Kailasha Awadh

UPRERARegistered

Kailasha Awadh is a RERA-registered commercial project by Marigold Buildcon in Lucknow (RERA ID UPRERAPRJ850664). Registered with a completion deadline of 11 Sept 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
16.33%Q3'25
24.33%Q4'25
32.57%Q1'26
40.27%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ850664
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start12 Sept 2023
Project duration60 months
AddressSarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typePartnership Firm
Applicant address47/16, Clay Square, Kabir Marg, Lucknow, Uttar Pradesh- 226001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    Commercial Building/08927/LDA/BP/22-23/3826/29072023

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered28 Nov 2023
Original completion11 Sept 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹66,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors247 · 1 · 5 (units from plan)
Homes · commercial units4 · 243 (shops and offices filed in the same plan)
  • SHOP243 98%
  • OTHER4 2%
ConfigurationUnitsCarpet area
SHOP2439-57
OTHER4156-311
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower-1 · SHOP, OTHER52479-57
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 1,097.38 m² for a OTHER, far outside the rest of that type, so the ranges above leave it out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Deepankar Sharma
License CA/2014/64728
4/119 , Virat Khand, Lucknow
Engineer
Chhatrapal Singh
Nauranga Rath, Hamirpur, Uttar Pradesh-210428
Contractor
Baba Construction Pvt. Ltd.
B-3, Baba Complex, Sector-23, Sanjay Nagar, Ghaziabad, Uttar Pradesh
Sr.Development work declared to RERA
1Demarcation of Plots
We have one plot of size 5592.52 sq. mtr.having 1 main entrance gate from the 24 m wide front road.
2Boundary Wall
2Mtr High Precast Rcc Boundary wall at the center face of boundary wall there would be a Logo of the project which give a beautiful iconic design to boundary wall.
3Road Work
From the main entrance gate we will make 80 mm thick interlocking brick /RCC road through out the project. Whose wideness starts from 6 - 10 mtr.
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
We will provide Two nos. of pump for the requirement of blocks through underground pipelines.
6Sewer System
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.when come into force.
7Drain
Storm water shall be Provided. Storm water from Roads and other landscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
8Parks
NA
9Tree Planting
We will provide many type of trees all along the boundary wall & green area
10Design For Electric Supply Including Street Lighting
We will design & implement the system as per local electricity Board and will consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and DG back for common service like External lighting, Fountain, STP, Pump room etc.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.,when come into force.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
We will suggest to individual to use low flow fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
16Fire Protection And Fire Safety System
Fire protection will be provides as per By-lays and Guidelines of Fire Dept.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
We will have staircases which will be provided with emergency exit doors and emergency exit gates
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 11 Sept 2028. 1 of them carries a revalidation, valid to 11 Sept 2028.

Sanctioned by Lucknow Development Authority · 5,592 sqm of land · an approved plan of 1 block and 247 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
Commercial Building/08927/LDA/BP/22-23/3826/2907202312 Sept 202311 Sept 202811 Sept 202811 Sept 2028—
Commercial Building/08927/LDA/BP/22-23/3826/2907202312 Sept 202311 Sept 202811 Sept 202811 Sept 202812 Sept 2023
valid to 11 Sept 2028
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

21 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
26.45.38.96 N, 80.55.23.36 E0Plot
26.45.41.13 N, 80.55.23.33 E0Plot
26.45.38.00 N, 80.55.21.54 E0Plot
26.45.39.97 N, 80.55.19.72 E5593Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 17290
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 37324
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · Affidavit Cum Undertaking For Registration Of Project Under RERA
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New26 Sept 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New22 Sept 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New22 Sept 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New22 Sept 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New23 Sept 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New23 Sept 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New23 Sept 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New23 Sept 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New21 Sept 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New7 Oct 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New7 Oct 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New7 Oct 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New21 Sept 2023 ↗

Quarterly progress reports

12 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

12 quarterly progress reports are on file with UPRERA, covering 2023-Q2 to 2026-Q1.

QuarterConstructionCertificates
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q216.33%CA ↗ · Arch ↗ · Eng ↗
2025-Q324.33%CA ↗ · Arch ↗ · Eng ↗
2025-Q432.57%CA ↗ · Arch ↗ · Eng ↗
2026-Q140.27%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMarigold Buildcon
RolePromoter · current
RERA IDUPRERAPRM257672
PANABUFM2845E
CIN / TANLKNM13696E
Registered address47/16, Clay Square, Kabir Marg, Lucknow, Uttar Pradesh- 226001
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
MB COLLECTION ACCOUNT FOR KAILASHA AWADHBankCANARA BANKBranchSECTOR-8, INDIRA NAGAR, LUCKNOWBranch addressLITTLE ANGELS HIGH SCHOOL, SECTOR- 8, INDIRA NAGAR, LUCKNOW, UTTAR PRADESH- 226016Branch districtLucknow, Uttar PradeshA/C no.IFSCCNRB0018487
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
MB SEPARATE ACCOUNT FOR KAILASHA AWADHBankCANARA BANKBranchSECTOR-8, INDIRA NAGAR, LUCKNOWBranch addressLITTLE ANGELS HIGH SCHOOL, SECTOR- 8, INDIRA NAGAR, LUCKNOW, UTTAR PRADESH- 226016Branch districtLucknow, Uttar PradeshA/C no.IFSCCNRB0018487
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
MB TRANSACTION ACCOUNT FOR KAILASHA AWADHBankCANARA BANKBranchSECTOR-8, INDIRA NAGAR, LUCKNOWBranch addressLITTLE ANGELS HIGH SCHOOL, SECTOR- 8, INDIRA NAGAR, LUCKNOW, UTTAR PRADESH- 226016Branch districtLucknow, Uttar PradeshA/C no.IFSCCNRB0018487
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Kailasha Awadh

Is Kailasha Awadh RERA registered?

Yes. Kailasha Awadh is registered with UPRERA under registration number UPRERAPRJ850664, registered on 28 Nov 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Kailasha Awadh?

The completion date filed with UPRERA is 11 Sept 2028. No completion certificate is on record yet.

Who is the builder of Kailasha Awadh?

Marigold Buildcon is the promoter entity that filed Kailasha Awadh with UPRERA (promoter RERA ID UPRERAPRM257672). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Kailasha Awadh have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Kailasha Awadh located?

Kailasha Awadh is registered in Lucknow, as filed with UPRERA.

What configurations are available in Kailasha Awadh?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Kailasha Awadh?

The approved unit plan filed with UPRERA runs from 9 to 311 m² of carpet area (about 95 to 3,349 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Kailasha Awadh?

The approved unit plan describes 1 block and 247 units of which 4 are homes and 243 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Kailasha Awadh?

About 179 units per acre: 247 planned units across 1.38 acres (5,592 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗