Kings Crest is a RERA-registered residential project by Elite Infra Developers and Interiors Private Limited in Itaua Beniram, Bareilly (RERA ID UPRERAPRJ718743). Registered with a completion deadline of 31 Mar 2029.
RERA status as reported: Registered.Construction progress
Construction stayed at 10% across 3 consecutive filed quarters (Oct–Dec 2025 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ718743 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Bareily Development Authority |
| Proposed start | 1 Oct 2025 |
| Project duration | 42 months |
| Address | Plot No. 116 (P), Village Itaua Beniram, Teh. & distt. Bareilly UP, Itaua Beniram, Bareilly, Bareilly |
| Tehsil | Bareilly |
| Applicant type | Company |
| Applicant address | 255 JANAKPURI, BAREILLY up 243122 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
PRD/PH/02887/BDA/LD/24-25/0346/11022025
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 17 Oct 2025 |
| Original completion | 31 Mar 2029 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹47,500 |
| Sanctioning authority | Bareily Development Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots No. of residential plots under 100 sqmt area is 21 , between 100-150 sqmt area is 20, No. of commercial plots is 5. |
| 2 | Boundary Wall 0.23 m thick Boundary wall upto 3.00m high with 1;6 Ratio and both side plaster with 1;5 ratio will be constructed. |
| 3 | Road Work stone ballast with compaction soiling coat 40 mm to 63 mm, 6mm to 10mm thick coat of stone grit and sand including compaction and laying concrete slab 10 cm thick with 1;2;4 ratio. |
| 4 | Footpaths footpaths will be provided in park concrete paver block will be used for pavement. Ballard lights will be provided along the footpath in park. |
| 5 | Water Supply Including Drinking Water Facilities under ground water tank of capacity 30 KLD will be provided. Pump house will be provided for efficient supply of water to overhead water tank situated on terrace top of each residence. |
| 6 | Sewer System under ground sewarage system will be provided to connect each residence towards the STP located in Park. STP of 25 KLD will be provided and an outflow line will be connected to external sewer lineon the front road. |
| 7 | Drain covered drain along the roads will be provided, concrete cover blocks will be used to cover drain. |
| 8 | Parks concrete blocks will be used for external boundary . park level will be 0.3 m high from internal road level and various amenities will be provided such as children play area and Gazebo. |
| 9 | Tree Planting palm tree will be provided along the road. Box hedges will be provided along the footpath in park. Hibiscus tree and trabulars Palms will be provided at various locations in Park. Carpet grass of type-4 will be planted along with Marigold and Petunia flower bed |
| 10 | Design For Electric Supply Including Street Lighting we will provide underground electric supply for houses. Street lights will be provided along with road 1 street light placed between 2 correponding units. Transformer of 500 KVA will be provided. |
| 11 | Community Buildings NA |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP of capacity 25 KLD will be provided inside park. Drain outlet from the STP will be connected to the external sewer line on the front road. treated water will also be used for landscaping |
| 13 | Solid Waste Management And Disposal System we will provide garbage collection area separately in Park. |
| 14 | Water Conservation System Rain water harvesting pit will be provided in park . underground recharge pits will be provided to conserve collected water. |
| 15 | Energy Management System Including Use of Renewable Energy NA |
| 16 | Fire Protection And Fire Safety System NA |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services NA |
| 19 | Other Miscellaneous Work NA |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 30 Jun 2030.
Sanctioned by Bareily Development Authority · 8,432 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| PRD/PH/02887/BDA/LD/24-25/0346/11022025 | 1 Jul 2025 | 30 Jun 2030 | 29 Jun 2033 | 31 Mar 2029 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
Land & documents
16 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 116P | 9423.75 | Khasra |
| Sale deed · 12580 The registered deed by which the promoter bought the land. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Registry document · 316 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 430 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 22 Sept 2025 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 22 Sept 2025 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 22 Sept 2025 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 22 Sept 2025 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 22 Sept 2025 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 22 Sept 2025 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 22 Sept 2025 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 22 Sept 2025 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 23 Sept 2025 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 22 Sept 2025 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 10 Oct 2025 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 9 Oct 2025 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 22 Sept 2025 ↗ |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | New | 22 Sept 2025 ↗ |
Quarterly progress reports
4 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
4 quarterly progress reports are on file with UPRERA, covering 2025-Q3 to 2026-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2025-Q3 | 10% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 10% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 10% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Elite Infra Developers and Interiors Private Limited |
| Role | Promoter · current |
| RERA ID | UPRERAPRM383164 |
| PAN | AAHCE6470A |
| CIN / TAN | LKNE07033F |
| Name of chairman | Adit Aneja |
| Registered address | 255 JANAKPURI, BAREILLY up 243122 |
| RERA contact | |
| Registered since | 2025 |
| Legal name | LUCKYBRICK BUILDWELL PRIVATE LIMITED |
| Role | Co-promoter |
| Applicant type | Company |
| Address | 97/98-A, RESIDENCY GARDENS, STADIUM ROAD, BAREILLY UP 243001 |
| RERA contact |
| Legal name | AARAV INFRAPROJECTS LLP |
| Role | Co-promoter |
| Applicant type | Limited Liability Partnership (LLP) |
| Address | AKASH PURAM, PILIBHIT BY PASS ROAD, NEAR SANJAY NARSING HOME, BAREILLY UP 243006 |
| RERA contact |
| Legal name | AMARON DEVELOPERS |
| Role | Co-promoter |
| Applicant type | Partnership Firm |
| Address | 168, Prem Nagar Bareilly UP 243001 |
| RERA contact |
Nearby projects
Bareilly
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | Elite Infra Developers and Interiors Pvt. Ltd. Collection Account For Kings CrestBankCanara BankBranchRajendra NagarBranch addressRajendra Nagar BareillyBranch districtBareillyA/C no.IFSCCNRB0002838Branch emailcb2838@canarabank.com |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | Elite Infra Developers and Interiors Pvt. Ltd. Separate Account For Kings CrestBankCanara BankBranchRajendra NagarBranch addressRajendra Nagar BareillyBranch districtBareilly, Uttar PradeshA/C no.IFSCcb2838canarabank.com |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | Elite infra Developers and Interiors Pvt. Ltd. Rera Transaction account for Kings CrestBankCanara BankBranchRajendra NagarBranch addressRajendra Nagar BareillyBranch districtBareilly, Uttar PradeshA/C no.IFSCcb2838canarabank.com |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Quarterly progress report 2026-Q2 | QPR 2026-Q2 newly filed with RERA | 21 Oct 2026 |
What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about Kings Crest
Is Kings Crest RERA registered?
Yes. Kings Crest is registered with UPRERA under registration number UPRERAPRJ718743, registered on 17 Oct 2025. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for Kings Crest?
The completion date filed with UPRERA is 31 Mar 2029. No completion certificate is on record yet.
Who is the builder of Kings Crest?
Elite Infra Developers and Interiors Private Limited is the promoter entity that filed Kings Crest with UPRERA (promoter RERA ID UPRERAPRM383164). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does Kings Crest have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Kings Crest located?
Kings Crest is registered in Itaua Beniram, Bareilly, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗