KALINDI TOWER KALINDI KUNJ

UPRERARegistered

KALINDI TOWER KALINDI KUNJ is a RERA-registered residential project by BULANDSHAHR DEVELOPMENT AUTHORITY in Kalindi Kunj Scheme Khurja, Bulandshahr (RERA ID UPRERAPRJ368832). Registered with a completion deadline of 11 Aug 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
53%Q1'25
53%Q2'25
53%Q3'25
53%Q4'25
53%Q1'26
46.3%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ368832
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryBulandsahar Development Authority
Proposed start12 Feb 2025
Project duration30 months
AddressPlot No-4, Kalindi Kunj Scheme Khurja, Kalindi Kunj Scheme Khurja, Khurja, Bulandshahr
TehsilKhurja
Applicant typeCompetent authority
Applicant addressM.G. ROAD, YAMUNA PURAM, BULANDSHAHR
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Building permit sanctioned

    23/23

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered28 Oct 2025
Original completion11 Aug 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹20,500
Sanctioning authorityBulandsahar Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors70 · 1 · 8 (units from plan)
  • 3 BHK42 60%
  • 2 BHK28 40%
ConfigurationUnitsCarpet area
3 BHK4299-104
2 BHK2880-85
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · OTHER, 3 BHK, 2 BHK87080-104
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
AR SAMEEP GARG
License CA/2000/26238
H.M COMPLEX, FIRST FLOOR, NEAR AXIS BANK, RAMGHAT ROAD, ALIGARH
Engineer
DESIGN DUTY STRUCTURE CONSULTANT
1/38 UPPER GROUND FLOOR DLF DISHAD EXTENTION BHAUPURA GHAZIABAD
Contractor
SUNIL GARG AND COMPANY
150, EAST MODEL TOWN GHAZIABAD
Sr.Development work declared to RERA
1Demarcation of Plots
ON SITE DEMARCATION OF PLOT BOUNDARIES AND BLOCK CONSTRUCTION BOUNDARIES ARE MARKED AS PER DRAWING PROVIDED BY THE CONSULTANT.
2Boundary Wall
STRUCTURAL BOUNDARY WALL CONSTRUCTING THE COLUMN AND BEAM ARRANGEMENTS, FOR AESTHETICS USING THE ADDITIONAL LIGHTING THE GRILL ELEMENTS WITH DECORATIVE FLOOR FINISH
3Road Work
IN THE SETBACKS USING CEMENT CONCRETE ROAD.
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
UNDERGROUND WATER SUPPLY TANK USING FOR WATER SUPPLY IN THE BUILDING ALSO THIS WATER SUPPLY LINE USE FOR DRINKING WATER FOR EVERY HOUSE HOLD AN D COMMON DRINKING WATER FACILITY.
6Sewer System
SEWERAGE SYSTEM IS DIRECT CONNECTED WITH COMMON SEWER LINE , EVERY HOUSE HOLD SEWER SYSTEM IS CONNECTED WITH MULTI PIPING SEWER SYSTEM.
7Drain
DRAIN PIPELINE IS CONNECTED WITH SCHEME DRAIN SYSTEM, EVERY HOUSEHOLD DRAIN HAS MUTI TRACK SYSTEM FOR REDUCE THE CHOKING.
8Parks
NA
9Tree Planting
AS PER GREEN AREA MARKED IN LAYOUT PLANTATION TOBE DONE.
10Design For Electric Supply Including Street Lighting
AS PER ELECTRICAL LAYOUT, ELECTRICAL POINTS IN HOUSING UNITS AND COMMON AREA IS PROVIDED, STREET LIGHTS ARE PLACED ON BOUNDARY WALLS AS PER CONSULTANT DRAWING.
11Community Buildings
NOT APPLICABLE
12Treatment and Disposal System of Sewage and Sullage water
NOT APPLICABLE, DIRECTLY CONNECTED WITH CENTRALIZED SEWER SYSTEM.
13Solid Waste Management And Disposal System
GARBAGE DUCT IS PROVIDED ON EACH FLOOR, WHICH IS COLLECTING ALL THE GARBAGE IN BASEMENT AND TRANSPORTED BY MUNICIPAL GARBAGE CAR.
14Water Conservation System
RAIN WATER HARVESTING SYSTEM IS PROVIDING.
15Energy Management System Including Use of Renewable Energy
NOT APPLICABLE
16Fire Protection And Fire Safety System
FIRE FIGHTING SYSTEM IS INSTALLING AS PER FIRE FIGHTING NORMS, PROVISIONAL NOC ALSO OBTAINED FROM FIRE DEPARTMENT.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NOT APPLICABLE
18Emergency Evacuation Services
FIRE STARE IS PROVIDED AS PER FIRE SAFETY NORMS
19Other Miscellaneous Work
LEVELS OF STILT AND SETBACKS ARE MAINTAINED FOR EASY VEHICULAR CIRCULATION.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 6 May 2029.

Sanctioned by Bulandsahar Development Authority · 3,249 sqm of land · an approved plan of 1 block and 70 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
23/237 May 20256 May 20296 May 203011 Aug 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
884,8853249Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1425-1430 (01 JULY ,2017 - 30 jUNE, 2023)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New21 Jun 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New8 Jul 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New8 Jul 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New8 Jul 2025 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New8 Jul 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New8 Jul 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New21 Jun 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New8 Jul 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New8 Jul 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New1 Jul 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New24 Oct 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New3 Jul 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New8 Aug 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New28 Jul 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New8 Jul 2025 ↗

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2024-Q4 to 2026-Q1.

QuarterConstructionCertificates
2024-Q453%CA ↗ · Arch ↗ · Eng ↗
2025-Q153%CA ↗ · Arch ↗ · Eng ↗
2025-Q253%CA ↗ · Arch ↗ · Eng ↗
2025-Q353%CA ↗ · Arch ↗ · Eng ↗
2025-Q453%CA ↗ · Arch ↗ · Eng ↗
2026-Q146.3%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameBULANDSHAHR DEVELOPMENT AUTHORITY
RolePromoter · current
RERA IDUPRERAPRM13457
PANAAALB0116G
CIN / TANMETB01501D
Registered addressM.G. ROAD, YAMUNA PURAM, BULANDSHAHR
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Bulandshahr

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
VC BKDA COLLECTION ACCOUNT FOR KALINDI TOWER KALINDI KUNJBankICICI BANKBranchYAMUNAPURAMBranch addressFORTUNE COURT, CP 11, YAMUNAPURAM COMMERCIAL BULANDSHAHRBranch districtBulandshahr, Uttar PradeshA/C no.IFSCICIC0005815Branch emailRAJAT.GOYAL2@ICICIBANK.COM
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
VC BKDA SEPARATE ACCOUNT FOR KALINDI TOWER KALINDI KUNJBankICICI BANKBranchYAMUNAPURAMBranch addressFORTUNE COURT, CP11, YAMUNAPURAM COMMERCIAL BULANDSHAHRBranch districtBulandshahr, Uttar PradeshA/C no.IFSCICIC0005815
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
VC BKDA TRANSACTION ACCOUNT FOR KANLINDI TOWER KALINDI KUNJBankICICI BANKBranchYAMUNAPURAMBranch addressFORTUNE COURT, CP11, YAMUNAPURAM COMMERCIAL BULANDSHAHRBranch districtBulandshahr, Uttar PradeshA/C no.IFSCICIC0005815
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about KALINDI TOWER KALINDI KUNJ

Is KALINDI TOWER KALINDI KUNJ RERA registered?

Yes. KALINDI TOWER KALINDI KUNJ is registered with UPRERA under registration number UPRERAPRJ368832, registered on 28 Oct 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for KALINDI TOWER KALINDI KUNJ?

The completion date filed with UPRERA is 11 Aug 2027. No completion certificate is on record yet.

Who is the builder of KALINDI TOWER KALINDI KUNJ?

BULANDSHAHR DEVELOPMENT AUTHORITY is the promoter entity that filed KALINDI TOWER KALINDI KUNJ with UPRERA (promoter RERA ID UPRERAPRM13457). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does KALINDI TOWER KALINDI KUNJ have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is KALINDI TOWER KALINDI KUNJ located?

KALINDI TOWER KALINDI KUNJ is registered in Kalindi Kunj Scheme Khurja, Bulandshahr, as filed with UPRERA.

What configurations are available in KALINDI TOWER KALINDI KUNJ?

The unit plan filed with UPRERA lists OTHER, 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in KALINDI TOWER KALINDI KUNJ?

The approved unit plan filed with UPRERA runs from 80 to 104 m² of carpet area (about 856 to 1,122 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in KALINDI TOWER KALINDI KUNJ?

The approved unit plan describes 1 block and 70 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is KALINDI TOWER KALINDI KUNJ?

About 87 units per acre: 70 planned units across 0.80 acres (3,249 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗