SUPERTECH ORB-R (PHASE-III) is a RERA-registered real-estate project in Gautam Budh Nagar (RERA ID UPRERAPRJ5551). RERA status: NCLT (since 25 Mar 2022). Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: NCLT.| RERA ID | UPRERAPRJ5551 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | NCLT |
| Proposed start | 1 Aug 2012 |
| Original start | 1 Aug 2012 |
| Project duration | 113 |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| RERA registered | 11 Aug 2017 |
| Promised completion | 30 Jun 2021 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹55,500 |
| NCLT order date | 25 Mar 2022 |
| Configuration | Units | Carpet area |
|---|---|---|
| 4 BHK | 46 | 227–227 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 2014/III-227/757 | 30 Sept 2014 | 30 Sept 2019 | 30 Jun 2021 |
| Khasra | Area | Type |
|---|---|---|
| GH-01 | SECTOR74 | — |
| GH 01 A | 209271.47 | Plot |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 3988 | 7 Oct 2010 | — | — |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | Arch · Eng | view ↗ |
Other projects registered in Gautam Budh Nagar.
Yes. SUPERTECH ORB-R (PHASE-III) is registered with UPRERA under registration number UPRERAPRJ5551, registered on 11 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
SUPERTECH ORB-R (PHASE-III) is 61 months past the completion date filed with UPRERA (30 Jun 2021), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
SUPERTECH ORB-R (PHASE-III) is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗