported to UP-RERA, HIMALAYA PRIDE (PHASE 2 : TOWER C) was completed on 5 Aug 2020.

Is HIMALAYA PRIDE (PHASE 2 : TOWER C) delayed?

Measured against the latest completion date reported to UP-RERA, HIMALAYA PRIDE (PHASE 2 : TOWER C) is 7 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.