Timeline Bar
Timeline
Registration & Cost Details
Inventory
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| SHOP | 19 | 29.7–482.57 |
| OTHER | 990 | 18.255–119.815 |
Promoters & Contact
Contact Details
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| PLG/(BP)3385/IT/4241 | 27 Jun 2019 | 26 Jun 2024 | 30 Jun 2023 | 26 Jun 2027 |
| PLG/(BP)/3385/IT/4241 Revalidated: PLG/(BP)/3385/IT/4241 (27 Jun 2019) | 27 Jun 2019 | 26 Jun 2024 Revalidated upto: 26 Jun 2025 | 29 Dec 2023 | 26 Jul 2028 |
| PLG/(BP)/3385/IT/4241 Revalidated: PLG/(BP)/3385/IT/4241 (27 Jun 2019) | 27 Jun 2019 | 26 Jun 2024 Revalidated upto: 26 Jun 2029 | 28 Dec 2024 | 25 Jun 2032 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 7 | 91308 | Plot |
Approved Unit Plan
Individual floor/unit rows are not listed here.
Frequently Asked Questions
What is the RERA registration number of GRANDTHUM PHASE IV?
The RERA registration number of GRANDTHUM PHASE IV is UPRERAPRJ103135, as recorded on the UP-RERA portal.
What is the RERA status of GRANDTHUM PHASE IV?
As reported by UP-RERA, the status of GRANDTHUM PHASE IV is "Registered".
Where is GRANDTHUM PHASE IV located?
As reported to UP-RERA, GRANDTHUM PHASE IV is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will GRANDTHUM PHASE IV be completed?
The latest completion date reported to UP-RERA for GRANDTHUM PHASE IV is 28 Dec 2024.
Is GRANDTHUM PHASE IV delayed?
Measured against the latest completion date reported to UP-RERA, GRANDTHUM PHASE IV is 19 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026