CASA GRANDE-2

UPRERARegistered

CASA GRANDE-2 is a RERA-registered residential project by EARTHCON CONSTRUCTIONS PRIVATE LIMITED in Gautam Budh Nagar (RERA ID UPRERAPRJ4491). Registered with a completion deadline of 5 Oct 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
66.21%Q4'24
71.3%Q1'25
75.3%Q2'25
81.3%Q3'25
85.3%Q4'25
88.32%Q1'26
90.71%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ4491
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start4 Mar 2013
Original start4 Mar 2013
Project duration164 months
AddressGH-06C, Sector Chi-05, Greater Noida, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressT-17,D D Flat, Jasola Vihar, New Delhi-110025
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 5 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. valid to

    Permit revalidated

    NIYO/2023/972

  9. valid to

    Permit revalidated

    NIYO/2025/1854

  10. Completion certificate filed

  11. to

    Extension granted

  12. Completion certificate filed

  13. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered8 Aug 2017
Original completion31 Dec 2020
Revised completion5 Oct 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary16 Aug 2025
Registration fee₹96,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors582 · 4 · 20 (units from plan)
Homes · commercial units572 · 10 (shops and offices filed in the same plan)
  • 1 BHK254 44%
  • 2 BHK210 36%
  • 3 BHK108 19%
  • SHOP10 2%
ConfigurationUnitsCarpet area
3 BHK10891-104
2 BHK21062-70
1 BHK25419-34
SHOP1016-101
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A2 · 3 BHK, OTHER2010891-104
B1 · 2 BHK, OTHER2010562-70
B2 · 2 BHK, OTHER2010562-70
Beetle Suites · 1 BHK, SHOP, OTHER1926416-41
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mod Arch India
License CA/98/22706
1st Floor, B-99, Sectot-63, Noida-201301
Contractor
Ascent Constructions Private Limited
Sr.Development work declared to RERA
1Demarcation of Plots
Front Side 24 meter. wide road , Back Side Abadi Expansion, Right side plot no. GH-06B & Left Side Informal
2Boundary Wall
2.1meter. Hight boundary wall and 547.45meter. Long
3Road Work
6meter. wide Internal Road & 6meter. Wide road around the tower for circulation
4Footpaths
927.891 sq. m.( Area of Footpath)
5Water Supply Including Drinking Water Facilities
Under Ground Water Tank 200 KL Raw Water & 200 KL Treated water Tank external water Supply with Distribution .
6Sewer System
External Sewerage with STP
7Drain
External storm water drainage with RWH
8Parks
Total Landscaping Area including road 7237.667 Sq.Meter
9Tree Planting
No of proposed Tree-144 and No of proposed evergreen tree-72
10Design For Electric Supply Including Street Lighting
Total load of Project 5061 KW the capacity of transformer is 5210 KVA & the transformer of 2 nos of 2000 KVA Load & Transformer of 1250 KV(Total Electric load=3419.67 KV)
11Community Buildings
Yes, One community centre (G+1) is planned.
12Treatment and Disposal System of Sewage and Sullage water
STP of 600 KLD with 300 KL of treated effluent Storage tank for flushing Gardening System.
13Solid Waste Management And Disposal System
Solid Waste Management System is planned as Per inviorment clearance by (EIA).
14Water Conservation System
Rain Water Harvesting System 4 nos of 4.35 m dia x 4.50 m (Depth) RWH well with 1.50m x 1.50m De-silt and 300mm dia x 25 m boring.
15Energy Management System Including Use of Renewable Energy
As per guidelines of ministry of renewable energy Govt. of India.
16Fire Protection And Fire Safety System
Sprinklers And Alarm Sytem are proposed for towers more than 60m ht.
17Social Infrastructure And Other Public Amenities Including Public Health Services
N.A.
18Emergency Evacuation Services
As per fire norms & fire NOC is received
19Other Miscellaneous Work
Commmunity building & water body
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

5 permits

An approval and the date it runs to - not proof the work matching it was done.

5 sanctioning permits are on record with UPRERA, the latest valid to 4 Mar 2018. 4 of them carry a revalidation, the latest valid to 6 Oct 2025.

Sanctioned by Greater Noida Authority · 17,246.55 sqm of land · an approved plan of 4 blocks and 582 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
PLG/BP-3025/GH/OPA-14884 Mar 20134 Mar 20185 Mar 202331 Dec 2020—
PLG/BP-3025/GH/OPA-14884 Mar 20134 Mar 20186 Oct 202530 Jun 20214 Mar 2013
valid to 6 Oct 2025
PLG/BP-3025/GH/OPA-14884 Mar 20134 Mar 20185 Oct 20306 Oct 20254 Mar 2013
valid to 6 Oct 2025
PLG/BP-3025/GH/OPA-14884 Mar 20134 Mar 20184 Oct 20306 Oct 202521 Dec 2021
valid to 6 Oct 2025
as NIYO/2023/972
PLG/BP-3025/GH/OPA-14884 Mar 20134 Mar 20185 Oct 20306 Oct 20257 Nov 2024
valid to 6 Oct 2025
as NIYO/2025/1854
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 5 Oct 2026.

#Granted fromExtended uptoNote
131 Dec 202030 Jun 2021Six months extension in view of force majeure caused by covid-19 pandemic
230 Jun 20216 Oct 2025—
36 Oct 20255 Oct 2026—

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-06C18154Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 20081
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New4 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New3 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New3 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New3 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New3 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New3 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New3 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New4 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Jul 2018 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old23 Feb 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old23 Feb 2018 ↗

Quarterly progress reports

26 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

26 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q231.4%CA ↗ · Arch ↗ · Eng ↗
2021-Q331.4%CA ↗ · Arch ↗ · Eng ↗
2021-Q432.74%CA ↗ · Arch ↗ · Eng ↗
2022-Q133.65%CA ↗ · Arch ↗ · Eng ↗
2022-Q234.9%CA ↗ · Arch ↗ · Eng ↗
2022-Q337.87%CA ↗ · Arch ↗ · Eng ↗
2022-Q442.16%CA ↗ · Arch ↗ · Eng ↗
2023-Q147.66%CA ↗ · Arch ↗ · Eng ↗
2023-Q250.86%CA ↗ · Arch ↗ · Eng ↗
2023-Q353.96%CA ↗ · Arch ↗ · Eng ↗
2023-Q456.98%CA ↗ · Arch ↗ · Eng ↗
2024-Q160.03%CA ↗ · Arch ↗ · Eng ↗
2024-Q263.05%CA ↗ · Arch ↗ · Eng ↗
2024-Q366.21%CA ↗ · Arch ↗ · Eng ↗
2024-Q471.3%CA ↗ · Arch ↗ · Eng ↗
2025-Q175.3%CA ↗ · Arch ↗ · Eng ↗
2025-Q281.3%CA ↗ · Arch ↗ · Eng ↗
2025-Q385.3%CA ↗ · Arch ↗ · Eng ↗
2025-Q488.32%CA ↗ · Arch ↗ · Eng ↗
2026-Q190.71%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameEARTHCON CONSTRUCTIONS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM5849
PANAABCE5693F
CIN / TANDELE04226F
Name of chairmanMR. SHADAB KHAN
Registered addressT-17,D D Flat, Jasola Vihar, New Delhi-110025
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
EARTHCON CONSTRUCTIONS PVT LTD COLLECTION ACCOUNT CASA GRANDE2BankINDUSIND BANK LTDBranchSECTOR-18Branch addressGROUND FLOOR,SHOP NO-18,18A,18B,ANSAL FORTUNE ARCADE,CAPTAIN VIJAYANT THAPAR,,POCKETE,SECTOR-18,NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCINDB0000036Branch emailramesh.rawatindusind.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Earthcon Constructions Pvt Ltd Separate Bank Account Casa Grande2BankIndusind Bank LtdBranchSector-18Branch addressGround Floor, Shop No-18,18A,18B, Ansal Fortune Arcade, Captain Vijayant Thapar Marg, PocketE, Sector-18,Noida,Gautam Budh Nagar,Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCINDB0000036Branch emailramesh.rawatindusind.com
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
EARTHCON CONSTRUCTION PVT LTD TRANSACTION ACCOUNT CASA GRANDE2BankINDUSIND BANK LTDBranchSECTOR-18Branch addressGROUND FLOOR ,SHOP NO-18,18A,18B,ANSAL FORTUNE ARCADE, CAPTAIN VIJAYANT THAPAR MARG, POCKET-E, SECTOR-18, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCINDB0000036Branch emailramesh.rawat indusind.com
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

10 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
Promoter’s complaints tally (all their projects)148 (Under Registration - 2 ) → 149 (Under Registration - 3 )
changed in Estanzo’s record
1 Oct 2026
Promoter’s complaints tally (all their projects)148 (Under Registration - 3 ) → 148 (Under Registration - 2 )
changed in Estanzo’s record
23 Sept 2026
Quarterly progress report
2026-Q1
QPR 2026-Q1
newly filed with RERA
23 Sept 2026
Revised completion date on file2025-10-06 → 2026-10-05
changed in Estanzo’s record
17 Sept 2026
Completion extension
no. 3
extension 3 to 2026-10-05
newly filed with RERA
17 Sept 2026
Promoter’s complaints tally (all their projects)147 (Under Registration - 2 ) → 148 (Under Registration - 3 )
changed in Estanzo’s record
13 Sept 2026
Promoter’s complaints tally (all their projects)146 (Under Registration - 1 ) → 147 (Under Registration - 2 )
changed in Estanzo’s record
11 Sept 2026
Promoter’s complaints tally (all their projects)146 (Under Registration - 4 ) → 146 (Under Registration - 1 )
changed in Estanzo’s record
9 Sept 2026
Promoter’s complaints tally (all their projects)145 (Under Registration - 3 ) → 146 (Under Registration - 4 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Revised completion date on filechanged in Estanzo’s record · 17 Sept 2026
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 1 Oct 2026 · 6 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about CASA GRANDE-2

Is CASA GRANDE-2 RERA registered?

Yes. CASA GRANDE-2 is registered with UPRERA under registration number UPRERAPRJ4491, registered on 8 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has CASA GRANDE-2 been completed?

UPRERA still lists CASA GRANDE-2 as Registered, so it is not shown as completed here. A completion certificate dated 16 Aug 2025 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of CASA GRANDE-2?

EARTHCON CONSTRUCTIONS PRIVATE LIMITED is the promoter entity that filed CASA GRANDE-2 with UPRERA (promoter RERA ID UPRERAPRM5849). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted CASA GRANDE-2 more time to complete?

UPRERA's record carries 3 completion extensions for CASA GRANDE-2, the latest running to 5 Oct 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does CASA GRANDE-2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is CASA GRANDE-2 located?

CASA GRANDE-2 is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in CASA GRANDE-2?

The unit plan filed with UPRERA lists 3 BHK, 2 BHK, 1 BHK, SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in CASA GRANDE-2?

The approved unit plan filed with UPRERA runs from 16 to 104 m² of carpet area (about 173 to 1,119 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in CASA GRANDE-2?

The approved unit plan describes 4 blocks and 582 units of which 572 are homes and 10 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is CASA GRANDE-2?

About 137 units per acre: 582 planned units across 4.26 acres (17,246.55 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗