Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ757529
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Oct 2019
Project duration69 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressF-28, F/F Preet Vihar, Near Sagar Ratna Restaurant Delhi, East Delhi, 110092 IN
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    NOIDA/MVN/2019/III-303/1131

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion certificate filed

  5. Completion certificate filed

  6. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  7. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered16 Sept 2019
Original completion31 Dec 2024
Revised completion30 Jun 2025
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary23 Apr 2024
Registration fee₹1,08,500
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors558 · 6 · 28 (units from plan)
Homes · commercial units546 · 12 (shops and offices filed in the same plan)
  • 3 BHK428 77%
  • 4 BHK102 18%
  • 2 BHK16 3%
  • SHOP12 2%
ConfigurationUnitsCarpet area
4 BHK102142
2 BHK1682-111
3 BHK42894-125
SHOP123-84
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A1 · 4 BHK, 3 BHK27106122-142
B1 · 2 BHK, 3 BHK28110104-117
B2 · 2 BHK, 3 BHK28110104-117
C1 · 3 BHK, 2 BHK2811082-94
C2 · 3 BHK, 2 BHK2811082-94
Commercial · SHOP2123-84
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 253.79 m² for a SHOP, far outside the rest of that type, so the ranges above leave it out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. Vishal Sharma
License CA/98/23261
C/o CONFLUENCE CONSULTANCY SERVICE , B-421 NEW FRIENDS COLONY , NEW DELHI
Engineer
Dr. Vinod Jain
M/S VINTECH CONSULTANTS ,C35, PAMPOSH ENCLAVE , GK-1, NEW DELHI
Contractor
Countyestate Developers LLP
F-28, first Floor, Preet Vihar, New Delhi-110092
Sr.Development work declared to RERA
1Boundary Wall
Yes, Masonary Pucca and Railing Boundary wall of minimum 1500mm height.
2Road Work
Yes, RCC Trimix road with Kerb stone on sides and Trimix or stone paving in front of tower.
3Footpaths
Yes, Cement Concrete, stone and Grass pavers
4Water Supply Including Drinking Water Facilities
Yes, water supply from Authority to be collected in Under Ground water reservoires, Terrace Tanks equipped with hydro Pneumatic Pumps with G.I. Ring and risers.
5Sewer System
RCC Hume pipes with Manhole, Chambers and collection Chamber connected with Authority Sewer or to be bailed out to Authority Drain/Sewer after treatment.
6Drain
Yes, Saucer Drain and RCC Hume Pipe system.
7Parks
Yes, Beautiful Landscape with Civil Work in Masonary and Stone, Horticulture work and various types of Plantation.
8Tree Planting
Yes, Tree Planting all along road in Project. Total number of trees to be planted around 160.
9Design For Electric Supply Including Street Lighting
Yes, Electric Supply from NPCL Transformer 2 Nos of 1250KVA and 1000 KVA , D.G. Set 1 No of 1010 KVA
10Community Buildings
Yes, with Gym , Indoor Games facilities and S.Pool
11Treatment and Disposal System of Sewage and Sullage water
STP and Authority Sewerage System
12Solid Waste Management And Disposal System
Yes, Organic Waste Converter , Collection Bins and Segregation Table.
13Water Conservation System
Yes, Rain Water Harvesting , Drip Irrigation and Irrigation with Sprinklers and Bublers
14Energy Management System Including Use of Renewable Energy
Light in common areas or Towers external areas to be operated from Solar Energy , Lights LED
15Fire Protection And Fire Safety System
7 Nos Fire Pump 2 No Electric Motor Driven 2850 LPM Head 160m 1 No Diesel Driven 2850 LPM Head 160m 1 No Electric Motor Stand by 2850 LPM Head 160m 2 No Jockey Pump 180 LPM 1 No Compartation Pump Electric 1620 LPM Head 55m
16Social Infrastructure And Other Public Amenities Including Public Health Services
Proper Water Supply and sanitary Facilites on Ground Floor of every Tower
17Emergency Evacuation Services
Yes, refuge area provided on 19th Floors in addition to main and fire staircase in all towers
18Other Miscellaneous Work
Guard Room , entrance and exit Gates.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

3 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1Agarwal HomezUPRERAAGT12798
2INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
3URBAN AVENUES LLPUPRERAAGT10834
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 14 Jul 2024.

Sanctioned by Noida Authority · 20,639 sqm of land · an approved plan of 6 blocks and 558 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
NOIDA/MVN/2019/III-303/113115 Jul 201914 Jul 202414 Jul 202931 Dec 2024
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 Jun 2025.

#Granted fromExtended uptoNote
131 Dec 202430 Jun 2025Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-1520639Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 1/10103/237-304/212
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · NOIDA/GH-15(ECO CITY-SEC-75)/2018/6057
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · Reply to Objection Letter
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New15 Aug 2020 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New17 Aug 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New17 Aug 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New3 Sept 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New14 Aug 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New14 Aug 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New14 Aug 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New14 Aug 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New17 Aug 2019 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New29 Feb 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New29 Feb 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New29 Feb 2020 ↗

Quarterly progress reports

21 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

21 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal namePerfect Megastructure Pvt Ltd
RolePromoter · current
RERA IDUPRERAPRM93681
PANAAFCF6913M
CIN / TANU45200DL2010PTC208279
Name of chairmanMr. Amit Modi
Registered addressF-28, F/F Preet Vihar, Near Sagar Ratna Restaurant Delhi, East Delhi, 110092 IN
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
PERFECT MEGASTRUCTURE PRIVATE LIMITED-RERA ACCOUNTBankKotak Mahindra Bank LimitedBranchSector-63, NOIDAA/C no.IFSCKKBK0000180
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about IVY County

Is IVY County RERA registered?

Yes. IVY County is registered with UPRERA under registration number UPRERAPRJ757529, registered on 16 Sept 2019. Estanzo reproduces that filing; it does not verify the work behind it.

Has IVY County been completed?

UPRERA still lists IVY County as Registered, so it is not shown as completed here. A completion certificate dated 23 Apr 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of IVY County?

Perfect Megastructure Pvt Ltd is the promoter entity that filed IVY County with UPRERA (promoter RERA ID UPRERAPRM93681). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted IVY County more time to complete?

UPRERA's record carries 1 completion extension for IVY County, the latest running to 30 Jun 2025. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does IVY County have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is IVY County located?

IVY County is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in IVY County?

The unit plan filed with UPRERA lists 4 BHK, 2 BHK, 3 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in IVY County?

The approved unit plan filed with UPRERA runs from 3 to 142 m² of carpet area (about 31 to 1,534 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in IVY County?

The approved unit plan describes 6 blocks and 558 units of which 546 are homes and 12 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is IVY County?

About 109 units per acre: 558 planned units across 5.10 acres (20,639 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗