Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ14784
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start1 Jan 2018
Project duration87 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant address913,9TH FLOOR, ARUNACHAL BUILDING, BARAKHAMBA ROAD, NEW DELHI-110001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated

    197/GH/ZONE-6/17-18

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. valid to

    Permit revalidated

    288/PRAVANAN/GDA/2017-20

  6. Building permit sanctioned

    288/PRAVANAN/GDA/2017-20

  7. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  8. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  9. to

    Extension granted

  10. to

    Extension granted

  11. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  12. valid to

    Permit revalidated

    288/PRAVANAN/GDA/2017-20

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered6 Jan 2018
Original completion31 Dec 2022
Revised completion31 Mar 2025
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹23,500
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors203 · 2 · 15 (units from plan)
  • 1 BHK118 58%
  • 3 BHK71 35%
  • 2 BHK14 7%
ConfigurationUnitsCarpet area
1 BHK11827-44
3 BHK7177-244
2 BHK1459
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
O-5 · 1 BHK1211827-44
O-6 · 3 BHK, 2 BHK148559-244
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
AE STUDIO
License CA/97/21634
B4/225,Safdurjung Enclave, New Delhi-110029
Engineer
ACECON Engineers
A-269, L.G.F, Shivalik, Malviya Nagar,New Delhi-110017
Contractor
NA
NA
Sr.Development work declared to RERA
1Demarcation of Plots
1490.66 sqm Building periphery area part of the 42905 sq mtr integrated group housing complex
2Boundary Wall
1500mm high
3Road Work
Providing, laying & Fixing of Interlocking tiles/pavers of Cement Concrete 1:1.5:3 Cement Course sand and 20MM nominal size stone grit having 80MM thickness over crushed aggregates premixed with bituminous binder over bituminous Premix carpet of 20mm
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
water tank on terrace (5KL fire and 30KL domestic)
6Sewer System
connected to public sewer
7Drain
connected to public sewer
8Parks
In compliance with building bye laws & as per sanctioned drawing enclosed
9Tree Planting
50 trees per hectare
10Design For Electric Supply Including Street Lighting
As per the SLD
11Community Buildings
Completed & functional for the entire group housing complex
12Treatment and Disposal System of Sewage and Sullage water
connected to public sewer
13Solid Waste Management And Disposal System
connected to public sewer
14Water Conservation System
Rain water harvesting
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
over head fire tank of 25KL
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
basement fully sprinkler, one fire stair
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

4 permits

An approval and the date it runs to - not proof the work matching it was done.

4 sanctioning permits are on record with UPRERA, the latest valid to 4 Jun 2025. 3 of them carry a revalidation, the latest valid to 5 Aug 2025.

Sanctioned by Ghaziabad Development Authority · 3,608 sqm of land · an approved plan of 2 blocks and 203 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
197/GH/ZONE-6/17-1826 Dec 201725 Dec 202231 Dec 202231 Dec 2022—
197/GH/ZONE-6/17-1826 Dec 201726 Dec 202226 Dec 202430 Jun 202326 Dec 2017
197/GH/ZONE-6/17-1826 Dec 201726 Dec 20225 Aug 202529 Jun 20245 Jun 2025
valid to 5 Aug 2025
as 288/PRAVANAN/GDA/2017-20
288/PRAVANAN/GDA/2017-205 Jun 20214 Jun 20259 Jun 202529 Jun 20245 Jun 2021
valid to 7 Jun 2025
Plans and approvals filed with RERA
DocumentFile
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 31 Mar 2025.

#Granted fromExtended uptoNote
131 Dec 202230 Jun 2023Six months extension in view of force majeure caused by covid-19 pandemic
230 Jun 202329 Jun 2024—
329 Jun 202431 Mar 2025—

Land & documents

6 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Part of Khasra #549,556 & 527/43608—
527/46500Khasra
549 to 559 (TOTAL 10 KHASRA)1216Khasra
TOTAL AREA OF PROJECT3608Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 640015
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 640018
The registered deed by which the promoter bought the land.
PDF ↗
Lease deed · AGREEMENT JAN 2017
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · SUPPLEMENTARY AGREEMENT 06 JAN 2017
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New19 Jul 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old6 Jan 2018 ↗

Quarterly progress reports

17 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

17 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2024-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameOXIRICH CONSTRUCTION PVT LTD
RolePromoter · current
RERA IDUPRERAPRM32522
PANAACCK7900N
CIN / TANU70102DL2006PTC148042
Name of chairmanVIKAS DUA
Registered address913,9TH FLOOR, ARUNACHAL BUILDING, BARAKHAMBA ROAD, NEW DELHI-110001
RERA contact
Registered since2018
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
OXIRICH CONSTRUCTION PVT LTDBankDCB BANKBranchNEW DELHI(046)A/C no.IFSCDCBL0000046
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about OXIRICH SQUARE ONE

Is OXIRICH SQUARE ONE RERA registered?

Yes. OXIRICH SQUARE ONE is registered with UPRERA under registration number UPRERAPRJ14784, registered on 6 Jan 2018. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for OXIRICH SQUARE ONE?

The completion date filed with UPRERA is 31 Mar 2025. No completion certificate is on record yet.

Who is the builder of OXIRICH SQUARE ONE?

OXIRICH CONSTRUCTION PVT LTD is the promoter entity that filed OXIRICH SQUARE ONE with UPRERA (promoter RERA ID UPRERAPRM32522). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted OXIRICH SQUARE ONE more time to complete?

UPRERA's record carries 3 completion extensions for OXIRICH SQUARE ONE, the latest running to 31 Mar 2025. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does OXIRICH SQUARE ONE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is OXIRICH SQUARE ONE located?

OXIRICH SQUARE ONE is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in OXIRICH SQUARE ONE?

The unit plan filed with UPRERA lists 1 BHK, 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in OXIRICH SQUARE ONE?

The approved unit plan filed with UPRERA runs from 27 to 244 m² of carpet area (about 292 to 2,625 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in OXIRICH SQUARE ONE?

The approved unit plan describes 2 blocks and 203 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is OXIRICH SQUARE ONE?

About 228 units per acre: 203 planned units across 0.89 acres (3,608 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗