Irish Platinum

UPRERARegistered

Irish Platinum is a RERA-registered residential project by Irish Buildcon Private Limited in Sector-10, Gautam Budh Nagar (RERA ID UPRERAPRJ503189). Registered with a completion deadline of 31 Jan 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
22.37%Q3'25
27.36%Q4'25
31.66%Q1'26
35.82%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ503189
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Jan 2024
Project duration61 months
AddressGh-04A Sector-10 Greater Noida, Sector-10, Dadri, Gautam Budh Nagar
TehsilDadri
Applicant typeCompany
Applicant addressGh-04A Sector 10 Greater Noida
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Building permit sanctioned

    PLG/BP/SM-19-SEP-2023;19247

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered2 Mar 2024
Original completion31 Jan 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹99,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors600 · 5 · 34 (units from plan)
Homes · commercial units572 · 28 (shops and offices filed in the same plan)
  • 3 BHK340 57%
  • 4 BHK228 38%
  • SHOP28 5%
  • OTHER4 1%
ConfigurationUnitsCarpet area
3 BHK34075-103
4 BHK228116-139
OTHER44-5
SHOP2819-23
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · OTHER, 4 BHK34114116-139
B · 3 BHK, OTHER3417075-103
C · 3 BHK, OTHER3417075-103
COMMERCIAL · OTHER, SHOP5324-23
D · 4 BHK, OTHER34114116-139
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Kailash Aggarwal
License CA/86/10069
J-41 Sector -11, Noida
Engineer
Ramakrishna D Choudhary
B-1102, Vashudha , Dosti Vihar PokhranRoad-1,Vartak Nagar , Thane(W) 400606
Contractor
Vishal Enterprises
219B, Mian Sihani Road, Ghaziabad 201001
Sr.Development work declared to RERA
1Demarcation of Plots
Demarcation map attached with Lease deed of Plot
2Boundary Wall
Boundary wall is proposed to be constructed as per the architectural drawings
3Road Work
RCC Trimix road with kerb stone on sides and stone paving in front of towers
4Footpaths
All footpath will be constructed as per the architectural site plan and landscape plan
5Water Supply Including Drinking Water Facilities
Greater Noida Industrial development Authority pipe line water will be used for Drinking and other basic needs regarding water
6Sewer System
RCC hume pipe with mainhole chambers and collection chamber and connection to the Development authority sewer system
7Drain
Drain are provided in the entire open area that carries water to 4 rain water harvesting chambers provided at each corner at site
8Parks
Parks in the form of open/ green area is provided at the podium level which is 40 percent of plot area i.e 4015 sqmt
9Tree Planting
As per MoEFCC Norms no. of trees required 1 hectare /50 trees 1.8819 multiply 50 = 94 trees
10Design For Electric Supply Including Street Lighting
Electricity an d street lighting will be developed as per the design provided by the architect and appointed consultant considering site requirement
11Community Buildings
Floor area =585.510 sqmt and 2nd floor area 307.292sqmt respectively , which makes the total community area as 892.8 sqmt
12Treatment and Disposal System of Sewage and Sullage water
Proposed STP capacity is 240 KLD will be installed for treatment of wastewater. After the treatment of 211 KLD sewage ,169 KLD treated water will be generated which will be entirely used of DG cooling ,horticulture and flushing
13Solid Waste Management And Disposal System
Following arrangements will be made at the site in accordance to the solid Waste management rules 2016 a. 60 Percent bio degradable waste b. 30 percent non bio degradable c. 10 percent inert waste The soil waste will be segregated at source and collected to trained employed personals
14Water Conservation System
Considering Size of recharge pit size will be 8 mtr long 6 mtr wide and 2 mtr deep so the volume of the single pit will be 96 cum Total recharge will be required = 570.58/ 96=5.94 Nos
15Energy Management System Including Use of Renewable Energy
Power requirement of project is 1329 kw 2 transformer of capacity 1575 kva will be provided Source of power will be Noida power company limited 2 Nos. of DG set of total capacity 320 Kva will be provided of power back up
16Fire Protection And Fire Safety System
The fire protection system for the building is to be design as per the provisions of NBC 2016 and all the directions of local fire service authority
17Social Infrastructure And Other Public Amenities Including Public Health Services
social infrastructural space is provided at stilt and first floor level with areas 297 sqm and 543 sqm respectievly ,which makes the total community area is as 840 sqm
18Emergency Evacuation Services
Fire staircase is provided in each of the four towers for emergency evacuation as per the NBC guidelines and 9/ 7.5 m wide wide fire tender path has been provided for the tender movement in case of emergency
19Other Miscellaneous Work
All miscellaneous work will be completed before completion
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1anil kumar singhUPRERAAGT18130
2Rajesh BhandariUPRERAAGT23434
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 5 Feb 2029.

Sanctioned by Greater Noida Authority · 18,819 sqm of land · an approved plan of 5 blocks and 600 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG/BP/SM-19-SEP-2023;192476 Feb 20245 Feb 20294 Feb 203231 Jan 2029
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Gh-04A18819Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 33646
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New31 Jan 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New3 Feb 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New3 Feb 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New31 Jan 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New31 Jan 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New31 Jan 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New31 Jan 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New1 Feb 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Feb 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New31 Jan 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New31 Jan 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New31 Jan 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New31 Jan 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New16 Feb 2024 ↗

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2023-Q4 to 2026-Q2.

QuarterConstructionCertificates
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q222.37%CA ↗ · Arch ↗ · Eng ↗
2025-Q327.36%CA ↗ · Arch ↗ · Eng ↗
2025-Q431.66%CA ↗ · Arch ↗ · Eng ↗
2026-Q135.82%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameIrish Buildcon Private Limited
RolePromoter · current
RERA IDUPRERAPRM266262
PANAAHCI0059H
CIN / TANMRTI03778F
Name of chairmanMr. Gaurav Garg
Registered addressGh-04A Sector 10 Greater Noida
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
IRISH BUILDCON PRIVATE LIMITED IRISH PLATINUM COLLECTION ACCOUNTBankICICI BANKBranchTECHZONE-4 GREATER NOIDABranch addressSHOP NO.9A,9B PLOT NO.GH-05B TECHZONE 4 GREATER NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0004146Branch emailchaudhary.ankush@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
IRISH BUILDCON PRIVATE LIMITED IRISH PLATINUM SEPATARE ACCOUNTBankICICI BANKBranchTECHZONE-4 GREATER NOIDABranch addressSHOP NO. 9A , 9B PLOT NO. GH-05B TECHZONE-4 GREATER NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0004146
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
IRISH BUILDCON PRIVATE LIMITED IRISH PLATINUM TRANSACTION ACCOUNTBankICICI BANKBranchTECHZONE-4 GREATER NOIDABranch addressSHOP NO-9A,9B PLOT NO-GH05B TECHZONE -4 GREATER NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0004146
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Irish Platinum

Is Irish Platinum RERA registered?

Yes. Irish Platinum is registered with UPRERA under registration number UPRERAPRJ503189, registered on 2 Mar 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Irish Platinum?

The completion date filed with UPRERA is 31 Jan 2029. No completion certificate is on record yet.

Who is the builder of Irish Platinum?

Irish Buildcon Private Limited is the promoter entity that filed Irish Platinum with UPRERA (promoter RERA ID UPRERAPRM266262). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Irish Platinum have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Irish Platinum located?

Irish Platinum is registered in Sector-10, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Irish Platinum?

The unit plan filed with UPRERA lists 3 BHK, 4 BHK, OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Irish Platinum?

The approved unit plan filed with UPRERA runs from 4 to 139 m² of carpet area (about 48 to 1,493 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Irish Platinum?

The approved unit plan describes 5 blocks and 600 units of which 572 are homes and 28 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Irish Platinum?

About 129 units per acre: 600 planned units across 4.65 acres (18,819 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗