Estanzo

Timeline Bar

Registered14 Aug 2017
Promised31 Mar 2019
Completed3 Apr 2024

Timeline

Promised completion31 Mar 2019
Revised completion31 Mar 2019
Actual completion3 Apr 2024
Possession delay60 mo delay

Registration & Cost Details

Registration fee (in ₹)₹99,000
Project cost (in ₹ Lakhs)₹17,218 Lakhs
Project duration112 months
Project categoryResidential
Locality
Original start date9 Jun 2011
Proposed start date9 Jun 2011

Inventory

Total units395
Unit TypeUnitsCarpet Area (sqm)
2 BHK2859.27–65.96
3 BHK11085.19

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile7042604789
Emailepvrera@iitlnimbusgroup.com
Coordinator8743979519
Address1010-1011, 10th Floor, Narain Manzil 23, Barakhamba Road, New Delhi, 110001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BP2720/44/CLS7031

Revalidated: PLG/(BP)2720/998 (24 Jan 2019)

28 Sept 201227 Sept 2017

Revalidated upto: 23 Jan 2024

31 Mar 201923 Jan 2024

Land Parcels

Khasra No.AreaPlot Type
PLOT NO GH-03 SECTOR CHI-V52493.16
GH-0352493.16Plot

Approved Unit Plan

Unit plan rows on file198
Total flats (sum of rows)395
BlocksI1, J1, K1
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
101889 Jun 2011
18718 (CORRECTION DEED)28 Sept 2012

Frequently Asked Questions

What is the RERA registration number of IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1)?

The RERA registration number of IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) is UPRERAPRJ10246, as recorded on the UP-RERA portal.

What is the RERA status of IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1)?

As reported by UP-RERA, the status of IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) is "Registered".

Where is IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) located?

As reported to UP-RERA, IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) completed?

As reported to UP-RERA, IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) was completed on 3 Apr 2024.

Is IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) delayed?

Measured against the latest completion date reported to UP-RERA, IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) is 60 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026